SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Gau) 1069

IN THE GAUHATI HIGH COURT HIGH COURT OF ASSAM, NAGALAND, MIZORAM & ARUNACHAL PRADESH)
Mridul Kumar Kalita, J.
 
Indian Oil Corporation (Bongaigaon Refinery) - Appellant
Versus
M/S Esteem Projects Private Limited - Respondent
Arb.A. 18 of 2019
Decided On : 20-04-2026
 

Advocates Appeared:
For the Appellant :Mr. R. Choudhury, Advocate
For the Respondent:Mr. G. N. Sahewalla, Senior Advocate Mr. H. K. Sharma, Advocate

Appellate courts under the Arbitration and Conciliation Act, 1996, refrain from interfering with arbitral awards where the interpretation of contract clauses by the tribunal is plausible, even if an alternative view exists, unless the award is found to be perverse or illegal.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Sections 34 and 37 - Arbitration - Award - Challenge to jurisdiction - Interpretation of contract - Scope of judicial interference - Held, court should not interfere with an award merely because an alternative view on facts and interpretation of contract exists - Courts need to be cautious and should defer to the view taken by the arbitral tribunal unless the award portrays perversity unpardonable under the Act. (Paras 39-41)

(B) Appeal - Appellate jurisdiction - Court sitting in appeal is not to substitute its view for that of court below regarding interpretation of terms - Interference is limited to cases where decision is afflicted by perversity or illegality - Where two views are possible, the view taken by the tribunal should be respected. (Paras 39-40)

Facts of the case:
The dispute arose from a construction contract where the employer deducted liquidated damages for alleged delays. The contractor challenged this deduction in arbitration. The employer argued the tribunal lacked jurisdiction because the dispute was not "notified" according to specific contractual conditions. The lower court upheld the arbitral award, leading to the present appeal.

Findings of Court:
The court found that the tribunal's interpretation regarding the notification of claims was plausible under the circumstances, particularly because the damage deduction occurred well after the final bill submission. The court held that such an interpretation cannot be deemed perverse or unreasonable.

Issues: Whether the arbitral tribunal correctly assumed jurisdiction over the dispute despite the absence of a formal notification of the claim, and whether the appellate court was justified in refusing to set aside the arbitral award.

Ratio Decidendi: Judicial interference in arbitral awards is highly circumscribed. When an arbitral tribunal adopts a plausible and reasonable interpretation of contract clauses, the reviewing court must uphold the award, as it cannot function as an appellate authority substituting its own interpretation for that of the specialized forum.

Result: Appeal dismissed.

Table of Content
1. procedural history and factual foundation of the arbitral dispute. (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15)
2. appellant's contention regarding lack of arbitral jurisdiction due to non-notified claims under gcc clauses. (Para 16 , 17 , 18 , 19 , 20 , 21)
3. respondent's argument on the limited scope of judicial interference under section 34/37 of the arbitration act. (Para 22 , 23 , 24 , 25 , 26 , 27 , 28 , 29)
4. court's interpretation of gcc clauses governing notified vs. non-notified claims in arbitral disputes. (Para 30 , 31 , 32 , 33 , 34 , 35 , 36 , 37)
5. limited scope of appellate review where the arbitral tribunal's interpretation is plausible and non-perverse. (Para 38 , 39 , 40 , 41)
6. final dismissal of appeal and affirmation of the arbitral award. (Para 42 , 43 , 44)

JUDGMENT :

MRIDUL KUMAR KALITA, J.

1. Heard Mr. R. Choudhury, the learned counsel for the appellant. Also heard Mr. G. N. Sahewalla, the learned senior counsel assisted by Mr. H. K. Sharma, the learned counsel for the respondent.

2. This appeal under Section 37 (1) (c) of the Arbitration and Conciliation Act, 1996 has been filed by the appellant, namely, Indian Oil Corporation (Bongaigaon Refinery), impugning the judgment and order dated 26.02.2019 passed by the Court of the learned District Judge, Chirang, Kajalgaon, in Misc. (Arbitration) Case No.18/2016, whereby the application filed by the appellant under Section 34 of the Arbitration and Conciliation Act, 1996 for setting aside the arbitral award dated 28.04.2016 was dismissed.

3. The facts relevant for consideration of the instant appeal, in brief, are that the respondent herein was found as the successful bidder in a tender floated by the appellant for the work of “Heater package for the DHDT (Diesel Hydro- Treater) project”, Dhaligaon, Assam. The Letter of Intent (LOI) in respect of the work order No.2007/PC-1234 was issued in favor of the respondent on 16.08.2007. The letter of acceptance (LOA) was issued on 29.07.2007. The lump sum contract value of the work to be carried out by the respondent was USD 17,80,000/- (USD Seventeen Lakh Eighty Thousand Only) plus Rs. 18,72,20,000/- (Rupees Eighteen Crore Seventy-Two Lakh Twenty Thousand Only). The commencement date of the said contract was 16.08.2007 and the date of completion was 13 months from the date of LOI i.e., on 15.09.2008. However, the work was completed by the respondent on 10.08.2011, after a delay of 1059 days in completing the contract work.

4. The respondent, after completion of the work, by letter dated 07.12.2011, sought extension of time for completion of work up to 10.08.2011. The appellant by its letter dated 20.08.2014, informed the respondent of the approval of competent authority regarding allowing extension of time up to 10.08.2011 to complete the work in question with imposition of Liquidated Damages (LD) amounting to 10% of the total contract value as per Clause 4.4.0.0 of the General Conditions of Contract (GCC). The LD amount was estimated at Rs. 2,59,57,700/- (Rupees Two Crore Fifty Nine Lakh Fifty Seven Thousand Seven Hundred only).

5. It is pertinent to mention herein that the respondent submitted the final running account bill on 19.04.2012 for an amount of Rs. 23,27,946/- (Rupees Twenty Three Lakh Twenty Seven Thousand Nine Hundred Forty Six only).

6. Against the decision of the appellant regarding the deduction of the LD, the respondent initiated arbitration proceedings by filing statement of claims dated 10.09.2014 before the Indian Council of Arbitration (ICA) with following claims –

(i) Amount due under RA Bill No. 24 dated 19.04.2012 of Rs. 23,27,946/-;

(ii) Reimbursement of legal fees for opinion on procedure for post facto clearance and job work for imported material for Rs. 22,000/-;

(iii) Reimbursement of demurrage/cost incurred on imported dues for Rs. 22,80,109/-;

(iv) Additional cost incurred towards air freight on imported tubes;

(v) Fluctuation in exchange rate for Rs.

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top