SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Ker) 3168

IN THE HIGH COURT OF KERALA AT ERNAKULAM
S. MANU, J.
M/s. P.K. Chandrasekharan Nair & Co. – Appellant
Versus
M/s. Hindustan Petroleum Corporation Limited – Respondent
A.R. No. 96 of 2025
Decided On : 26-11-2025

Advocates Appeared:
For the Appellants : Reji George, Joseph Raju Mathews, Saisankar S.
For the Respondents: M. Gopikrishnan Nambiar, K. John Mathai, Joson Manavalan, Kuryan Thomas, Paulose C. Abraham, Raja Kannan, Nayanpally Ramola, Pooja Menon, E.K. Nandakumar

A partner cannot submit a dispute to arbitration without express authority from all partners, as required by Section 19(2)(a) of the Indian Partnership Act.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 11(6) - Indian Partnership Act, 1932 - Section 19(2)(a) - The maintainability of the arbitration request is challenged on the grounds of lack of express authority from one partner to represent the firm in arbitration. The Court emphasized that the authority to submit disputes to arbitration must be expressly conferred per Section 19(2)(a), and the lack of consent from the other partner renders the request inadmissible. (Paras 17-28)

(B) Legal authority of partners - Implied authority of a partner to bind the firm does not extend to submission of disputes to arbitration, requiring express consent from all partners in absence of customs to the contrary. (Paras 17-20)

(C) Judicial interpretation - The Court may examine the maintainability of an application under Section 11(6), particularly in cases where statutory provisions are contravened. (Paras 16-28)

Facts of the case:
The petition relates to the arbitration request by one partner of a firm against the respondent, alleging breach of partnership agreement related to running a petroleum outlet. A notice invoking arbitration was issued by one partner without the other’s consent.

Findings of Court:
The arbitration request was dismissed for lack of maintainability due to absence of express authority from both partners, as stipulated by Section 19(2)(a) of the Indian Partnership Act.

Issues: Whether one partner can submit a dispute to arbitration without the consent of the other partner under Section 19(2)(a) of the Indian Partnership Act.

Ratio Decidendi: The Court held that Section 19(2)(a) explicitly requires consent from all partners for arbitration requests, making the request by one partner inadmissible.

Result: Arbitration request dismissed as not maintainable.

Table of Content
1. establishment of the firm and initial agreements. (Para 1 , 2 , 3 , 4)
2. respondent's denial and maintainability objections. (Para 5 , 8 , 10)
3. court's examination of maintainability. (Para 6 , 7 , 9)
4. arbitration and validity of disputes. (Para 11 , 12 , 13 , 14 , 15)
5. issues of implied authority in arbitration. (Para 16 , 17 , 18 , 19)
6. analysis of previous judgments on authority. (Para 20 , 21 , 22 , 23)
7. final ruling on maintainability of the request. (Para 24 , 25 , 26 , 27 , 28)

ORDER :

1. This arbitration request is filed by a partner of M/s.P.K.Chandrasekharan Nair and Co., a partnership firm, in its name. It is stated that the firm was a dealer of the respondent since 1970. The firm was operating a retail outlet of petroleum products of the respondent in the property having an extent 39.620 cents in Survey No.931/1 of Nadama Village owned by Mr.N.Krishnan. An agreement was executed between the firm and the respondent in 1970 which was renewed periodically. Last renewal was on 01.07.2019. A copy of the agreement dated 01.07.2019 is produced as Annexure 1.

2. In 2013, the land owner filed O.S.293 of 2013 before the Sub Court, Ernakulam, for recovery of possession of property and other reliefs against the respondent and the then Managing Partner of the firm. Suit was dismissed and dispute was referred for arbitration as there was an arbitration clause in the lease deed between the respondent and the land owner. After filing of the suit, the land owner refused to renew the lease and to give consent for renewing the explosive licence. The outlet was therefore closed from 21.02.2021. Dispute between the respondent and the land owner was referred for arbitration. While so, the land owner filed C.S.No.80 of 2022 before the Commercial Court, Ernakulam, against the respondent and the then Managing Partner of the firm for compensation for unauthorized occupation after the expiry of the lease. The suit was dismissed for default on 30.08.2022.

3. On 29.06.2022 the respondent sent Annexure 2 letter instructing the firm to find alternate site due to pending litigation. Annexure 3 reply was sent seeking time to sort out the matter and to find alternate site. Later the respondent allowed another dealer to start a new retail outlet on the premises. W.P(C)No.8797 of 2024 was filed aggrieved by the said action. Respondent entered appearance and submitted that a fresh dealership agreement was entered into by it with another dealer. Therefore, the said dealer was impleaded. He produced a copy of the agreement between him and the respondent.

4. It is contended that as per Annexure 1 agreement, the firm was entitled to run the retail outlet for a period of 10 years ending on 30.06.2029. Therefore, it is alleged that the action of the respondent in entering into agreement with another dealer is in breach of Annexure 1 agreement. Annexure 4 is a notice issued to the respondent calling upon to pay a sum of Rs.2,51,60,000/- as damages. There was no response to the notice. Subsequently, Annexure 5 notice dated 19.02.2025 was issued invoking the arbitration clause in Annexure 1 agreement for initiating arbitration. A former Judge of this Court was nominated as the arbitrator. However, no response was received from the respondent and hence the arbitration request was filed.

5. Respondent filed counter affidavit. Allegations in the arbitration request against the respondent are denied in the counter affidavit. Respondent has produced a copy of the partnership agreement as Annexure A, pointing out that Mr.Anilkumar K.C. and Mrs.Ganga Sreekumar were the partners of M/s.P.K.Chandrasekharan Nair and Co. Mr.Anilkumar K.C. holds 51% of the partnership and 49% of the partnership was held by Mrs.Ganga Sreekumar. Respondent states that this arbitration request is not maintainable in view of the specific bar contained in Section 19(2)(a) of the Indian Partnership Act, 1932. Further the respondent states that no express authority was given by

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top