SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2023 Supreme(Raj) 328

IN THE HIGH COURT OF JUDICATURE FOR RAJASTHAN AT JODHPUR
Arun Bhansali, J.
M/s Kamla Construction Company - Petitioner
Versus
Rajasthan Rajya, District Collector, Bikaner - Respondent
S.B. Arbitration Application No. 21 of 2020
Decided On : 10-02-2023

Advocates:
Advocate Appeared:
For the Petitioner: Mr. Pradeep Choudhary.
For the Respondent: Mr. Saransh Vij for Mr. Sudhir Tak, AAG.

Point of Law: Court should only look into existence of arbitration agreement before making reference, nothing more, nothing less.

Headnote:

Arbitration and Conciliation Act, 1996 - Section 10 and 11 - Limitation Act, 1963 - Article 137 - Right to Information Act, 2005 - Arbitrator - Dispute between parties - Application seeking reference of dispute between parties to Arbitrator – Applicant has admittedly sought reference of dispute after 22 years.

Finding of the Court :

Application as well as in notice has made reference to certain deaths in family and illness of partner, necessarily leads to conclusion that applicant himself being aware of huge delay somehow wants to explain same, which aspect is of no consequence insofar as claim getting barred by limitation is concerned - As applicant has admittedly sought reference of dispute after 22 years, claim is ex-facie barred by limitation and there apparently was no subsisting dispute between parties - As claims of applicant are ex-facie time barred and there is no subsisting dispute.

Result: Application dismissed.

ORDER :

1. This application under Section 10 and 11 of the Arbitration and Conciliation Act, 1996 (‘the Act’) has been filed by the applicant seeking reference of dispute between the parties to Arbitrator.

2. It is inter alia indicated that the applicant was issued a work order dated 1.1.1996 for manufacture and supply of 20 lakh first class bricks and an agreement No.7/1995-1996 was executed in this regard. As per the order and contract, the work was to commence from 16.1.1996 and was to be concluded in 12 months i.e. by 15.1.1997.

3. It is claimed that the applicant earnestly commenced implementation of the work order and supplied 20 lakh bricks by 31.10.1996, however, another order dated 31.10.1996 was issued to the applicant for supply of additional 20 lakh bricks and based on the said quantity, it was expected that the contract would be extended till 15.1.1998.

4. It is then indicated in the application that for various reasons on account of rains etc. instead of 40 lakh bricks, the applicant was required to manufacture 45.50 lakh bricks, however, the applicant was not made full and final payment by the respondents in terms of Clause-10(a) of the agreement. It is claimed that on account of delayed payment, the applicant is entitled for interest on the outstanding payment.

5. It is then indicated that in terms of Clause-19 of the agreement, any question, difference or objection in connection with the agreement was to be referred to a sole arbitrator to be appointed as per the procedure prescribed, based on which, the applicant issued a notice dated 5.3.2020, however, as the respondents have not followed the procedure prescribed under Clause-19, they have lost the right to appoint arbitrator and, therefore, a sole arbitrator be appointed.

6. A reply to the application has been filed by the respondents inter alia with the submissions that the petitioner did not complete the work in the stipulated time period i.e. 31.3.1997 and there was a delay of more than a year in execution of the work order and, therefore, the petitioner is not entitled to any relief.

7. Further submissions have been made that the applicant was lying in the state of slumber as the dispute pertains to the year 1998 and the present application has been filed in 2020 after issuing notice. The claim made is ex-facie barred by limitation even as per Article 137 of the Limitation Act, 1963 and, therefore, the application deserves dismissal.

8. No rejoinder to the reply has been filed.

9. Learned counsel for the applicant made submissions that the claim made by the applicant is genuine, wherein, the respondents have not made payment of huge outstanding amount to the applicant and not only this, even the final bill has not been prepared and, therefore, the plea raised pertaining to the claim being barred by limitation has no substance. It was emphasized that as the final bill has not been prepared so far, it cannot be said that the claim is barred by limitation so as to seek dismissal.

10. Further submissions have been made that it is well settled that the issue pertaining to the limitation has to be considered by the arbitrator and this Court while examining the matter under Section 11 of the Act, cannot determine the aspect of limitation.

11. Reference in this regard has been made to judgments in Duro Felguera. S.A. v. Gangavaram Port Limited: (2017) 9 SCC 729 and M/s. Jai Shiv Construction Company v. State of Rajasthan & Ors.: S.B. Arbitration Application No.19/2019, decided on 21.7.2022.

12. Learned counsel for the respondent made submissions that in case where the claim made is ex-facie time barred and it is manifest that there is no subsisting dispute, the Court can refuse to make the reference under Section 11 of the Act.

13. Reliance has been placed on judgment in Bharat Sanchar Nigam Limited & Anr. v. Nortel Networks India Private Limited: (2021) 5 SCC 738.

14. I have considered the submissions made by learned counsel for the parties and have perused the material ava

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top