IN THE HIGH COURT OF JUDICATURE FOR RAJASTHAN AT JODHPUR
PUSHPENDRA SINGH BHATI, J.
M/s. Kailash Chand Gian Chand Jain, Through Its Proprietor Gian Chand Jain - Petitioner
Versus
Union Of India, Through General Manager North Western Railway and Ors. – Respondents
S.B. Arbitration Application No. 35 Of 2018
Decided On : 16-08-2023
Arbitration and Conciliation Act, 1996 - Section 11(6) - Arbitration application - Claiming reliefs - Demand for Arbitration - Requirement for mediation - Held, Court also observes that on issue of limitation, so raised, due assistance has been rendered not only on behalf of respondent herein, but also by other Members of Bar (including Senior Advocates and Additional Advocate General) , who furnished before this Court precedent laws governing issue, which enabled this Court to deal with said issue in an appropriate manner during present adjudication - However, while identical arbitration applications, on earlier occasions, were being heard, precedent laws on issue of limitation, as furnished herein, were not placed before this Court, and thereafter, issue of limitation was left to be adjudicated by arbitrator, which does not seem to be in conformity with precedent law cited at Bar - Application dismissed.
JUDGMENT :
1. The instant arbitration application has been filed by the applicant-Firm under Section 11(6) of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as ‘Act of 1996’) claiming the following reliefs:-
Any other order, which may kindly be deem, fit and proper may kindly be passed in favour of the petitioner.”
2. The respondents issued the tender for civil works pertaining to zone-II, i.e. filing, cutting, widening, raising etc. from KM 1/0 to KM 50/0 in c/w gauge conversion project of Jodhpur-Jaisalmer. The contract was executed between the applicant and the respondent no.2 on 20.09.1994. The tentative date for completion of the work was stipulated as 11.01.1995, but after extension, the work in question was completed on 31.05.1996, and that, the respondent no.4 vide letter dated 22.02.1997 issued the satisfactory performance certificate.
2.1 The final bill has been paid on 17.11.1998 after certain deductions; the said final final bill was signed ‘Under Protest’ by the applicant, but vide letter dated 23.06.1999 it was impressed upon the applicant to withdraw the said remark i.e. “Under Protest”; the applicant suggested that it shall withdraw such remark, subject to the condition that the respondent-Department shall make the complete payment as demanded vide letter (Annexure-5) issued in the month of July, 1999, but the said request was not considered by the respondent-Department. Thereafter, the applicant, for the first time on 16.11.2000, made a request for appointment of an Arbitrator.
2.2 The applicant also served a representation 07.11.2011 for invocation of the arbitration clause 64 of General Conditions of Contract (GCC), 1989, and for referring the dispute for arbitration.
The applicant also preferred a civil writ petition (S.B.C.W.P. No. 5400/2012) before this Hon’ble Court, but the same was dismissed as withdrawn on 01.05.2018 with liberty to file an arbitration application.
3. Learned counsel for the applicant submitted that there is an existing arbitration agreement alongwith the present application, which contained an arbitration clause, and the same is sufficient for referring the dispute for arbitration.
3.1. The Arbitration Clause 64 of the GCC is reproduced as hereunder :
64(1)(ii) – The demand for arbitration shall specify the matters which are in question or subject of the dispute or difference as also the amount of claim itemwise. Only such dispute(s) or difference(s) in respect of which the demand has been made together with counter claims or set off shall be referred to arbitration and other matters shall not be included in the reference.
64(1)(ii)(a)-the Arbitration proceeding shall be assumed to have commenced from the day, a written and valid demand for arbitration is received by the Railway.
(b) The claimant shall submit his claim stating the facts supporting the claim alongwith all relevant documents and the relief or remedy sought after each
B and T AG Vs. Ministry of Defence, Arbitration Pertition (C) No.13 of 2023
M/s Kamla Construction Company Vs Rajasthan Rajya, S.B. Arbitration Application No. 21/2020
The main legal point established in the judgment is that an application for appointment of an arbitrator under Section 11 of the Arbitration and Conciliation Act, 1996 is subject to the time limitati....
The main legal point established in the judgment is that the limitation for filing an application under Section 11 of the Arbitration Act arises upon the failure to make the appointment of the arbitr....
The main legal point established in the judgment is that the limitation period for filing an application seeking appointment of an arbitrator under Section 11(6) of the Arbitration and Conciliation A....
(1) Period of limitation to file application under Section 11 of Arbitration and Conciliation Act, 1996 is 3 years’ from date of refusal to appoint Arbitrator, or on expiry of 30 days’, whichever is ....
An application under Section 11 for appointment of an arbitrator is time-barred if filed after three years from the refusal to appoint, with delays not justified.
Arbitration requests must be filed within three years of the cause of action; failure to act in time bars subsequent petitions.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.