SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2024 Supreme(Raj) 525

IN THE HIGH COURT OF JUDICATURE FOR RAJASTHAN AT JODHPUR
REKHA BORANA, J.
M.M. Enterprises through its Partner Shri Mohammad Majhar S/o Late Shri Abdul Vahid – Appellant
Versus
Hindustan Zinc Ltd. – Respondent
S.B. Arbitration Application No. 20 of 2023
Decided on : 09-04-2024

Advocates Appeared:
For the Appellant : Mr. Siddharth Mandawat
For the Respondent: Mr. Punit Singhvi through VC

IMPORTANT POINT
The limitation period for filing an application under Section 11(6) of the Arbitration and Conciliation Act, 1996 is governed by Article 137 of the Limitation Act, and the claims must be alive at the time of invoking arbitration, with the period of limitation potentially extended due to exceptional circumstances such as the COVID-19 pandemic.

Headnote:

ARBITRATION - APPOINTMENT OF ARBITRATOR - Arbitration and Conciliation Act, 1996, Section 11(6); Limitation Act, 1963, Article 137 - The court discussed the applicability of Section 11(6) of the Arbitration and Conciliation Act, 1996, which allows for the appointment of an arbitrator when a party invokes the arbitration clause and the other party fails to respond. The court also interpreted Article 137 of the Limitation Act, which governs the limitation period for applications under Section 11, establishing that the limitation period begins when the right to apply accrues. The court concluded that the application for arbitration was within the limitation period, considering the exclusion of time due to the COVID-19 pandemic as per the Supreme Court's directive.

Fact of the Case:

The contractor entered into a work order with the Company for material handling and bagging services, which was terminated prematurely. Disputes arose over unpaid amounts and the termination of the contract, leading the contractor to invoke the arbitration clause after the Company denied their claims. The contractor filed an application for the appointment of an arbitrator after the Company failed to respond to the notice invoking arbitration.

Finding of the Court:

The court found that the application for the appointment of an arbitrator was within the limitation period. It ruled that the claims were not time-barred, as the period of limitation was extended due to the COVID-19 pandemic, and the claims were alive at the time of invoking arbitration.

Issues: Whether the application for the appointment of an arbitrator is within the limitation period and whether the claims sought to be referred to arbitration are time-barred.

Ratio Decidendi: The court applied the principles from the Supreme Court's judgments regarding the limitation period for arbitration applications, establishing that the limitation period begins when the right to apply accrues and that the claims must not be ex facie time-barred at the time of invoking arbitration.

Final Decision: The application under Section 11(6) of the Arbitration and Conciliation Act, 1996 was allowed, and Shri Shiv Singh Chouhan was appointed as the sole arbitrator to adjudicate the disputes between the parties.

ORDER :

REKHA BORANA, J.

1. The present application under Section 11(6) of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as ‘the Act of 1996’) has been preferred for appointment of an independent and impartial sole arbitrator.

2. The facts as submitted are as under:

    (i) The applicant company (hereinafter referred to as ‘the contractor’) was into a transportation business and vide office order dated 29.01.2013, a work order bearing No.HZ12SLK211/5100013067 for “Zinc Smelter Debari Material Handling in Roaster-3 and Bagging of Calcine into bags, Loading into trucks at R&A Plant” was issued in its favour by non-applicant (hereinafter referred to as ‘the Company’) pursuant to its Notice Inviting Tender having finalised in favour of the contractor.

(ii) As per the work order, 3,12,000 M.T. work was to be carried out every year and 90% of the said completed work i.e. 2,80,000 M.T. was payable. But, an amount for only 2,65,000 M.T. work was paid to the contractor which became one of the causes of dispute between the parties.

(iii) The work order was stipulated for a period of three years i.e. from 01.02.2013 to 31.01.2016 but the same was terminated four months prior to the stipulated date of completion. As the contractor had spent substantial amount in collecting the assets so as to ensure the completion of contract as per the requirements of the Company, because of the termination of the contract prior to its stipulated period, it suffered huge losses and also suffered loss of profit which it could have gained, if it would have been permitted to complete the work. The same too became a cause of dispute between the parties.

(iv) The non-payment of amount qua the extra work got completed by the contractor and further, the extension of maintenance period to 30-45 days, instead of 15 days as agreed upon, also became the cause of dispute.

(v) Qua the unpaid amounts and losses occurred, a demand notice dated 02.04.2018 was served by the contractor on the Company requesting for the payment of the same. However, the same was denied by the Company and hence, as the agreement entered into between the parties contained an arbitration clause, vide notice dated 01.04.2022, the same was invoked by the contractor. Vide the notice, the Company was called upon to appoint an arbitrator in terms of the arbitration clause for resolution of the disputes as arisen between the parties.

(vi) The notice dated 01.04.2022 having not been responded to/acted upon, the present application under Section 11(6) of the Act of 1996 was preferred on 11.08.2023.

3. A reply to the application has been preferred on behalf of the Company raising a preliminary objection to the effect that the present application is barred by limitation and hence, deserves to be dismissed. It has been submitted that admittedly the demand notice was served in the year 2018 whereas the notice invoking arbitration clause was issued on 01.04.2022 i.e. after a period of more than 3 years and hence, was clearly barred by limitation.

(ii) Regarding the termination of the contract before the stipulated date, it has been submitted that the same was permissible as per clause 14.3 of the agreement and hence, cannot be said to be a cause of any dispute.

4. Learned counsel for the non-applicant Company while submitting the preliminary objection on the issue of the limitation relied upon the Hon’ble Apex Court judgment in the case of Bharat Sanchar Nigam Limited and Others Vs. Nortel Networks India Private Limited, (2021) 5 SCC 738, wherein it has been held that the period of limitation for issuing notice of arbitration would not get extended by mere exchange of letters. Sections 5 to 20 of the Limitation Act do not exclude the time taken on account of settlement discussions. The Hon’ble Apex Court further held that where once the time has begun to run, no subsequent disability or inability to institute a suit or make an application stops it. There must be a clear notice invoking arbitration

          Click Here to Read the rest of this document
          1
          2
          3
          4
          5
          6
          7
          8
          9
          10
          11
          SupremeToday Portrait Ad
          supreme today icon
          logo-black

          An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

          Please visit our Training & Support
          Center or Contact Us for assistance

          qr

          Scan Me!

          India’s Legal research and Law Firm App, Download now!

          For Daily Legal Updates, Join us on :

          whatsapp-icon Back to top