IN THE HIGH COURT OF JUDICATURE FOR RAJASTHAN AT JODHPUR
REKHA BORANA, J.
M.M. Enterprises through its Partner Shri Mohammad Majhar S/o Late Shri Abdul Vahid – Appellant
Versus
Hindustan Zinc Ltd. – Respondent
S.B. Arbitration Application No. 20 of 2023
Decided on : 09-04-2024
ARBITRATION - APPOINTMENT OF ARBITRATOR - Arbitration and Conciliation Act, 1996, Section 11(6); Limitation Act, 1963, Article 137 - The court discussed the applicability of Section 11(6) of the Arbitration and Conciliation Act, 1996, which allows for the appointment of an arbitrator when a party invokes the arbitration clause and the other party fails to respond. The court also interpreted Article 137 of the Limitation Act, which governs the limitation period for applications under Section 11, establishing that the limitation period begins when the right to apply accrues. The court concluded that the application for arbitration was within the limitation period, considering the exclusion of time due to the COVID-19 pandemic as per the Supreme Court's directive.
Fact of the Case:
The contractor entered into a work order with the Company for material handling and bagging services, which was terminated prematurely. Disputes arose over unpaid amounts and the termination of the contract, leading the contractor to invoke the arbitration clause after the Company denied their claims. The contractor filed an application for the appointment of an arbitrator after the Company failed to respond to the notice invoking arbitration.
Finding of the Court:
The court found that the application for the appointment of an arbitrator was within the limitation period. It ruled that the claims were not time-barred, as the period of limitation was extended due to the COVID-19 pandemic, and the claims were alive at the time of invoking arbitration.
Issues: Whether the application for the appointment of an arbitrator is within the limitation period and whether the claims sought to be referred to arbitration are time-barred.
Ratio Decidendi: The court applied the principles from the Supreme Court's judgments regarding the limitation period for arbitration applications, establishing that the limitation period begins when the right to apply accrues and that the claims must not be ex facie time-barred at the time of invoking arbitration.
Final Decision: The application under Section 11(6) of the Arbitration and Conciliation Act, 1996 was allowed, and Shri Shiv Singh Chouhan was appointed as the sole arbitrator to adjudicate the disputes between the parties.
ORDER :
REKHA BORANA, J.
1. The present application under Section 11(6) of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as ‘the Act of 1996’) has been preferred for appointment of an independent and impartial sole arbitrator.
2. The facts as submitted are as under:
(ii) As per the work order, 3,12,000 M.T. work was to be carried out every year and 90% of the said completed work i.e. 2,80,000 M.T. was payable. But, an amount for only 2,65,000 M.T. work was paid to the contractor which became one of the causes of dispute between the parties.
(iii) The work order was stipulated for a period of three years i.e. from 01.02.2013 to 31.01.2016 but the same was terminated four months prior to the stipulated date of completion. As the contractor had spent substantial amount in collecting the assets so as to ensure the completion of contract as per the requirements of the Company, because of the termination of the contract prior to its stipulated period, it suffered huge losses and also suffered loss of profit which it could have gained, if it would have been permitted to complete the work. The same too became a cause of dispute between the parties.
(iv) The non-payment of amount qua the extra work got completed by the contractor and further, the extension of maintenance period to 30-45 days, instead of 15 days as agreed upon, also became the cause of dispute.
(v) Qua the unpaid amounts and losses occurred, a demand notice dated 02.04.2018 was served by the contractor on the Company requesting for the payment of the same. However, the same was denied by the Company and hence, as the agreement entered into between the parties contained an arbitration clause, vide notice dated 01.04.2022, the same was invoked by the contractor. Vide the notice, the Company was called upon to appoint an arbitrator in terms of the arbitration clause for resolution of the disputes as arisen between the parties.
(vi) The notice dated 01.04.2022 having not been responded to/acted upon, the present application under Section 11(6) of the Act of 1996 was preferred on 11.08.2023.
3. A reply to the application has been preferred on behalf of the Company raising a preliminary objection to the effect that the present application is barred by limitation and hence, deserves to be dismissed. It has been submitted that admittedly the demand notice was served in the year 2018 whereas the notice invoking arbitration clause was issued on 01.04.2022 i.e. after a period of more than 3 years and hence, was clearly barred by limitation.
(ii) Regarding the termination of the contract before the stipulated date, it has been submitted that the same was permissible as per clause 14.3 of the agreement and hence, cannot be said to be a cause of any dispute.
4. Learned counsel for the non-applicant Company while submitting the preliminary objection on the issue of the limitation relied upon the Hon’ble Apex Court judgment in the case of Bharat Sanchar Nigam Limited and Others Vs. Nortel Networks India Private Limited, (2021) 5 SCC 738, wherein it has been held that the period of limitation for issuing notice of arbitration would not get extended by mere exchange of letters. Sections 5 to 20 of the Limitation Act do not exclude the time taken on account of settlement discussions. The Hon’ble Apex Court further held that where once the time has begun to run, no subsequent disability or inability to institute a suit or make an application stops it. There must be a clear notice invoking arbitration
Bharat Sanchar Nigam Limited and Others Vs. Nortel Networks India Private Limited
C. Budhraja v. Chairman, Orissa Mining Corporation Ltd.
Major (Retd.) Inder Singh Rekhi v. DDA [(1988) 2 SCC 338]
Panchu Gopal Bose v. Board of Trustees for Port of Calcutta [(1993) 4 SCC 338]
Utkal Commercial Corporation. v. Central Coal Fields Ltd. [(1999) 2 SCC 571]
The limitation period for filing an application under Section 11(6) of the Arbitration and Conciliation Act, 1996 is governed by Article 137 of the Limitation Act, and the claims must be alive at the....
The main legal point established in the judgment is the application of the Limitation Act, 1963 to arbitration proceedings and the significance of acknowledging claims to extend the period of limitat....
An application under Section 11 for appointment of an arbitrator is time-barred if filed after three years from the refusal to appoint, with delays not justified.
Arbitration requests must be filed within three years of the cause of action; failure to act in time bars subsequent petitions.
The appointment of an Arbitrator should proceed if there is doubt about the subsistence of the disputes, and objections regarding claims should be left to be determined by the Arbitrator.
The Arbitration and Conciliation Act requires strict adherence to limitation periods for the appointment of arbitrators; delays exceeding three years render petitions ex-facie time-barred.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.