IN THE HIGH COURT OF JUDICATURE FOR RAJASTHAN BENCH AT JAIPUR
SAMEER JAIN, J.
Jaipur Vidhyut Vitran Nigam Limited – Appellant
Versus
Office Of Electricity Ombudsman, Rajasthan – Respondent
S.B. Civil Writ Petition No. 3840 of 2016
Decided on : 30-05-2023
Constitution of India, 1949 - Article 226 - Electricity Act, 2003 - Section 42, 62, 64, 45, 181, 43, 48, 50, 55, 56 - Rajasthan Electricity Regulatory Commission in Electricity Supply Code and Connected Matters (Eleventh Amendments) Regulations, 2017 - Arbitration & Conciliation Act, 1996 - Section 34 - Indian Contract Act, 1872 - Sections 3, 8, and 39 - Power of High Court tp issue certain writs - Extension of contract demand - Writ petitions are filed by petitioner assailing different orders passed by Electricity Ombudsman issue before EO was regarding recovery of transformation losses consumers who were falling category of Large Industries - Held, Orders of EO are liable to grounds of delay laches, acquiescence probate reprobate respondent-customers acquiesced terms conditions imposed paying due amount substantially case - Court has held levy of cost pro rata cost of transformer and transformation losses prior valid legal case of National Engineering Industries Limited - Court occasion to consider similar controversy in case consideration of controversy Court also reached to a similar conclusion relevant part of which is reproduced - Application disposed of.
JUDGMENT :
1. All these writ petitions are filed by the petitioner Discom-Jaipur Vidyut Vitran Nigam Limited (for short “JVVNL”) assailing different orders passed by the Electricity Ombudsman, Rajasthan (for short “EO”). The issue before the EO was regarding recovery of transformation losses (at 3%) and cost/pro-rata cost of EHV Transformer, from the consumers who were falling under the category of ‘Large Industries’, on allowing increase in contract demand at lower voltage than the prescribed level of supply of voltage according to their contract demand. For reference, the prescribed voltage level for various categories of load is reproduced as under:
| Category of Consumer | Character of services | |
| g) Large Industrial (except Railway Traction) | Contract Demand | Voltage of Supply |
| i) Connected Load above 112 kW (150 HP) and/or contract/actual demand above 125 kVA but up to 1500 kVA | i) HT 11 kV | |
| ii) Contract/actual demand is above 1500 kVA but up to 5000 kVA | ii) HT 33 kV | |
| iii) Contract/actual demand above 5000 kVA | iii) EHT 132 kV or 220 kV | |
…
(v) The Nigam may allow supply to a consumer at a voltage level one stage higher or lower in exceptional circumstances.”
2. Admittedly, all the consumers/applicants before the EO were large industrial consumers of electricity who were receiving voltage supply one stage lower than the prescribed load after their application for extension of contract demand was accepted. Since the supply was on one stage lower, which was only permissible in exceptional circumstances, the Discom was levying a charge of 3% as transformation losses and cost/pro rata cost of the transformer. The said levy was challenged by the consumers and the EO held the said levy to be without authority of law.
3. As common question of law is involved in all these writ petitions, with consent of the parties, they were all heard together and are now being decided by way of this common order.
FACTS/BACKGROUND:
4. The facts of the case, as per learned counsel for the petitioner-Discom, are as follows: 4.1) In SB Civil Writ Petition No.8753/2013, it is submitted that prior to 17.04.2006, the respondent-consumer was having a contract demand of 2600 KVA and accordingly its voltage supply was HT-33 KV. On 17.04.2006, the respondent-consumer applied for load extension from 2600 KVA to 6000 KVA with further request to sanction the same on lower load extension of 33 KVA power supply line instead of prescribed 132 KVA power supply line. On 19.05.2006, the application of the consumer was accepted with condition that respondent-consumer would be liable to pay the transformation losses charged @ 3% of total recorded consumption and with the condition that the respondent-consumer would also bear pro rata cost of EHP transformer above contract demand of 5000 KVA. Subsequently, the demand notice was accepted without protest and accordingly 3% transformation losses were being added and recovered from time to time. On 05.03.2007, respondent-consumer again applied for extension of load from 6000 KVA to 7000 KVA on 132 KV line but the said demand was refused by petitioner-Discom on 31.07.2007 due to non-availability of right of way. In the meanwhile, on 26.05.2007, respondent-consumer made another application for extension of contract demand from 6000 KVA to 6600 KVA on 33KV line. On 20.06.2007, the said application for extension was accepted and the contract demand of the respondent-consumer was increased to 6600 KVA on the 33KV line with the condition of 3% transformation losses over and above 5 MVA. The said practice continued till 2012 and it was only in October, 2012 that for the very first time, the respondent-consumer approached the Corporate Level Redressel Committee (for short “CLRC”) under Section 42(5) of the Electricity Act, 2003 (for short “Act of 2003”) alleging that levy of 3% transform
Sri Babu Ram Alias Durga Prasad v. Sri Indra Pal Singh (Dead) by L.Rs.: AIR 1998 SC 3021
P.R. Deshpande v. Maruti Balram Haibatti: AIR 1998 SC 2979
State of West Bengal and Ors. vs. Vishnunarayan and Associates (P) Ltd. and Ors.: (2002) 4 SCC 134
Bishan Das and Ors. vs. The State of Punjab and Ors.: AIR 1961 SC 1570
Harla vs. The State of Rajasthan: AIR 1951 SC 467
State of Punjab vs. Amar Singh Haruka: AIR 1966 SC 1313;
Maharashtra State Road Transport Corporation v. Balwant Regular Motor Service
R.N. Gosain v. Yashpal Dhir: AIR 1993 SC 352
State of Punjab and Ors. vs. Dhanjit Singh Sandhu: (2014) 15 SCC 144
Union of India (UOI) and Ors. vs. N. Murugesan and Ors.: (2022) 2 SCC 25
Electric distribution companies cannot charge consumers for transformer costs as such charges violate existing regulations; statutory directives from regulatory authorities must be adhered to without....
Commission constituted under Section 17 of the 1998 Act is an expert body and the determination of tariff which has to be made by the Commission involves a very highly technical procedure, requiring ....
New owners of properties are liable to pay fixed electricity charges of prior tenants, while charges deemed unlawful cannot be enforced against them.
The distribution licensee cannot impose additional fees for transformer losses on consumers billed at low tension rates, as per established tariff regulations.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.