SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Raj) 98

HIGH COURT OF JUDICATURE FOR RAJASTHAN BENCH AT JAIPUR
Praveer Bhatnagar, J.
RC Power Project Limited - Petitioner
Versus
State Of Rajasthan, Through Additional Chief Secretary, Department Of Energy – Respondent
S.B. Civil Writ Petition No. 5747 of 2025, S.B. Civil Writ Petition No. 5748 of 2025
Decided On : 31-01-2026

Advocates Appeared:
For the Petitioner: Mr. Kamlakar Sharma, Sr. Adv., assisted by Mr. Sandeep Pathak, Adv., Ms. Jaya Pathak, Adv., Ms. Shefali Sharma, Adv., Ms. Palak Saraswat, Adv., Mr. Harshit Bansal, Adv.
For the Respondent: Mr. Rajendra Prasad, AG (Sr. Adv.), Mr. Umang Gupta, Adv., Mr. Tarang Gupta, Adv., Ms. Vidhi Mitruka, Adv., Mr. Tanay Goyal, Adv., Mr. Sheetanshu Sharma, Adv., Ms. Dhriti Laddha, Adv., Ms. Harshita Thakral, Adv.

Judicial review in government contracts is limited, ensuring non-arbitrariness, and contract termination on grounds of corruption can occur without pre-notice when grounded in statutory provisions.

Headnote:(A) Rajasthan Transparency in Public Procurement Act, 2012 - Sections 11(2)(a)(i) and 46(3) - Termination of contract and debarment of petitioner following allegations of corrupt practices and violations of procurement norms - The court ruled the action was justified as it adhered to statutory provisions and contractual obligations, upholding that judicial review in such matters is limited to ensuring non-arbitrariness. (Paras 5, 6, 21, 38)

(B) Principles of natural justice - The court determined that the principles did not require a show cause notice before contract termination where contractual terms allow for such termination upon identifying corrupt practices. (Paras 12, 26)

(C) Judicial review - The court emphasized that judicial intervention in matters of government contracts is only warranted in instances of mala fides or arbitrariness, not simply based on the existence of disputed facts or contractual dissatisfaction. (Paras 15, 20)

Facts of the case:
The petitioner challenged the termination and debarment orders by JVVNL, alleging arbitrariness and violation of principles of natural justice while contending significant financial prejudice from these actions.

Findings of Court:
The termination order was upheld as resting on credible findings of corrupt practices, with no procedural violation upon which interference was warranted.

Issues: The court addressed if the termination constituted an arbitrary exercise of power and whether pre-termination procedures aligned with both contract terms and statutory provisions.

Ratio Decidendi: The court held that the contractual framework permitted termination for suspected corrupt practices without advance notice and affirmed the limited scope of judicial review in contract disputes.

Result: Writ petitions dismissed.

Table of Content
1. writ petition based on contract disputes. (Para 1 , 2 , 3)
2. petitioner's arguments against termination and debarment. (Para 4 , 5 , 6 , 7 , 8 , 9 , 10 , 11)
3. respondent's defenses against petitioner's claims. (Para 13 , 14 , 15 , 16 , 17)
4. judicial review scope in government contracts. (Para 20 , 21 , 22)
5. termination grounds under contract provisions. (Para 25 , 26 , 27 , 28 , 29 , 30)
6. valid grounds for debarment under statutory provisions. (Para 36 , 37 , 38 , 39)

JUDGMENT :

PRAVEER BHATNAGAR, J.

1. These two writ petitions, having been heard together, are decided by this common judgment.

2. The present writ petitions under Article 226 of the Constitution of India arises out of and relates to the tender process initiated by the respondent– Jaipur Vidyut Vitran Nigam Limited, (hereinafter, to be referred as 'JVVNL') under Tender-NIT No. JVVNL/SE(TW)/TN-545 & JVVNL/SE(TW)/TN-546 and the contract awarded pursuant thereto for execution of works relating to 33/11 KV Grid Sub-Stations on 'BOOT' model basis.

3. The petitioner has approached this Court assailing the termination of the said contract vide order dated 09.04.2025, along with the consequential actions including issuance of show- cause notice and the order of debarment dated 13.08.2025 and has prayed for quashing of the said orders on the ground that the same are arbitrary, violative of the principles of natural justice, contrary to the terms of the contract and in breach of the provisions of the Rajasthan Transparency in Public Procurement Act, 2012 (in short, ‘Act of 2012’) and the Rajasthan Transparency in Public Procurement Rules, 2013 (in short, ‘Rules of 2013’) framed thereunder.

Argument Advanced by Counsel for the Petitioner:-

4. Learned Senior counsel appearing on behalf of the petitioner submits that the impugned termination order dated 09.04.2025 and the consequential debarment order dated 13.08.2025 are ex facie arbitrary, unreasonable and unsustainable in law. It is contended that the respondents have acted in a pre-determined manner, without adhering to the contractual framework governing the parties and have sought to justify the termination retrospectively by relying upon internal enquiry reports and audit observations. It is argued that once a contract is lawfully awarded after scrutiny by the respondents’ own committees and substantial work has been executed thereunder, the respondents cannot abandon the contractual terms and resort to extra-contractual considerations to terminate the agreement.

5. Learned counsel for the petitioner further submits that the preliminary objection raised by the respondents regarding non- maintainability of the present writ petition is unsustainable in law. It is argued that the jurisdiction of this Court under Article 226 is not ousted merely because the dispute arises out of a contractual relationship. In order to buttress his argument reliance was placed on the case of ABL International Ltd. v. Export Credit Guarantee Corporation of India Ltd. , (2004) 3 SCC 553 , Vice Chairman & Managing Director, CIDCO v. Shishir Realty Pvt. Ltd., (2022) 16 SCC 527 , Subodh Kumar Singh Rathour v. Kolkata Metropolitan Development Authority , (2024) SCC OnLine SC 1682 and State of U.P. v. Sudhir Kumar Singh , (2021) 19 SCC 706 , wherein the Hon’ble Apex Court held that when the State or its instrumentalities are parties to a contract, they remain bound by the mandate of Article 14 to act fairly, reasonably and non-arbitrarily and that arbitrary repudiation or termination of contractual obligations is amenable to judicial review.

6. Learned counsel further submits that the mere existence of disputed questions of fact does not, by itself, bar the exercise of writ jurisdiction and while placing reliance on the judgments of Unitech Ltd. v. Telangana State Industrial Infrastructure Corporation , (2021) 16 SCC 35 and UMC Technologies Pvt. Ltd. v. Food Corporation of India , (2021) 2 SCC 551 , it is contended that where the ch

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top