SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Raj) 376

IN THE HIGH COURT OF JUDICATURE FOR RAJASTHAN AT JODHPUR
ARUN MONGA, SUNIL BENIWAL, JJ.
Jai Narayan Vyas University – Appellant
Versus
M/s Sawai Engineers – Respondent
D.B. Civil Miscellaneous Appeal No. 412 of 2025
Decided On : 16-04-2026

Advocates Appeared:
For the Appellant : Adwaita Sharma
For the Respondents: Himanshu Maheshwari, Bharat Maheshwari

An appellate authority reviewing an arbitral award possesses strictly limited supervisory jurisdiction; it cannot re-evaluate evidence or substitute its own interpretation of contractual clauses unless the award is proven to be patently illegal, perverse, or fundamentally in conflict with public policy.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Sections 34, 37, 28(3) and 34(2A) - Scope of judicial interference in arbitral awards - Appellate court exercising jurisdiction under Section 37 cannot sit as a court of appeal to re-appreciate evidence or substitute its own interpretation unless the findings are tainted by patent illegality, perversity, or jurisdictional error - Interpretation of contractual terms remains within the domain of the arbitral tribunal, and interference is not warranted merely because an alternative interpretation is possible. (Paras 8, 10, 13)

(B) Limitation - Mixed question of fact and law - Determination of limitation based on running accounts, including dates of payments and bill rejections, constitutes a factual finding by the arbitral tribunal which does not invite interference in appellate proceedings unless the findings are shown to be contrary to record or irrational. (Paras 14)

Facts of the case:
The dispute arose from a construction services contract where the service provider ceased work due to payment defaults. Arbitration was invoked following unresolved payment disputes. The tribunal ruled in favor of the service provider, which the employer challenged as being time-barred and based on incorrect contractual interpretation. The commercial court upheld the award, prompting an appeal against that decision.

Findings of Court:
The court concluded that the arbitral tribunal remained within its domain of expertise. It held that the commercial court appropriately exercised its supervisory jurisdiction, and no grounds for interference existed as the tribunal had adequately considered oral and documentary evidence. The court emphasized that the appellate jurisdiction is more restricted than the already limited grounds under the initial challenge stage.

Issues: The central questions addressed were whether the claims were barred by limitation and whether the appellate authority could interfere with the interpretation of contract clauses and the factual assessments made by the tribunal.

Ratio Decidendi: The court established that in the absence of patent illegality or perversity, an arbitral award must be respected; judges cannot re-evaluate evidence or replace the arbitrator's interpretation of contractual terms with their own, as the court's role is strictly supervisory rather than appellate.

Result: Appeal dismissed.

Table of Content
1. factual history regarding work order, arbitration, and prior litigation. (Para 1 , 2)
2. parties' conflicting contentions on contract interpretation, limitation, and arbitral jurisdiction. (Para 3 , 4)
3. scope of appellate jurisdiction under section 37 of the 1996 act. (Para 5 , 6 , 7 , 8 , 9)
4. judicial restraint regarding re-appreciation of evidence and contract interpretation. (Para 10 , 11 , 12 , 13)
5. limitation period in continuous running account transactions. (Para 14 , 15)
6. dismissal of appeal and affirmation of arbitral award. (Para 16 , 17)

ORDER :

1. Assailed herein is a judgment and order dated 06.11.2024 passed by the Commercial Court, Jodhpur Metropolitan, whereby the petition filed by the appellants under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter, “1996 Act”) was dismissed, and the Arbitral Award dated 31.12.2021 was upheld.

2. The dispute originates from a work order dated 22.09.2008 between the parties for construction of a Guest House of Academic Staff for a total work order of Rs.71,57,743/-. The work was to be completed within ten months, i.e., by 05.08.2009. Subsequently, an additional work order dated 18.09.2010 worth Rs.25 lakhs was issued for completion of the remaining work, extending the timeline up to 27.09.2010 without imposing any penalty.

2.1 However, due to lack of funds the University was unable to clear the bills. Consequently, the respondent stopped the work. The respondent also sent various communications to clear the outstanding dues. The matter was placed before the University’s Building Committee and Syndicate, wherein it was decided to pay the respondent for the work executed. The respondent was asked to submit his final bills. The respondent submitted final bills, and payments were made in parts. The respondent also submitted 14th running bill dated 29.06.2011 amounting to Rs.5,90,397/-. The appellant made part-payment of the said bill which was accepted by respondent under protest, leading to a dispute over a balance sum of Rs.2,26,617/-.

2.2 On 14.12.2015, respondent invoked arbitration under Clause 23 of the agreement. Upon failure of the University to appoint an arbitrator, the respondent approached this Court under Section 11(6) of 1996 Act, resulting in the appointment of a sole arbitrator on 15.05.2019. Arbitration proceedings were conducted, and by award dated 31.12.2021, the Arbitrator ruled in favour of the respondent. The appellants objected to the award under Section 34 of 1996 Act; however, the award was upheld by the Commercial Court on 06.11.2024.

2.3 Hence, the instant appeal.

3. Ms. Adwaita Sharma, learned counsel for the appellants vehemently contends that the impugned judgment dated 06.11.2024, as well as the Arbitral Award dated 31.12.2021, are contrary to the settled principles of law and the facts borne out from the record. Being perverse, patently illegal, and in conflict with the public policy, the same deserve to be set aside. It is submitted that the learned Commercial Court failed to exercise the jurisdiction vested in it under Section 34 of the 1996 Act, having mechanically observed that the scope of interference is limited, without duly adjudicating upon the specific objections raised by the appellants. Such failure to consider material issues strikes at the very root of the matter and renders the impugned judgment wholly unsustainable.

3.1 It is further contended that the learned Arbitrator gravely erred in interpreting Clause 6 of the agreement by importing conditions such as obtaining consent of the contractor and recording reasons for re-measurement, which are not contemplated under the contract. The clause clearly provides that measurements determined by the Engineer-in-Charge are final and binding, and only requires reasonable notice. The Arbitrator, therefore, not only misinterpreted the contractual terms but also travelled beyond the scope of reference by deciding issues not raised by the parties, thereby vitiat

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top