SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2023 Supreme(Del) 2828

IN THE HIGH COURT OF DELHI AT NEW DELHI
Suresh Kumar Kait, Neena Bansal Krishna, JJ.
Municipal Corporation of Delhi – Appellant
Versus
M/s Sweka Powertech Engineers Pvt. Ltd. – Respondent
FAO (COMM) 149 of 2022 & CM APPLs. 43428-30 of 2022
Decided On : 15-02-2023

Advocates appeared:
Mr. Akhil Mittal, Standing Counsel with Ms. Shreya Chopra, Advocate, for the Appellant.
Mr. Gaurav Saria, Ms. Charul Sarin & Mr. Harish Kumar, Advocates, for the Respondent.

The Court emphasized the limited scope of interference under Section 34 and 37 of the Act, 1996, and the need for valid permissible grounds for challenging an arbitral award.

Headnote:

Commercial Courts Act - Arbitration and Conciliation Act, 1996 - Work Order - Claims - Arbitral Award - Challenge under Section 34 - Common Order - Summary of Acts and Sections: Commercial Courts Act, 2015, Section 13; Arbitration and Conciliation Act, 1996, Section 37

Fact of the Case:

The respondent was awarded a work order by the appellant for street light arrangement and ancillary work. Disputes arose, leading to arbitration. The Sole Arbitrator partly allowed the respondent's claims and dismissed the appellant's counter-claim. Both parties challenged the award under Section 34 of the Act, 1996, which were dismissed by the District Judge. The appellant appealed the dismissal.

Finding of the Court:

The Court found that the appellant's challenges to the award were essentially based on reappreciation of evidence, which is beyond the scope of Section 37 of the Act. The appeal was dismissed as without merit.

Issues: Challenge to Arbitral Award under Section 34 of the Act, 1996

Ratio Decidendi: The Court's decision was based on the limited scope of interference under Section 34 and 37 of the Act, 1996, and the lack of grounds for interference with the findings of the Arbitrator.

Final Decision: The appeal was dismissed as without merit, and the pending applications were also dismissed.

JUDGMENT

Neena Bansal Krishna, J. The present appeal under Section 13 of the Commercial Courts Act, 2015 read with Section 37 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as "Act, 1996") has been filed challenging the Common Order dated 24.01.2022 passed by the learned District Judge (Commercial) Central District, Tis Hazari, dismissing both the petitions under Section 34 of the Act, 1996, preferred by the appellant and the respondent herein against the Arbitral Award dated 30.01.2019.

2. The facts in brief are that, the respondent herein, M/s Sweka Powertech Engineers Pvt. Ltd. was awarded Work Order No. EE(E)-Project/SYS/2010-2011/5 dated 16.07.2010 by the appellant herein/Municipal Corporation of Delhi for providing street light arrangement and ancillary work in different roads/streets of the Karol Bagh Zone. In pursuance to the said Work Order, the appellant entered into a contract dated 25.03.2010 with the respondent.

3. During the course of execution of work, certain disputes arose between the parties and accordingly, a Notice for settlement of disputes through arbitration in terms of the Agreement between the parties, was sent by the respondent to the appellant. However, on receiving no response from the appellant, a petition under Section 11 of the Act, 1996 was preferred which was allowed by this Court vide Order dated 02.04.2013 and Mr. Justice R.C. Chopra (Retd.) was appointed as the Sole Arbitrator. The Sole Arbitrator, however, recused himself on 14.03.2017.

4. Thereafter, the Commissioner, MCD appointed Professor (Er.) O.P. Gupta, VSM (Retd. Chief Engineer, MCD) as the substitute Arbitrator, who made the Award dated 30.01.2019 vide which the respondent's claims were partly allowed and the Counter-Claim of the appellant was dismissed. Both, the appellant as well as respondent, have challenged the Order under Section 34 of the Act, 1996.

5. To understand the grounds of challenge, it would be necessary to give a vignette of facts. The respondent, in terms of the Contract, was required to provide street light arrangement and ancillary work in different roads/streets of the Karol Bagh Zone and to complete the work within six months i.e., upto 15.01.2011. The respondent/claimant herein filed the following six Claims before the Sole Arbitrator:

Claim No.DescriptionClaim Amount (Rs.)Interest @ 18% p.a. (Rs.)Total AmountRemarks
1.For payment of Rs.64,96,268/- for work done along with interest @ 18% per annum64,96,26869,26,2671,34,22,535Completion date was 06.01.2011 & payment due date was 06.07.2011. Interest is claimed upto 08.06.2017 (5 years & 337 days)
2.The refund of the Security deducted by the respondent @ 10% from RA Bills19,88,38319,38,59139,26,974Payment due date was 06.01.2017. Interest is claimed upto 08.06.2017 (5 years & 152 days)
3.Fee paid towards inspection5,48,707Claim not pressed
4.Loss of profit on account of reduction of scope of work7,79,539Claim not pressed
5.Interest @ 18% per annum pre-suit, pendent lite & future on the claim No. 1 to 4 as stated aboveInterest already covered in Claim No. 1 & 2 and not pressed in Claim No. 3 & 4. Pendent elite and future interest to be calculated at appropriate time
6.Cost of Arbitration10,00,00010,00,000Interest on cost not pressed
Final Amount94,84,65188,64,8581,83,49,509

6. The appellant filed its Counter-Claim for compensation/penalty for slow performance and delay in execution of the work in the sum of Rs.63,61,942/- along with the interest @ 18% per annum, in addition to Arbitration cost of Rs.5,00,000/-.

7. The Sole Arbitrator vide Award dated 30.01.2019 allowed the Claim Nos. 1, 2, 5 & 6 i.e., payment of final bill; refund of security; the interest @ 9% per annum and the costs. The Claim Nos. 3 and 4 were not pressed by the claimant. The Arbitrator made the following orders:

    "Order:

    Considering the pleadings of both the parties, documentary evidences, on record, arguments made by learned counsels, examination/consideration of the case

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top