IN THE HIGH COURT OF HIMACHAL PRADESH AT SHIMLA
RANJAN SHARMA, J.
Keshav Ram - Appellant
Versus
National Highway Authority of India and Another - Respondents
Arbitration Case No. 45 of 2025
Decided On : 07-03-2025
(A) National Highways Act, 1956 - Section 3(A) - Arbitration and Conciliation Act, 1996 - Sections 29A(1), 29A(3), 29A(4), 29A(5) - Petition for extension of time for arbitral proceedings - The petitioner sought to regularize the period for completion of arbitral proceedings due to delays caused by the COVID-19 pandemic and administrative reasons - The court found that the delay was not attributable to the petitioner and that the mandate of the Arbitrator should be extended to prevent prejudice to the parties involved. (Paras 2, 6, 10)
(B) Sufficient Cause - The court emphasized that the reasons for delay in arbitral proceedings were bona fide and warranted an extension of time under Section 29A(5) of the Act. (Paras 7, 8)
(C) Prejudice to Parties - The court ruled that the abrupt termination of the Arbitrator's mandate prejudiced the petitioner, who had participated in the proceedings since 2018. (Paras 8, 10)
(D) Judicial Precedent - The court noted that similar extensions had been granted in previous cases involving the same subject matter. (Paras 9, 10)
Findings of Court:
The Impugned Order was quashed, and the Arbitrator was directed to complete the proceedings within six months.
Issues: The main issues were whether the delay in arbitral proceedings was attributable to the petitioner and whether the mandate of the Arbitrator could be extended.
Ratio Decidendi: The court held that the delay was due to administrative reasons and the COVID-19 pandemic, thus justifying the extension of the Arbitrator's mandate.
Result: Petition allowed.
JUDGMENT :
Ranjan Sharma, J.
1. Petitioner [Keshav Ram], has come up, before this Court, seeking the following relief(s):-
“That the period from 12-05-2020 onwards may kindly be regularized and the mandate of the Arbitrator may kindly be extended for a reasonable time.”
FACTUAL MATRIX:
2. Case of petitioner [Keshav Ram] as set- up by Mr. H.S. Chandel, Learned Counsel is thatpursuant to Notification under Section 3(A) of the National Highways Act, 1956, the Central Government published a Notification to acquire the stretch of land from 106.0002 to 155.800 Kms. (Solan – Shimla Section) for four lanning etc. in State of Himachal Pradesh. Consequently, the land in 22 villages of Tehsil Shimla [Rural], including the lands of petitioner was acquired by CALA i.e. Competent Authority/Land Acquisition in terms of anAward No.4, dated 25.05.2015:
(i)Feeling aggrieved against the Award dated 25.05.2015, passed by Competent Authority for Land Acquisition, the petitioner filed a reference petition before Learned Arbitrator-cum-Divisional Commissioner, Shimla, which was registered as Reference Petition No. 83/2018, whereby, Learned Arbitrator continued the arbitral proceedings, but on 14.03.2023 [referred to as the ‘Impugned Order’], the arbitral proceedings were closed and the mandate of Arbitrator was treated to have been terminated on the ground that arbitral proceedings could not be completed within the time schedule as per Section 29A(1) and Section 29A(3) of the Arbitration and Conciliation Act.
(ii) Consequent upon the passing of the Impugned Order on 14.03.2023, terminating the mandate of Arbitrator and in keeping the arbitral proceedings in abeyance till extension was sought from a competent Court, therefore, in these circumstances, since the petitioner was left without any remedy coupled with the fact that the delay in completion of arbitral proceedings was not attributable to the petitioner; and delay in completion of arbitral proceedings was entirely due to administrative reasons, for which, the parties should not be made to suffer, coupled with the fact that termination of mandate of Arbitrator will cause prejudice to the parties therefore, in these circumstances, it was prayed that the time for completion of arbitral proceedings may be enlarged with directions to Learned Arbitrator-cum-Divisional Commissioner concerned to conclude the proceedings.
3. Upon listing of this case today and in response to a query by this Court, Learned Counsel(s) for parties, jointly represented that in similar matters, relating to Solan-Shimla, Section of NH, this Court had enlarged time for conclusion of arbitral proceedings with direction(s) to Learned Arbitrator-cum-Divisional Commissioner, Shimla [HP] to complete the arbitral proceedings within a reasonable time.
4. Heard, Mr. H.S. Chandel and Mr. Ashir Kaith, Learned Counsel for petitioner and Ms. Sneh Bhimta, Learned Counsel for contesting respondent No.1 as well as Mr. Gobind Korla, Learned Additional Advocate General for respondent No.2 and have gone through the material on record.
STATUTORY PROVISION:
5. In order to appreciate the claim of the parties herein, it is necessary to have a recap of the statutory provision of Section 29A of the Arbitration and Conciliation Act, 1996 [hereinafter referred to as ‘Act’] which reads as under:-
“29A. Time limit for arbitral award —
(1) The award in matters other than international commercial arbitration shall be made by the arbitral tribunal within a period of twelve months from the date of completion of pleadings under sub-section (4) of section 23 Provided that the award in the matter of international commercial arbitration may be made as expeditiously as possible and endeavor may be made to dispose of the matter within a period of twelve months from the date of completion of pleadings under sub-section (4) of section 23.
(2) If the award is made within a period of six months from the date the arbitral tribunal enters upon the reference, the arbitral tribunal sh
The court ruled that delays in arbitral proceedings due to administrative reasons and the COVID-19 pandemic justified extending the Arbitrator's mandate under Section 29A of the Arbitration and Conci....
The court can extend the time for arbitral proceedings under sufficient cause, preventing parties from suffering due to delays not attributable to them.
The court ruled that extensions of time for arbitral proceedings are warranted when delays are not attributable to the parties, prioritizing efficiency and justice in the arbitration process.
The court ruled that arbitration mandates may be extended due to administrative delays not attributable to the parties, affirming the need for the timely resolution of disputes while preventing preju....
Extension of arbitration proceedings mandated by the court when delays are not attributable to the parties, ensuring fairness in the arbitral process.
The court emphasized that delays in arbitration due to administrative issues not attributable to the parties justify extending the arbitrator's mandate as per the provisions of the Arbitration and Co....
The court may extend the mandate of an Arbitrator for sufficient cause, ensuring parties are not prejudiced by delays not attributable to them.
Court extends arbitrator's mandate post-termination under Section 29A(5) for sufficient cause like procedural and administrative delays not attributable to petitioner, ensuring practical, expeditious....
Court may extend arbitrator's mandate under Section 29A(4),(5) post-termination for sufficient cause not attributable to petitioners, prioritizing pragmatic and effective arbitral conclusion.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.