SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(HP) 1042

IN THE HIGH COURT OF HIMACHAL PRADESH AT SHIMLA 
Ranjan Sharma, J.
Shiv Kumar - Petitioner
Versus
National Highways Authority of India (NHAI) & Another – Respondents
Arbitration Case No: 927 of 2024 a/w Arbitration Case Nos.928 to 932 of 2024
Decided On : 08-01-2025


Advocates:
Advocate Appeared:
For the Petitioner:Mr. Arush Matlotia, Advocate
For the Respondent:Ms. Shreya Chauhan, Advocate, Mr. Vishav Deep Sharma, Additional Advocate General

The court ruled that arbitration mandates may be extended due to administrative delays not attributable to the parties, affirming the need for the timely resolution of disputes while preventing prejudice due to procedural setbacks.

Headnote:(A) National Highways Act, 1956 - Section 3(a) - Arbitration and Conciliation Act, 1996 - Sections 29A(1), 29A(3), and 29A(4) - Extension of mandate of arbitrator - Petitioner sought extension of time for arbitration proceedings after the mandate was terminated due to delay not attributable to them - Court emphasized that the arbitral proceedings should not punish parties for administrative delays - Court found sufficient cause for extending the mandate and set aside the arbitrator’s action - Directions issued for completion of proceedings within six months. (Paras 4, 9, 12)

(B) Termination of Arbitrator’s Mandate - Grounds for extension of time for completing arbitral proceedings discussed - Ensured parties are not prejudiced by administrative delays in arbitral process. (Paras 9, 10)

Table of Content
1. judgment consolidates cases with common issues. (Para 1 , 2 , 3)
2. petitioner seeks extension of arbitration proceedings. (Para 4)
3. petitioner sought an extension due to delays in arbitral proceedings. (Para 5)
4. the legal provisions of the arbitration act are summarized. (Para 6 , 8)
5. court analyzes sufficient cause for extension. (Para 9)
6. arbitrator's actions and timelines justified an extension. (Para 10)
7. orders reinstated for completion of proceedings within six months. (Para 11)
8. court allows petitions and restores arbitral proceedings. (Para 12)

JUDGMENT :

Ranjan Sharma, J.

Since common question of facts and law are involved, therefore, with the consent of parties, all these cases, are taken up for adjudication together at this stage, in the interests of justice.

2. Learned Counsel for petitioners states that Arbitration Case No.927 of 2024, titled as Shiv Kumar versus National Highways Authority of India (NHAI) & Another, may be treated as ‘Lead Case’ for adjudicating the said case and all connected petitions. Prayer not opposed by Learned Counsel for contesting respondents. Accordingly, the prayer is allowed and this Court proceeds in the above matters.

3. Petitioner [Shiv Kumar] in Lead Case i.e. Arbitration Case No.927 of 2024, has come up, before this Court, seeking the following relief(s):-

“ It is, therefore, respectfully prayed that in view of the facts stated above the application may kindly be allowed and the time limit for completing the Arbitration proceedings in Case No.(Revenue Appeal) No.176 of 2022, titled as Shiv Kumar versus NHAI and another pending adjudication before the learned Arbitrator-cum-Divisional Commissioner Kangra at Dharamshala, District Kangra [HP], may kindly be extended for a further period of 6 months and delay if any may kindly be condoned.”

FACTUAL MATRIX IN LEAD CASE- ARBITRATION CASE NO.927 OF 2024.

4. Case of petitioner [Shiv Kumar] in Arbitration Case No.927 of 2024, as set-up by Mr. Arush Matlotia, Learned Counsel is that pursuant to Notification under Section 3(a) of the NATIONAL HIGHWAYS ACT , 1956, the Central Government published a Notification to acquire the stretch of land from Kilometer 11.0 to Kilometer 42.0 (Pathankot-Mandi Section) of National Highway No.154 for building, widening, maintenance, management and operation of said Highway in State of Himachal Pradesh. Consequently, the land belonging to petitioner at Village Kohri, Tehsil Nurpur, District Kangra [HP] was acquired by CALA i.e. Competent Authority/Land Acquisition in terms of an Award No.11 of 2021, dated 25.02.2021.

4(i). Feeling aggrieved against the Award dated 25.02.2021, passed by Competent Authority for Land Acquisition, the petitioner filed a reference petition under Section 3G(5) of NATIONAL HIGHWAYS ACT before Learned Arbitrator-cum-Divisional Commissioner, Kangra, Himachal Pradesh which was registered as Revenue Appeal No.176 of 2022, whereby, Learned Arbitrator initiated the reference proceedings in April 2022 by directing the NHAI to file reply, which was filed belatedly. Thereafter issues were framed and after recording evidence of PW’s, the matter was taken up by Learned Arbitrator by directing the Respondent-NHAI to lead evidence. Thus, the arbitral proceedings were not concluded within the maximum permissible period of eighteen months as mandated under Section 29A(1) and Section 29A(3) of the Arbitration and Conciliation Act.

4(ii). It is averred that though the parties participated in arbitral proceedings from time to time, yet, abruptly the Arbitrator has passed an order that since the Award has not been passed within the period of maximum permissible period of eighteen months, therefore, the mandate of Arbitrator stands terminated and the arbitral proceedings were kept in abeyance so as enable the parties to seek extension of mandate or continuance of these proceedings from a competent Court. In this background, the petitioner has set up a case in Para 7 of instant petition,

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top