IN THE HIGH COURT OF HIMACHAL PRADESH, SHIMLA
BIPIN CHANDER NEGI, J.
Rajinder Sharma - Petitioner
Versus
Government of India and another - Respondents
Arbitration Case No.608 of 2024
Decided on : 23-09-2024
| Table of Content |
|---|
| 1. land acquisition process and case background. (Para 1 , 2 , 3) |
| 2. statutory time limits for arbitration. (Para 4) |
| 3. arbitrator's duty to adhere to statutory provisions. (Para 5 , 6 , 7) |
| 4. exclusion of specific periods in computing limitation. (Para 8) |
| 5. consequences of failing to complete arbitration timely. (Para 10 , 11) |
| 6. directions for conclusion of arbitration proceedings. (Para 12 , 13) |
JUDGMENT :
Bipin Chander Negi, J.
The arbitral dispute arises out of the land acquisition in District Solan, H.P. for the purpose of building (widening/ four laning etc.) maintenance, management and operation of National Highway- 22. The land has been acquired under the provisions of NATIONAL HIGHWAYS ACT , 1956.
2. Arbitration case No. 608 of 2024 pertains to Award No. 30 dated 27.06.2016, with respect to which the petitioner had preferred Reference Petition No. 458 of 2018. In the aforesaid reference, the Arbitrator had issued notices on 3.12.2018. The reply was filed on 30.08.2019. Vide order dated 26.05.2023, it was observed that the mandate of the Arbitrator had expired. Hence, the aforesaid arbitral proceedings were kept in abeyance, till the time period for completing the arbitral proceedings, was extended under Section 29-A.
3. From a perusal of the aforesaid, it is evident that the Reference Petition against the award had been filed by the land owners about 5 years back.
4. The relevant extract of the provisions involved in the present lis, as amended by the Act No 33 of 2019 w.e.f 31.08.2019, are being reproduced here-in-below for a ready reference:-
“29-A. Time limit for arbitral award.—(1) The award in matters other than international commercial arbitration be made by the arbitral tribunal within a period of twelve months from the date of completion of pleadings under sub-section (4) of Section 23:
(2)…………..
(3) The parties may, by consent, extend the period specified in sub-section (1) for making award for a further period not exceeding six months.
(4) If the award is not made within the period specified in sub-section (1) or the extended period specified under sub- section (3), the mandate of the arbitrator(s) shall terminate unless the court has, either prior to or after the expiry of the period so specified, extended the period: Provided that while extending the period under this sub- section, if the court finds that the proceedings have been delayed for the reasons attributable to the arbitral tribunal, then, it may order reduction of fees of arbitrator(s) by not exceeding five per cent for each month of such delay: Provided further that where an application under sub- section (5) is pending, the mandate of the arbitrator shall continue till the disposal of the said application: Provided also that the arbitrator shall be given an opportunity of being heard before the fees is reduced.
(5) The extension of period referred to in sub-section (4) may be on the application of any of the parties and may be granted only for sufficient cause and on such terms and conditions as may be imposed by the court.
Section 23. Statements of claim and defence
(4) The statement of claim and defence under this section shall be completed within a period of six months from the date the arbitrator or all the arbitrators, as the case may be, received notice, in writing, of their appointment.”
The sum and substance of the aforesaid provisions is that from the date the arbitrator receives notice the statement of claim and defence (pleadings) shall be completed within a period of six months there from. Further the award shall be made by the arbitral tribunal within a period of twelve months from the date of completion of pleadings. However, the parties may, by consent, extend the period specified for making award for a further period not exceeding six months. If the award is not made within the period specified or the extended period specified the mandate of the arbitrator shall terminate unless the court has, either prior to or after the expiry
AI
Arbitrator must adhere to statutory timelines; delays can lead to termination of mandate to ensure just compensation for affected parties.
Timely completion of arbitration proceedings is mandatory under the Arbitration and Conciliation Act, 1996, and failure to comply may result in termination of the Arbitrator's mandate.
Timely completion of arbitration proceedings is mandatory under the Arbitration and Conciliation Act, and failure to adhere to statutory timelines may result in termination of the arbitrator's mandat....
Point of Law : When a statute envisages an authority, be it an Arbitrator, to do a particular act in a particular manner and in a prescribed time schedule, then onus is upon the said authority/Arbitr....
The main legal point established in the judgment is that the award must be made within the specified time limit as per Section 29(A) of the Arbitration and Conciliation Act, 1996, and the parties hav....
Arbitration awards must be issued within prescribed time limits. If the period exceeds without consent or extension from the Court, the award can be invalidated.
As right to property is a Constitutional right under Article 300A of Constitution of India, appellant cannot be deprived of his property except in accordance with law.
Extension of arbitration proceedings mandated by the court when delays are not attributable to the parties, ensuring fairness in the arbitral process.
The court can grant an extension of time for arbitral proceedings if it is satisfied that the delay was due to circumstances beyond the control of the arbitral tribunal, as provided under S.29A of th....
The court can extend the time for arbitral proceedings under sufficient cause, preventing parties from suffering due to delays not attributable to them.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.