IN THE HIGH COURT OF JAMMU & KASHMIR AND LADAKH AT SRINAGAR
VINOD CHATTERJI KOUL, J.
M/s Khari Hydro Power Project Pvt. Ltd - Applicant
Versus
Union Territory of J&K and Others – Respondents
AA No.15 Of 2021
Decided On : 02-06-2022
The applicant sought relief under Section 9 of the Arbitration and Conciliation Act, 1996 for securing payment due for electricity supplied. The respondents objected, arguing that the application did not fulfill the purpose of Section 9 and that disputed questions of fact should be adjudicated through arbitration. The court considered the relevant agreement and provisions of Section 9, emphasizing that the court's power for interim measures is limited after the constitution of the arbitral tribunal. The court highlighted the need for exceptional circumstances to entertain an application under Section 9 after the constitution of the arbitral tribunal. Ultimately, the court directed the respondents to furnish a bank guarantee for the outstanding amount before the court, subject to the final outcome of arbitral proceedings.
Fact of the Case:
The applicant sought relief under Section 9 of the Arbitration and Conciliation Act, 1996 for securing payment due for electricity supplied. The respondents objected, arguing that the application did not fulfill the purpose of Section 9 and that disputed questions of fact should be adjudicated through arbitration.
Finding of the Court:
The court considered the relevant agreement and provisions of Section 9, emphasizing that the court's power for interim measures is limited after the constitution of the arbitral tribunal. The court highlighted the need for exceptional circumstances to entertain an application under Section 9 after the constitution of the arbitral tribunal. Ultimately, the court directed the respondents to furnish a bank guarantee for the outstanding amount before the court, subject to the final outcome of arbitral proceedings.
Issues: The main issue was whether the applicant's relief under Section 9 of the Act was justified, considering the objections raised by the respondents.
Ratio Decidendi: The court emphasized the limitations on its power for interim measures under Section 9 after the constitution of the arbitral tribunal and the need for exceptional circumstances to entertain such applications. It also highlighted the importance of adjudicating rights, claims, and interests of the parties through arbitration rather than deciding the whole case through interim measures.
Final Decision: The court directed the respondents to submit/furnish an unconditional and irrevocable Bank Guarantee in the amount of Rs.6,00,56,413/- before the Registry of the Court, with encashment subject to the final outcome of arbitral/arbitration proceedings.
JUDGMENT :
1. This petition has been preferred under Section 9 of the Arbitration and Conciliation Act, 1996 (for short “the Act”) for grant of following relief:
(ii) With further Orders commanding the Respondents in particular Respondent no.3 to release in due discharge of the Contractual Obligations undertaken by the Respondents under the Power Purchase Agreement dated 21.05.2018, the amount in the sum of INR 6,00,56,413.00 (Six Crores Fifty-Six Thousand Four Hundred and Thirteen only) dues and long overdue and payable to the Applicant Company.
2. The case set up by applicant is that it was allotted Khari-1 Small Hydro Power Development Scheme located at Village Ahama Trigam, Tehsil Banihal-Khari District Ramban, J&K on BOOT (Build Own Operate Transfer) basis, by J&K Energy Development Agency (JAKEDA) vide allotment letter dated 16th September 2013. According to applicant, he availed financial assistance from Indian Renewable Energy Development Agency Limited (IRDA) by way of Term Loan in the sum of Rs.27.25 Crores. It is claimed that aforesaid project was completed and commissioned by applicant company on 27th September 2020 and thereafter commenced supply of electricity to respondent no.2, followed by periodical invoices raised by applicant company for the electricity supplied to respondents and consumed by it/its end consumers. Petitioner claims that respondents have so far consumed electricity supplied worth the sum of Rs.6,00,56,413.00, which is yet to be paid.
3. Objection/counter has been filed by respondents, in which they insist that application does not fulfil the purpose of Section 9 of the Act as there is no immediate cause available to applicant for invoking Section 9. It is also contended that applicant is trying to raise highly disputed questions of facts which can only be adjudicated in case applicant commences arbitration proceedings and that a relief, which may be ultimate and final though not admitted, cannot be granted in the given circumstances.
4. I have heard learned counsel for parties and considered the matter.
5. As is discernible from the file, Clause 10.0 of the Agreement dated 21st May 2018 entered into between the parties, all questions, differences or disputes between the parties arising out of or in connection with this Agreement to the extent of power vested with JKSERC, shall be settled through arbitration in accordance with the provisions of the Jammu & Kashmir Arbitration and Conciliation Act, 1997 and any statutory modifications thereto. It also provides that efforts should be made by parties to settle the dispute through reconciliation before referring the matter to arbitration.
6. In the above backdrop, it would be appropriate to reproduce Section 9 of the Act:
(1) A party may, before or during arbitral proceedings or at any time after the making of the arbitral award but before it is enforced in accordance with section 36, apply to a Court:
(i) for the appointment of a guardian for a minor or a person of unsound mind for the purposes of arbitral proceedings; or
(ii) for an interim measure of protection in respect of any of the following matters, namely:
(a) the preservation, interim custody or sale of any goods which are the subject-matter of the arbitration agreement;
(b) securing the amount in dispute in the arbitration;
(c) the detention, preservation or inspection of any property or thing which is the subject-matter of the dispute in arbitration, or as to which any question may arise therein and authorising for any of the afores
The Court emphasized the limited circumstances under which the Court should intervene under Section 9(3) of the Act, 1996 after the constitution of the Arbitral Tribunal, and the alternative remedy u....
The award holder can seek interim relief under Section 9 of the Arbitration and Conciliation Act, 1996 until the complete satisfaction of the award.
The main legal point established in the judgment is that the Court applied the principles of strong prima facie case and weighing the balance of convenience in favor of the respondent company in gran....
The relief sought under Section 9 of the Arbitration Act is interim in nature and cannot be a permanent measure.
The financial distress of a party cannot justify securing unadjudicated claims as interim relief under Section 9 of the Arbitration Act; a prima facie case, balance of convenience, and irreparable ha....
Arbitration Application – Grant if interim relief - Court exercising appellate jurisdiction against an order in a Section 9 application, do not even have jurisdiction
The court can continue to entertain an application for interim relief under section 9 of the Arbitration and Conciliation Act, 1996 after the constitution of the arbitral tribunal if the court has al....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.