SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2023 Supreme(J&K) 620

IN THE HIGH COURT OF JAMMU AND KASHMIR AND LADAKH AT SRINAGAR
SINDHU SHARMA, J.
Vice Chairman, Lakes and Waterways Development Authority, Srinagar – Petitioner
Versus
Gh. Nabi Kraipak and Another – Respondents
AA No. 2 of 2014
Decided On : 16-06-2023

Advocates:
Advocate Appeared:
For the Petitioners: D.C. Raina, Satinder Singh, Sajad Ashraf, Ilyas Nazir Laway.
For the Respondent: Mir Suhail.

IMPORTANT POINT
The court established that the scope of judicial review of arbitral awards is highly restricted, and an award can only be set aside on specific grounds, including lack of jurisdiction, invalidity of the arbitration agreement, or conflict with public policy.

Headnote:

ARBITRATION - SETTING ASIDE ARBITRAL AWARD - Jammu and Kashmir Arbitration and Conciliation Act, 1997, Section 34 - The court discussed the limited grounds for setting aside an arbitral award under Section 34, emphasizing that the court does not sit in appeal over the award. Key provisions include the validity of the arbitration agreement, the jurisdiction of the arbitrator, and the public policy exception. The court interpreted these provisions to affirm the arbitrator's decision, concluding that the claim was not time-barred and that the arbitration process was valid, thus upholding the award.

Fact of the Case:

The applicant, LAWDA, sought to set aside an arbitration award favoring the respondent, a contractor, regarding payment for work done on a dredging project. Disputes arose over the amount due, leading to arbitration after both parties consented to the process. The arbitrator awarded the contractor Rs. 30,01,527, which LAWDA contested on several grounds, including alleged time-bar and lack of jurisdiction.

Finding of the Court:

The court found that the arbitrator had jurisdiction and that the claim was not time-barred. It emphasized that the arbitration agreement was valid and that the arbitrator's findings were reasonable and well-reasoned, dismissing the applicant's challenges to the award.

Issues: 1. Whether the claim was time-barred under Section 43 of the Arbitration Act. 2. Whether there was a valid arbitration agreement between the parties. 3. Whether the award was against public policy or contained patent illegality.

Ratio Decidendi: The court reiterated that under Section 34 of the Arbitration Act, the grounds for setting aside an arbitral award are limited. It held that the arbitrator's findings on jurisdiction and limitation were binding, and the award did not contravene public policy or statutory provisions.

Final Decision: The court dismissed the application to set aside the arbitral award, affirming the validity of the arbitration process and the award itself.

JUDGMENT :

SINDHU SHARMA, J.

1. This application under Section 34 of the Jammu and Kashmir Arbitration and Conciliation Act, 1997 (hereinafter referred to as Arbitration Act) for setting aside of the arbitration award dated 07.12.2013 passed by the sole Arbitrator Er. Zahoor Ahmad Chat, Executive Director, JKSPDC.

2. Lakes and Water Development Authority (LAWDA) (applicant herein), invited tenders vide NIT No. 2 of 5/2001, dated 11.05.2021 issued by the Executive Engineer, Civil Division, LAWDA, Srinagar vide its Endorsement No. CD/LWDA/577-606, dated 11.05.2001 for Mechanical Dredging/Desilting of Bed of Dal Lake near Shalimar Bridge to the required depth including all types of leads and lifts, carriages up to dumping site, dumping, leveling and dressing etc., as a complete job, as per the requirements of the Authority at the cost of Rs. 19,38,850/-. The respondent participated in the NIT and upon being successful was allotted the aforesaid work which was to be completed within stipulated time as mentioned in the NIT.

3. Dispute arose between the parties pertaining to the payment on account of work done. The applicant asked the respondents for signing of works register for an amount of Rs. 6,45,635/- but the respondent refused to sign the Works Register for an amount of Rs. 6,45,635/-, as settled by the authority and submitted his own bill for an amount of Rs. 19,05,250/-. The applicants did not agree to the amount raised by the respondent and consequently, no payment was released to the respondents.

4. The respondent No. 1, i.e., Contractor, aggrieved of inaction of respondent for releasing his work done payment, approached this Court by filing the writ petition bearing OWP No. 654/2003 regarding release of payment for the works executed by him. This writ petition was dismissed on 03.11.2006, as being not maintainable, however, the respondent was granted liberty to agitate the same through appropriate proceedings. Aggrieved of the judgment in the writ petition, the respondent filed LPA No. 177/2008. The appellate court, dismissed the appeal by the applicant against the judgment dated 16.04.2010 with the observation that the dismissal of the appeal shall not prevent the respondent to avail appropriate remedy as may be available to him under the provisions of law.

5. The respondent No. 1, thereafter, approached the Civil Court by filing a suit for recovery and injunction and sought a decree to recover of an amount of Rs. 35,33,850/- along with interest @ 18% and also permanent prohibitory injunction restraining the respondents from recovery of his loan amount till full and final payment is released. During the pendency of this suit, applicants (LAWDA) filed an application seeking a reference of the dispute raised by the respondent for arbitration under the Arbitration and Conciliation Act. In his response to the application to reference, the respondent submitted his no objection to the reference of the dispute for arbitration, as sought by the applicant. The applicants thereafter also provided a list of the arbitrators for reference of the dispute of the arbitration to which the respondent gave his concurrence. The learned 4th Additional District Judge referred the matter to the Arbitrator for adjudication of the dispute vide order dated 26.07.2011.

6. The Arbitrator passed the impugned award on 07.12.2013 awarding an amount of Rs. 30,01,527/- in favour of the claimant to be paid by respondent Nos. 1 to 3. The applicants have assailed this order of arbitration on the following grounds:

    a. That the award passed by the Arbitrator is illegal as the claim put forth by the respondent No. 1 was time barred. Since the period of limitation prescribed for availing the opportunity of remedy in arbitration proceedings is three years and in the present case, the proceedings were initiated in the year 2011, as such, the claim put forth by the respondent was barred by limitation in terms of Section 43 of Jammu and Kashmir Arbitration and Conciliati

              Click Here to Read the rest of this document
              1
              2
              3
              4
              5
              6
              7
              8
              9
              10
              11
              SupremeToday Portrait Ad
              supreme today icon
              logo-black

              An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

              Please visit our Training & Support
              Center or Contact Us for assistance

              qr

              Scan Me!

              India’s Legal research and Law Firm App, Download now!

              For Daily Legal Updates, Join us on :

              whatsapp-icon Back to top