IN THE HIGH COURT OF JAMMU & KASHMIR AND LADAKH AT JAMMU
RAJESH SEKHRI, J.
Manzoor Hussain – Appellant
Versus
UT of J&K & Ors. – Respondent
WP(C) No. 552 of 2025
Decided on : 05-03-2025
(A) Constitution of India - Article 226 - Writ jurisdiction - Release of admitted liability for construction work - Petitioner executed work for Budha Amarnath Ji Yatra and raised bills amounting to Rs. 9.45 lacs, which were admitted but not released by the respondents - Respondents contended that release of funds is contingent upon approval from Urban Local Bodies - Court held that contractor's belief in the legality of the work is legitimate and directed release of funds. (Paras 1-8)
(B) Contractual obligations of the State - The State must act in a just, fair, and reasonable manner in fulfilling contractual obligations, as established in M/s Surya Construction v. The State of UP. (Para 5)
Facts of the case:
The petitioner was awarded a contract for construction work, completed the work, and submitted bills which were admitted but not paid due to procedural delays.
Findings of Court:
The court found that the respondents did not dispute the execution of work or the liability to pay, and directed the release of funds within a specified timeframe.
Issues: The main issues were the legality of the work execution and the conditions for the release of funds.
Ratio Decidendi: The court ruled that the contractor's execution of work under the belief of proper authorization is valid, and the State must fulfill its contractual obligations.
Result: Petition allowed; funds to be released within three weeks.
JUDGMENT :
1. Petitioner has invoked writ jurisdiction of this Court, under Article 226 of the Constitution of India, for a mandate to the respondents, in particular respondents no. 3 and 5, for the release of admitted liability of Rs. 9.45 lacs on account of the execution of work, regarding construction of temporary bath rooms and allied works for Budha Amarnath Ji Yatra at Rajouri, along with interest @ 18 % per annum.
2. The case set out by the petitioner is that pursuant to the issuance of tender and acceptance of his bid by respondent no. 3, the work of construction of temporary bath rooms and allied works for Budha Amarnath Ji Yatra at Rajouri, came to be allotted in his favour vide allotment order no. EER/R&B/OG/2023-24 dated 25.09.2023. He executed and completed the allotted work to the satisfaction of the executing agency and raised bills amounting to Rs. 9.45 lacs, which came to be submitted by respondent no. 4 to the Executive Engineer, PWD (R&B) Division Rajouri-respondent no. 3 on 24.11.2023, after the completion certificate came to be issued in his favour by respondent no. 3 and signed by respondent no. 4. According to the petitioner, respondent no. 3, while admitting his liability submitted the bills to respondent no. 5 vide its communication no. 11196-97 dated 14.12.2023. He approached respondent no. 5 for release of the billed amount, who further admitted liability of the petitioner and produced a communication addressed to Director Urban Local Bodies, Jammu regarding release of funds against the allotted work. The grievance of the petitioner is that despite lapse of considerable time and representation made by him, his admitted liability has not been released in his favour and same has been withheld by the respondents without any lawful justification.
3. Heard arguments and perused the file.
4. Mr. Ravinder Gupta, learned counsel for respondents no. 1 to 4 has produced a Govt. Order No. 43-JK(HUD) of 2020 dated 04.02.2020, to contend that engineering wings of the Urban Local Bodies have been abolished and the execution of works came to be assigned to the Public Works (R&B) Department. According to Mr. Gupta, after the abolition of engineering wings of Urban Local Bodies, though all the payments/work done claims of the erstwhile Urban Local Bodies are being processed by Public Works (R&B) Divisions of the concerned Urban Local Bodies, however, the Finance Department has issued guidelines/modalities vide its circular dated 26.04.2021 for strict adherence by all the departments with respect to release of past liabilities and in case of any violation, action is required to be initiated against the erring officer. In essence, it is the stand of learned counsel for respondents no. 1 to 4 that admitted liability of the petitioner can be released only after release of funds by the concerned Urban Local Body and accord of sanction and administrative approval of the work.
5. It is by far a crystallized position of law now that it is not for the contractor, executing the work on behalf of the government or its agencies or Urban Local Bodies for that matter to consider whether Administrative approval, technical sanction and other legal formalities have been completed or not before undertaking a work, duly allotted in his favour by the competent authority. If a work duly sanctioned and allotted is executed and a completion certificate in this respect is issued in favour of a contractor, it is for the Government or the executing agency to explain that how work was executed in the absence of accord of approval and completion certificate is issued. A contractor who undertakes a particular work, after its due allotment, undertakes the same on the legitimate belief that the work is being undertaken by him after its due approval and completion of all the legal and codal formalities. Hon’ble Supreme Court in M/s Surya Construction v. The State of UP (Civil Appeal No. 2610/2010 dated 02.05.2010), has clearly ruled that State, while en
Contractors executing government work are entitled to payment based on the belief of proper authorization, and the State must act justly in fulfilling its contractual obligations.
Point of Law : Respondents have made the petitioner to execute the work out of his own funds, it is their bounden duty to reimburse the petitioner at the earliest, that too with interest.
A contractor's entitlement to payment for executed works cannot be denied based on alleged lack of administrative approval when such works were accepted, confirming the principle of accountability in....
Delay and laches cannot be invoked by the government to deny an admitted claim for payment, emphasizing the need for timely compensation to contractors.
Contractors are entitled to payment for work performed in good faith, regardless of the absence of formal Administrative approval for excess work.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.