(A) Prevention of Corruption Act - Sections 7 and 13(2) read with Section 13(1)(d) - Conviction of public servants for demanding and accepting bribes - Evidence of demand and acceptance established through corroborative testimonies despite non-examination of complainant - Legal presumption under Section 20 applicable. (Paras 8, 13, 21)
(B) Evidence - Non-examination of complainant - Not fatal to prosecution if demand and acceptance proved by other witnesses - Contextual circumstances surrounding demand and acceptance are relevant. (Paras 8, 14)
Facts of the case:
Appellants were convicted for demanding bribes from a complainant for clearing a work contract payment under the Gram Shamridhi Yojana. A trap was laid, and both were caught red-handed accepting bribes.
Findings of Court:
The court affirmed the conviction based on corroborative evidence from witnesses, establishing the demand and acceptance of bribes.
Issues: The main issues were the sufficiency of evidence in the absence of the complainant and the validity of the trap conducted.
Ratio Decidendi: The court held that the absence of the complainant does not negate the prosecution's case if other evidence sufficiently establishes demand and acceptance. Legal presumptions under the Act support the prosecution's case.
Result: Appeals dismissed; conviction upheld.
JUDGMENT :
GAUTAM KUMAR CHOUDHARY, J.
1. Heard the parties.
1.1 Both the aforesaid appeals are directed against the common judgment of conviction and sentence passed in connection with Vigilance (Spl.) Case No. 16 of 2003, whereby and whereunder, appellants have been convicted for the offence punishable under Sections 7 and 13(2) read with Section 13(1)(d) of the Prevention of Corruption Act.
2. Complainant is Sunil Kumar Munda, who had been awarded a work contract of Rs. 69,800/- under Gram Shamridhi Yojana in Chandil Block in the year 2002 for laying of bricks in village Balidih of District Saraikella, Kharsawan. After the completion of the work he received payment of Rs. 50,000/- by different cheques and also got wheat and rice of worth Rs. 9,000/-. It is alleged that for clearing the bill for release of balance amount, Assistant Engineer-Arun Kumar and Junior Engineer-Ram Janam Sharma demanded Rs. 3,500/- each i.e. 5%-5% commission on the said amount.
3. On receipt of the complaint, the Superintendent of Police, Vigilance Bureau, Ranchi deputed police inspector i.e. Diwa Shankar Prasad to verify the complaint and submit his report. He accordingly verified the matter and found the allegation true and submitted his report to the Superintendent of Police, Vigilance Bureau, Ranchi. Thereafter, on the direction of the Superintendent of Police, Vigilance, Ranchi, Vigilance P.S. Case No. 14 of 2003 was lodged and the Dy. S.P. namely, R.K. Dhan was appointed as I.O. of the case.
4. A trap team was constituted, and on 07.05.2003, after completing the pre-trap formalities, trap was laid on 08.05.2003 in the quarters of both the appellants situated in Chandil Block. The trap was first laid in the official quarter of Ramjanam Sharma, Junior Engineer and then in the house Arun Kumar, Assistant Engineer. Both of them were apprehended red handed while accepting the bribe amount of Rs. 3,500 each tendered by the appellant in the presence of shadow witness.
5. After investigation, charge sheet was submitted for the offence punishable under Sections 7 and 13(2) read with Section 13(1)(d) of the Prevention of Corruption Act against the appellants and they were put on trial under these sections.
6. Altogether nine witnesses were examined on behalf of the prosecution and the relevant documents were adduced into evidence, marked as exhibits Nos. 1-10 and X as well as material exhibits have also been proved.
7. After prosecution evidence, statement of the appellants was recorded under Section 313 of the Cr.P.C. Defense is of innocence and false implication.
8. It is argued by the learned counsel on behalf of the appellants that there are serious infirmities in the prosecution case which renders the judgment of conviction unsustainable. Complainant has not been examined, and the complaint has been proved formally proved by a witness who was not the author of the document. It is argued that in the absence of proof of demand by the complainant, the evidence of proof of demand by other witnesses is not sufficient to prove the charges under Section 7 and 13(2) of the P.C Act. Prove of demand by the shadow witness or the I.O. will not be sufficient. Reliance is placed on A. Subair v. State of Kerala, (2009) 6 SCC 587 wherein it has been held:
As far as the impact of non-examination of the complainant, law has now been settled that mere non-examination of a complainant will not be fatal to the prosecution, if demand and acceptance is proved by other evidences on record. Hon’ble Supreme Court held in Neeraj Dutta v. State (NCT of Delhi), (2023) 4 SCC 731:
90. Accordingly, the question referred for consideration of this
The absence of the complainant's testimony does not invalidate the prosecution's case if demand and acceptance of bribes are established through other evidence.
Establishing demand and acceptance of bribe is essential for conviction under the Prevention of Corruption Act; failure to prove these elements results in acquittal.
Mere recovery of tainted notes without proof of demand and voluntary acceptance insufficient for conviction under Sections 7, 13(1)(d) PC Act; demand is sine qua non, presumption under Section 20 ina....
The evidence in the record is sufficient to establish the charges for the offences punishable under Section 7 as well as Section 13 (2) read with Section 13 (1) (d) of the Prevention of Corruption Ac....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.