High Court of Judicature at Madras
THE HONOURABLE MR. JUSTICE K. KANNAN
Cash and Gain Finance and Investments rep. by its Managing Partner S.Vasatha & Others
Versus
Manjula Udaya Shankar
CRP (PD) No.1337 of 2008 and M.P.No.1 of 2008
Decided On : 31-10-2008
Arbitration - Partnership Dispute - Arbitration and Conciliation Act of 1996, Section 8 - 21
Fact of the Case:
The defendants sought for a reference to arbitration based on an arbitration agreement in a suit filed by a partner of a firm seeking dissolution. The application under Section 8 of the Arbitration and Conciliation Act was dismissed, leading to the Civil Revision Petition.
Finding of the Court:
The Court found that the disputes arising from mismanagement and fraud practiced by the defendants would not be governed by the arbitration clause in the partnership deed.
Issues: Interpretation of the arbitration clause in the partnership deed, applicability of limitation, and non-filing of the original or certified copy of the arbitration agreement.
Ratio Decidendi: The Court held that the duty of the Court to refer the parties to arbitration under Section 8(1) is unexceptional, and the mere fact that the party could have also approached for arbitration under Section 8(3) does not mandate that the party seeking reference ought to have taken steps under Section 8(3). The Court also emphasized that the delay in passing orders under Section 8 should not result in a party losing the remedy through arbitral process due to a plea of limitation attributable to the Court's delay.
Final Decision: The Court set aside the order of the lower court and directed that the dispute raised by the plaintiff in the suit be referred to arbitration through an Arbitrator duly appointed in accordance with the law.
I. Genesis of action
The defendants in a suit filed at the instance of a partner of a firm seeking for dissolution, moved an application under Section 8 of the Arbitration and Conciliation Act of 1996 seeking for a reference to arbitration on the basis that the subject matter of suit was governed by an arbitration agreement. The application was dismissed and the aggrieved parties are the Civil Revision Petitioners before this Court.
II. Core reason for dismissal of the petition.
2. While dismissing the application, the Court below took note of the averments in the plaint regarding the so called mismanagement and fraud practiced by the defendants and interpreted them to mean that disputes arising out of such a situation would not be governed by the relevant clause in the partnership deed though provided with an arbitration clause.
III. The relevant clause for consideration.
3. The partnership deed provided as follows:-
"Any disputes arising out of this partnership or as to interpretations operation or enforcement of terms of this partnership between the parties or their legal representatives shall be referred to the arbitration of a person appointed by the partners whose decision shall be final and binding on all partners and their legal representative".
IV. Principal grounds of challenge.
4. It is contended by the counsel for the revision petitioners that the interpretation given by the Court below was clearly wrong and that any issue relating to winding up and the entitlement of any party to resort to the provisions of Section 44 are squarely governed within the term disputes and amenable to arbitration by the operation of the clause referred to above.
V. Reference to arbitration Factors agaisnt, as urged in C.R.P.
5. The learned senior counsel for the respondent has difficulties to support the line of reasoning adopted by the Court below but sets out his objections as follows:
(a) The reference to arbitration will be an exercise in futility since it will be barred by limitation.
(b) The original or a duly certified copy of arbitration agreement has not been filed along with the petition under Section 8 and hence the petition is liable for rejection.
VI. Examination of the issue of limitation.
6. The suit had been instituted in the year 1999 and even before filing the written statement, the defendants had filed an application under Section 8 with a copy of the partnership deed containing the arbitration clause. On 13.07.200o, the suit had been subsequently transferred to the District Munsif Court at Coimbatore and the petition was pending all along without any orders of the Court.
A. Plaintiffs objections:
(a) Initiative for arbitral process not taken by defendants.
7. The argument unfolds on the premise that section 8(3) of the Arbitration and Conciliation Act allows for the commencement of arbitration proceedings, its continuance and rendering of an arbitral award, notwithstanding an application filed under Section 8(1). The petitioners ought to have taken steps to have an Arbitrator appointed by resort to Clause 18 of the Partnership Deed and if there was no concurrence in the appointment of an Arbitrator, they ought to have applied under Section 11 of the Act by an application before the Chief Justice for appointment of an Arbitrator.
(b) The commencement of the dispute relevant period for computing limitation.
8. The learned senior counsel relied on Section 21 of the Arbitration and Conciliation Act to state that the arbitral proceedings in respect of a particular dispute would commence on the date on which a request for the dispute to be referred to arbitration is received by the respondent. This request must be read into the application under Section 8(1) and if such a construction is made, it would mean that the cause of action had arisen on 13.07.2000 when the petition had been filed. The petitioners are bound to have taken steps within 3 years for appointment of the Arbitrator by an application of rul
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.