SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2021 Supreme(Mad) 2613

IN THE HIGH COURT OF JUDICATURE AT MADRAS
SENTHILKUMAR RAMAMOORTHY, J.
S. Gunasekaran & Others - Appellant
Versus
M/s. S & S Foundations Pvt. Ltd., Rep. by its Managing Director, Chennai - Respondent
Arb.O.P. No. 76 of 2021 & A. No. 2745 of 2021
Decided On : 17-12-2021

Advocates Appeared:
For the Petitioners:E. Om Prakash, S.C. for M/s. U. Karunakaran, Advocates.
For the Respondent:K. Bijai Sundar, Advocate.

Headnote:

Arbitration and Conciliation Act 1996 - Section 34(2) - Set aside Arbitration Award - Respondent was required to pay an aggregate sum of Rs.30 crores for purchase - MoU imposed an obligation on Petitioners to coordinate with respective land owners, obtain relevant documents and submit same for perusal by Respondent - If total cost of purchase exceeded Rs.30 crores, such cost was to be borne by Petitioners - Petitioners were unable to procure full extent of 120 acres in terms of MoU - By Supplemental MoU, extent of land to be procured was reduced from 120 acres to 65 to 67 acres, and sale consideration was increased from Rs.25 lakhs per acre to Rs.35 to Rs.37 lakhs per acre - Petitioners did not complete procurement of full extent of 67 acres, even as per Supplemental MoU - Petitioners assail Award on grounds : first ground of challenge is both MoU and Supplemental MoU are contingent contracts - Second ground of challenge is Arbitral Tribunal completely disregarded documentary evidence adduced by Petitioners - Third ground of challenge is that MoU and Supplemental MoU specified a mechanism to deal with non-compliance by Petitioners – Held, finding of Arbitral Tribunal that Petitioners had relinquished their rights under MoU and Supplemental MoU, in absence of a pleading for such purpose by Respondent, constitutes a patent illegality and warrants interference - On this issue, it should also be borne in mind that both MoU and Supplemental MoU prescribe mechanism to deal with breach - In construction contracts, it is standard practice for contractors to submit bids by factoring a profit percentage which ranges between 10% to 15% of value of work as judicially noticed in several judgments cited by Respondent - Arbitral award is liable to be interfered with if such award is based on no evidence - Award of a sum of about 2.43 crores towards loss of profit is admittedly on basis of no evidence - After recording a categorical finding that no evidence was adduced, Arbitral Tribunal committed a patent error in awarding a sum of Rs.2.43 crores - In this respect also, Award is not sustainable - Since award of costs to Respondent is on principle that costs follow event or loser pays, award of costs is also liable to be set aside on account of interference with other aspects of Award - Arbitral Award set aside.

JUDGMENT :

(Prayer: This Petition has been filed under Section 34(2) of the Arbitration and Conciliation Act 1996 praying to set aside the Arbitration Award dated 29.05.2019 made in Arbitration Case on the file of the Arbitrator Mr.Padmanaban Judge (Rtd.) and consequently allow the counter claims as claimed by the petitioners herein.)

1. The Petitioners were the respondents in the arbitral proceedings between them and the Respondent herein. The arbitral award dated 29.06.2019 (the Award) is assailed in this petition.

2. The Petitioners owned about 39.28 acres of land close to the Grand Southern Trunk(GST) Road. Some time in the year 2013, the Respondent approached the Petitioners in relation to the procurement of the above mentioned 40 acres as well as additional lands of an extent of 80 acres. Pursuant to negotiations in such regard, a Memorandum of Understanding dated 09.05.2013(the MoU) was executed between the parties. In terms of the MoU, the Petitioners were required to facilitate and procure the acquisition of 120 acres, in the aggregate, as described in the schedule to the MoU, by the Respondent herein. The MoU records that the Petitioners herein had already purchased an extent of 34.38 acres and also held an agreement for an extent of 4.90 acres, thereby aggregating to 39.28 acres. The sale consideration of Rs.25 lakhs per acre was fixed for the procurement of 120 acres under the MoU. The Respondent was required to pay an aggregate sum of Rs.30 crores for such purpose. The MoU imposed an obligation on the Petitioners herein to coordinate with the respective land owners, obtain the relevant documents and submit the same for perusal by the Respondent. If the total cost of purchase exceeded Rs.30 crores, such cost was to be borne by the Petitioners. The MoU provided for area sharing as follows: 26.1% or 6900 sq. ft. per acre of land was allotted to the share of the Petitioners; and 73.9% or 22200 sq. ft. per acre of land was alloted to the share of the Respondent. The MoU also stipulated that the Respondent is entitled to procure the lands if the Petitioners failed to do so, and that any excess cost in such regard shall be deducted by making an adjustment against the area allotted to the Petitioners under the MoU. Such MoU also contained an arbitration clause.

3. The agreed position is that the Petitioners were unable to procure the full extent of 120 acres in terms of the MoU. Pursuant to negotiations, the parties entered into a Supplemental Memorandum of Understanding dated 27.06.2014 (the Supplemental MoU). By the Supplemental MoU, the extent of land to be procured was reduced from 120 acres to 65 to 67 acres, and the sale consideration was increased from Rs.25 lakhs per acre to Rs.35 to Rs.37 lakhs per acre. However, the Supplemental MoU recorded that any amounts paid by the Respondent in excess of Rs.25 lakhs per acre shall be adjusted from the share of the Petitioners. The Supplemental MoU also provided for a further 20% of the above mentioned excess amount to be adjusted towards interest factor. The Supplemental MoU contained a schedule in which the survey numbers of lands, which were required to be procured, were set out. Significantly, the Supplemental MoU imposed an obligation on the Petitioners herein to procure the balance extent of 10 acres or thereabouts within a period of 15 days from the date of Supplemental MoU. In case of default, the Respondent could proceed to procure the lands and adjust the excess cost, if any, against the share of the Petitioners in the total project area.

4. Pursuant to both the MoU and the Supplemental MoU, payments were made to the Petitioners herein. Each time such payment was received by the Petitioners, it appears that endorsements were made on the MoU or the Supplemental MoU, as the case may be.

5. The Petitioners did not complete the procurement of the full extent of 67 acres, even as per the Supplemental MoU. While an extent of about 61.5 acres was procured, an extent of 5.5 acr

          Click Here to Read the rest of this document
          1
          2
          3
          4
          5
          6
          7
          8
          9
          10
          11
          SupremeToday Portrait Ad
          supreme today icon
          logo-black

          An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

          Please visit our Training & Support
          Center or Contact Us for assistance

          qr

          Scan Me!

          India’s Legal research and Law Firm App, Download now!

          For Daily Legal Updates, Join us on :

          whatsapp-icon Back to top