SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2022 Supreme(Mad) 1465

IN THE HIGH COURT OF JUDICATURE AT MADRAS
SENTHILKUMAR RAMAMOORTHY, J.
M/s. R.S. Infotainment (P) Ltd., Rep. by its Director R. Jayaraman, Chennai & Others - Appellant
Versus
M/s. Photon Factory Rep. by its Partner, Gautham Vasudev Menon, Chennai & Others - Respondent
Civil Suit No. 153 of 2013
Decided On : 05-04-2022

Advocates appeared:
For the Plaintiffs:V. Anand, B. Ramesh Babu, Advocates. For the Defendants:Chitra Sampath, Senior Advocate, Revathi Manivannan, Anand Abdul, Vinodh Associates, Advocates.

The main legal point established in the judgment is the award of damages for breach of contract and the determination of interest at a commercial rate based on the date of breach.

Headnote:

Breach of Contract - Recovery of Damages - Agreement dated 27.11.2008 - Interest at 24% p.a. - [BREACH OF CONTRACT] - [RECOVERY OF DAMAGES] - [CLAUSE 4 of the Agreement]

Fact of the Case:

The Plaintiff filed a suit for recovery of a sum of Rs.9,53,50,000/- from the first, third and fourth Defendants for breach of an Agreement dated 27.11.2008. The Plaintiff paid a sum of Rs.4.25 crore to the first Defendant for producing a movie, but the production was not commenced. The Defendants denied the claims and contended that the Plaintiff committed breach of the Agreement by not making further payments.

Finding of the Court:

The Court found that the Contesting Defendants did not commence production of the movie despite receiving the sum of Rs.4.25 crore from the Plaintiff. The Court concluded that the Contesting Defendants committed breach of the Agreement and awarded damages to the Plaintiff.

Issues: The issues included whether the Plaintiff paid the amounts agreed under the Agreement, whether time schedule for payment was the essence of the contract, and whether the Plaintiff committed breach of the terms agreed under the Agreement.

Ratio Decidendi: The Court held that the Plaintiff suffered a loss due to the Contesting Defendants' failure to commence production, and awarded damages based on breach of contract. The Court also awarded interest at 12% per annum from a reasonable extension date until the date of payment, and costs to the Plaintiff.

Final Decision: The suit was decreed, and the first, third and fourth Defendants were directed to pay the Plaintiff a sum of Rs.4.25 crore with interest at 12% per annum from 11.05.2010 till the date of payment, along with costs of Rs.12,00,000/-.

Judgement Key Points

Certainly. Based on the provided legal document, the main legal points established are as follows:

  1. Breach of Contract and Damages: The court found that the defendants failed to commence production of the movie despite receiving payment, constituting a breach of the agreement. As a result, damages were awarded to the plaintiff for this breach (!) (!) .

  2. Interest on Damages: The court awarded interest at a rate of 12% per annum from the date of breach or from a reasonable extension date, which was determined to be around 11.05.2010, until the date of payment (!) (!) .

  3. Limitation and Cause of Action: The court held that the suit was filed within the period of limitation, with the cause of action arising after the expiry of the original deadline but within a reasonable time thereafter, especially considering the extension implied by subsequent correspondence (!) (!) .

  4. Payment and Expenditure: The court concluded that the defendant did not establish that the funds received were used for the production of the specific movie in question ("Production No.6"). Evidence of expenditure was found unreliable, and no proof was provided that the production was completed or that the movie was released under the claimed title (!) (!) (!) (!) .

  5. Effect of Subsequent Agreements and Communications: The court noted that subsequent agreements and correspondence, including a letter dated 12.02.2010, indicated that the parties intended to perform their obligations despite the expiry of original deadlines. This extended the timeline for performance and negated the argument that the original time was of the essence (!) (!) (!) (!) .

  6. Right to Recover Funds: Since the defendants retained the funds without initiating production, and failed to prove expenditure towards the specific project, the plaintiff was entitled to recover the amount paid, which was Rs.4.25 crore, as damages for breach of contract (!) (!) (!) .

  7. Non-Applicability of Clause 4 for Interest: Although the agreement stipulated a 24% interest rate, the court clarified that this clause was not directly applicable to the damages claim. Instead, interest was awarded at a commercial rate of 12% per annum from the date the breach was established (!) (!) (!) .

  8. Discharge of Liability upon Release of the Movie: The court found that the release of the movie "Nee Thane En Pon Vasantham" did not discharge the defendants' liability, especially since the evidence did not establish that the film was produced as "Production No.6" or that the funds were used accordingly (!) (!) (!) (!) .

  9. Summary of the Final Award: The court decreed that the defendants pay Rs.4.25 crore with interest at 12% per annum from 11.05.2010 until payment, along with costs amounting to Rs.12,00,000 (!) (!) (!) .

These points collectively affirm the principles that breach of contractual obligations, especially related to the commencement of production and the appropriate use of funds, entitles the injured party to damages, including interest, provided that the breach is established and the cause of action is timely filed.


JUDGMENT

(Prayer: The suit has been filed under Order IV Rule 1 of the High Court Original Side Rules read with Order VII Rule 1 of CPC to order and decree that the Defendants 1,3 and 4 do pay the Plaintiff a sum of Rs.9,53,50,000/- and for costs of the suit.)

1. The suit is filed for recovery of a sum of Rs.9,53,50,000/- from the first, third and fourth Defendants. The Plaintiff entered into an Agreement dated 27.11.2008(the Agreement) with the first Defendant, which is a partnership firm in which the third and fourth Defendants are partners. The second Defendant is not a party against whom relief is prayed for. Therefore, the first, third and fourth Defendants are collectively referred to in this judgment as the Contesting Defendants. Under the Agreement, the Plaintiff engaged the services of the first Defendant to produce a Tamil movie, which was described as Production No.6 since it was untitled. The Agreement provided that the first Defendant should commence production of the movie on 10.12.2008 and complete the entire production of the first print before 05.04.2009. The Agreement provided for the payment of a sum of Rs.13,50,00,000/- by the Plaintiff to the first Defendant towards funding the cost of production as per the schedule set out in clause 2 thereof. In clause 3, it was recorded that the Plaintiff had paid an advance amount of Rs.2,50,00,000/- which was acknowledged by the first Defendant. In case the first Defendant did not complete the movie by the first week of April 2009, the Agreement provided for the payment of interest by the first Defendant at 24% per annum on the entire sum of Rs.13,50,00,000/- until the date of completion and handing over of the first copy of the movie to the Plaintiff. The Plaintiff was declared as the producer of the movie and the negative right holder. In terms of and pursuant to the Agreement, the Plaintiff paid the first Defendant a sum of Rs.4,25,00,000/- in the aggregate, including the sum of Rs.2,50,00,000 which was acknowledged therein. The receipt of the said sum in several tranches was acknowledged by the first Defendant by counter signing, in acceptance, a letter dated 12.02.2010 from the Plaintiff to the first Defendant (the Letter). According to the Plaintiff, the first Defendant did not commence production of the movie. The suit for recovery of a sum of Rs.9,53,50,000/- was filed in the above facts and circumstances.

2. The Plaintiff states that the receipt of the sum of Rs.4,25,00,000/- was acknowledged by the Contesting Defendants. In spite of receiving the said amount, the Contesting Defendants did not take any steps to proceed with the production of the movie. Therefore, the Plaintiff asserts that the Contesting Defendants committed breach of the Agreement. Before filing the present suit, the Plaintiff filed a suit in O.S.No.451 of 2013 on the file of the 8th Assistant City Civil Court at Chennai seeking to prevent the first, third and fourth Defendants from undertaking, commencing or releasing movies of third parties before completing the movies of the Plaintiff. In the said suit, the Plaintiff applied for and obtained leave to sue for damages by filing a separate suit. The Plaintiff states that the Agreement provides for payment of interest at 24% per annum on amounts received by the first Defendant, and, therefore, the Plaintiff is entitled to interest at 24% per annum on the sum of Rs.4,25,00,000/-. The Plaintiff also asserts that it is entitled to default interest on the total sum of Rs.13,50,00,000/- from 10.12.2003 to 05.04.2009. Thus, the Plaintiff claims an aggregate sum of Rs.9,53,50,000/-

3. The Defendants deny these claims. The first and third Defendants filed a common written statement. Likewise, the second and fourth Defendants filed a common written statement disclaiming liability and involvement in the relevant transactions. The first and third Defendants state that the Agreement provided that the Plaintiff should pay a sum of Rs.13,50,00,000/- as per the

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top