SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2023 Supreme(Mad) 3336

IN THE HIGH COURT OF JUDICATURE AT MADRAS
THE HON'BLE MR. JUSTICE ABDUL QUDDHOSE
M/s. Chemfab Alkalis Ltd. - Plaintiff
Versus
State Bank of India and ors. – Defendants
C.S.No.466 of 2009
Decided On : 18-12-2023

Advocates:
Advocate Appeared:
For the Plaintiff : Mr.Srinath Sridevan Senior Counsel for Mr.Bhagavath Krishnan
For the Defendant : Mr.M.L.Ganesh

IMPORTANT POINT
Strict compliance with the terms of a letter of credit is essential for payment; any discrepancies in the documents presented invalidate the entitlement to payment.

Headnote:

BANK GUARANTEE - LETTER OF CREDIT DISPUTE - Order IV Rule I of Madras High Court Original Side Rules, Order VII Rule 1 of C.P.C. - The court analyzed the discrepancies in the performance bank guarantee issued by the second defendant compared to the approved format in the letter of credit. It emphasized that strict compliance with the terms of the letter of credit is essential for payment. The court concluded that the first defendant bank was not obligated to disburse payments due to these discrepancies, thereby protecting the plaintiff's interests against potential fraud.

Fact of the Case:

The plaintiff entered into a sales contract with the third defendant for a salt washery plant, agreeing to pay a total of Euro 3,70,000. The plaintiff paid an advance and was to open a letter of credit for the remaining amount. Discrepancies arose regarding the performance bank guarantee provided by the third defendant, leading the plaintiff to seek a declaration that the defendants were not entitled to payment under the letter of credit.

Finding of the Court:

The court found that the performance bank guarantee issued by the second defendant did not conform to the approved format in the letter of credit. The discrepancies were significant enough to prevent the first defendant bank from making any payments to the third defendant.

Issues: 1. Whether the bank guarantee issued by the second defendant is in the stipulated format? 2. Whether there are discrepancies in the bank guarantee compared to the approved format? 3. Whether the bank guarantee is payable? 4. Whether the third defendant accepted the performance trial run results? 5. Whether the third defendant can invoke the letter of credit without conducting a performance test? 6. Whether the court has jurisdiction over the case against the second and third defendants? 7. Whether the plaintiff is entitled to the reliefs sought?

Ratio Decidendi: The court held that strict compliance with the terms of the letter of credit is mandatory. Any discrepancies in the documents presented, including the performance bank guarantee, invalidate the entitlement to payment under the letter of credit. The court also noted that the bank's obligation is limited to the documents presented and does not extend to the underlying transaction.

Final Decision: The court decreed in favor of the plaintiff, declaring that the second and third defendants are not entitled to any payment under the letter of credit and issued permanent injunctions against them and the first defendant from making any payments under the letter of credit.

JUDGMENT :

PRAYER: Plaint filed under Order IV Rule I of Madras High Court Original Side Rules and Order VII Rule 1 of C.P.C. for the following reliefs:

a) For a Declaration that the Defendants 2 & 3 are not entitled to claim payment of any sum under the letter of Credit bearing No.0702408IM0000782 dated 10-09-2008 issued by the 1st Defendant; and

b) For Consequential Permanent Injunction restraining the Defendants 2 & 3 from claiming payment of any sum under the letter of Credit bearing No.0702408IM0000782 dated 10-09-2008 issued by the 1st Defendant ; and

c) For Consequential Permanent Injunction restraining the 1st Defendant from making payment of any sum under the letter of Credit bearing No.0702408IM0000782 dated 10-09-2008 issued by the 1st Defendant;

d) for costs of the suit.

This suit has been filed, seeking the following reliefs:

    a) For a Declaration that the Defendants 2 & 3 are not entitled to claim payment of any sum under the letter of Credit bearing No.0702408IM0000782 dated 10-09-2008 issued by the 1st Defendant; and

b) For Consequential Permanent Injunction restraining the Defendants 2 & 3 from claiming payment of any sum under the letter of Credit bearing No.0702408IM0000782 dated 10-09-2008 issued by the 1st Defendant ; and

c) For Consequential Permanent Injunction restraining the 1st Defendant from making payment of any sum under the letter of Credit bearing No.0702408IM0000782 dated 10-09-2008 issued by the 1st Defendant;

d) for costs of the suit.

2. The plaintiff has entered into a sales contract with the third defendant on 28.08.2008 and as per the sales contract, the plaintiff agreed to purchase salt washery plant manufactured by the third defendant for a total sales consideration of Euro.3,70,000/-. As per the sales contract, the plaintiff paid 20% as advance to the third defendant by way of bank transfer and for the balance 80%, the plaintiff committed to open a letter of credit as per the terms and conditions of the sales contract dated 28.08.2008. In the sales contract dated 28.08.2008, the third defendant had to conduct certain performance test runs. The third defendant was also obligated to provide a performance bank guarantee in favour of the plaintiff.

3. As per the terms of the sales contract dated 28.08.2008, the plaintiff on 12.09.2008 approached the first defendant and sought for a letter of credit. The third defendant has also provided a draft performance bank guarantee obtained from the third defendant's banker on 08.09.2008.

4. The machineries agreed to be purchased by the plaintiff from the third defendant were shipped by the third defendant from Spain on 13.02.2009 for delivery to the plaintiff. According to the plaintiff, the third defendant ran performance test runs of the machineries which were erected in the plaintiff's factory which were the imported machineries sold by the third defendant to the plaintiff on 30.04.2009. According to the plaintiff, the test runs could not be completed because one of the main components was not functioning properly. Therefore, according to the plaintiff, the third defendant failed to discharge its obligations under the sales contract dated 28.08.2008.

5. On 04.05.2009, the first defendant bank handed over a performance bank guarantee issued by the 2nd defendant on behalf of the 3rd defendant as per the sales contract dated 28.08.2008. According to the plaintiff, since the bank guarantee issued by the 2nd defendant was not in the approved format, the plaintiff by its letter dated 09.05.2009 sent to the first defendant bank and requested them not to disburse the sums as per the letter of credit. However, according to the plaintiff, the first defendant bank by its reply dated 12.05.2009 rejected the stand taken by the plaintiff and informed the plaintiff that payment will be made to the 3rd defendant as per the letter of credit. On 15.05.2009, the plaintiff replied to the first defendant bank, reiterating that the first defendant bank should not disburse the sums to

                    Click Here to Read the rest of this document
                    1
                    2
                    3
                    4
                    5
                    6
                    7
                    8
                    9
                    10
                    11
                    Judicial Analysis

                    AI

                    SupremeToday Portrait Ad
                    supreme today icon
                    logo-black

                    An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

                    Please visit our Training & Support
                    Center or Contact Us for assistance

                    qr

                    Scan Me!

                    India’s Legal research and Law Firm App, Download now!

                    For Daily Legal Updates, Join us on :

                    whatsapp-icon Back to top