SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2024 Supreme(Mad) 1719

IN THE HIGH COURT OF JUDICATURE AT MADRAS
ANITA SUMANTH, J.
Sasi Road Finishers and Engineering Contractor Rep. By its Managing Partner, B.Sangeethkumar, - Appellant
Versus
The Superintending Engineer, Highways Department – Respondent
W.P.No.14751 of 2024 & W.M.P.Nos.15991 & 15992 of 2024
Decided on : 20-06-2024

Advocates:
Advocate Appeared
For the Appellant : Mr.N.R.Elango, Senior Counsel For Mr.N.Manoharan
For the Respondents:Mr.J.Ravindran, Additional Advocate General Assisted by Mr.M.R.Gokul Krishnan Additional Government Pleader, Mr.S.Doraisamy for R5

IMPORTANT POINT
The court established that compliance with mandatory tender requirements and the avoidance of conflicts of interest are essential for valid participation in government tenders.

Headnote:

Tender - Writ Petition - Tamil Nadu Transparency in Tenders Rules 2000, 2012 - The court analyzed the conflict of interest provisions and the mandatory requirements for tender submissions, concluding that the petitioner's bid was invalid due to non-compliance with the Working Condition Certificate requirement.

Fact of the Case:

The petitioner, a registered partnership firm, sought to quash the rejection of its tender bid for a road widening project, arguing that the delay in obtaining a Working Condition Certificate (WCC) was not its fault and that the rejection was based on a conflict of interest.

Finding of the Court:

The court found that the petitioner's bid was invalid as it did not include the mandatory WCC, and the conflict of interest due to the relationship with another bidder was significant, leading to the rejection of the bid.

Issues: Whether the rejection of the petitioner's tender bid was lawful given the absence of a Working Condition Certificate and the alleged conflict of interest.

Ratio Decidendi: The court held that the absence of the WCC rendered the bid ineligible, and the relationship between the petitioner and another bidder constituted a conflict of interest, violating the principles of fairness in the tender process.

Result: The writ petition is dismissed.

ORDER :

Prayer : Writ petition filed under Article 226 of the Constitution of India praying to issue a writ of certiorarified mandamus calling for the records relating to the impugned orders (i) dated 17.05.2024 (Bid No.1046286) relating to Tender No .42/2023-2024/HDO dated 26.02.2024 passed by the 1st respondent, (ii) dated 25.03.2024 made in Na.Ka.No.Plant Certificate/E Va A/2024 and (iii) dated 04.04.2024 made in Na.Ka.No. Plant Certificate/E Va A/2024 passed by the 2nd respondent, quash the same and consequently direct the 2nd respondent to issue Working Condition Certificate of Plant and Equipment to enable the 1st respondent to

re-do the process of Technical Bid by including the petitioner’s name.

The petitioner is a registered partnership firm engaged in Government contract work from 1997. The subject-matter of this writ petition is an on-line tender notice relating to road widening issued by Uthangarai (H) C&M Sub-Division of the State Highways department for widening, from two land Paved Shoulders to Four Lane and Strengthening at KM 0/0 – 1/550 of connecting road between SIPCOT and Pochampalli – Kondamandapatti.

2. The tender notice was issued on 26.02.2024 and the documents were available for prospective bidders from 01.03.2024 on the Government website. The last date for submission of bids was 19.03.2024. The special conditions of contract made it mandatory for the bidder to enclose a Working Condition Certificate for plant and equipment (in short ‘WCC’) from the competent authority in the prescribed format. The certificate should have been obtained after the date of tender so as to ensure that the condition of plant and equipment was optimum. The special conditions made it more than amply clear that a bid unaccompanied by the WCC would be found ineligible.

3. The petitioner had submitted the application for WCC on 15.03.2024 to R1 both via email as well as through RPAD. However, unfortunately, as the mail had been sent after working hours, at 7.45 p.m. on a Friday evening, the request for WCC came to the attention of the respondents only on Monday i.e., 18.03.2024.

4. It is relevant to note that two separate applications for WCC had been sent under the cover of one email id being srfdharmapuri@gmail.com. The applications were on the letter-head of the petitioner firm and of P.Baskar, the petitioner’s father.

5. Since the respondents were of the view that there was a conflict of interest in the petitioner seeking WCC, both on its behalf as well as on behalf of his father, a competing bidder, a reply was sent to the petitioner by e-mail on 18.03.2024 asking that separate applications be made for issuance of WCC by the two bidders.

6. In the meantime, the petitioner had, on 17.03.2024, submitted its bid without enclosing the WCC. Condition 2 under the special condition for plant and machineries states clearly that ‘the working conditions for the above machineries obtained after the date of tender notice from the Divisional Engineer (QC) concerned should be uploaded in original, the tender received without the above certificate shall be rejected’. Thus, the petitioner’s bid without the mandatory enclosure of the WCC was technically invalid.

7. Vide letter dated 25.03.2024, R2 states that the petitioner’s bid was ineligible as the request for WCC had been received from the petitioner only on 25.03.2024, beyond the last date of tender, being 19.03.2024. On 02.04.2024, the petitioner points to his requisition dated 15.03.2024 and that such request had been received by R2 on 18.03.2024 (by RPAD). In fact, the request sent by e-mail had been received on 15.03.2024 itself.

8. On 04.04.2024, the petitioner’s bid is rejected by R2 for the aforesaid reasons i.e., that the request for WCC had been made in common by the petitioner and his father, and that the petitioner’s bid had been submitted without enclosing the WCC. However, as that communication has been issued by R2, the Divisional Engineer, who is not the Tender Inviting Authority

        Click Here to Read the rest of this document
        1
        2
        3
        4
        5
        6
        7
        8
        9
        10
        11
        SupremeToday Portrait Ad
        supreme today icon
        logo-black

        An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

        Please visit our Training & Support
        Center or Contact Us for assistance

        qr

        Scan Me!

        India’s Legal research and Law Firm App, Download now!

        For Daily Legal Updates, Join us on :

        whatsapp-icon Back to top