SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Mad) 4583

IN THE HIGH COURT OF JUDICATURE AT MADRAS
J. NISHA BANU, R.KALAIMATHI
Army Welfare Housing Organisation(AWHO) – Appellant
Versus
Nagarajan Vasudeva Rao – Respondent


Advocates:
Advocate Appeared:
For the Appellants: Mr.A.R.L.Sundaresan, Senior Counsel for Mr.V.G. Suresh Kumar
For the Respondents: Mr.Ramasubramaniam Raja

Judgement Key Points

Key Points: - The Court holds that a "No Profit No Loss" organization remains subject to RERA registration and liability for delays; ongoing projects without completion certificates must be registered (!) (!) (!) (!) . - Section 18(1) enforces interest to be paid for delay till possession if the allottee does not withdraw, and compensation may be awarded under Section 18, with remedies and limits governed by Rule 18 and other provisions; the appellate authorities have rightly granted interest at SBI MCLR + 2% and mandated mental agony compensation and litigation costs (!) (!) (!) (!) (!) (!) (!) . - Section 72 provides factors to be considered in awarding compensation (disproportionate gain, loss, repetition, and other just factors); the court confirms that these factors are guidance for quantum, while interest under Section 18 is separate (!) (!) (!) (!) . - Registration is mandated for ongoing projects under Section 3, including projects deemed structurally completed but not fully completed; exemptions under Rule 2(h)(ii) were considered but ultimately the project was held to require registration (!) (!) (!) (!) . - Appeals by AWHO were dismissed; TNREAT and TNRERA orders directing registration and payment of interest and compensation were upheld (!) .

What is the applicability of the Real Estate (Regulation and Development) Act to a "No Profit No Loss" organization in relation to registration and liability for delays?

What are the grounds and standards for awarding interest, compensation, and mental agony under Section 18 and Section 72 of the RERA Act, including whether uniform interest rates and criteria satisfy due process?

How do Section 3 registration requirements apply to ongoing projects deemed structurally complete but not fully completed, and what is the consequence for non-registration in such contexts?


Table of Content
1. introduction of the case and parties involved. (Para 1 , 2)
2. key issues to be resolved under rera. (Para 3 , 8)
3. findings of the adjudicating authority. (Para 5 , 6 , 12)
4. arguments from the appellants regarding their liability under rera. (Para 10 , 13 , 14 , 15 , 18)
5. arguments from appellants concerning quantification of compensation. (Para 19 , 20 , 22)
6. examination of legal principles concerning interest liability. (Para 23 , 27 , 28)
7. court's observation on regulatory compliance. (Para 30 , 31)
8. conclusion on the necessity for project registration. (Para 32 , 33 , 34)
9. final ruling of the court. (Para 36)

JUDGMENT :

J. Nisha Banu, J

The above appeals in C.M.S.A.Nos.23 to 25 of 2024 and 30 & 31 of 2023 have been filed by the Army Welfare Housing Organisation (AWHO) under Section 58 of the Real Estate (Regulation & Development) Act, 2016 (hereinafter referred to as "the Act"), read with Section 100 of the CIVIL PROCEDURE CODE , challenging the impugned orders dated 20.12.2023 and 21.04.2023 passed in Appeal Nos. 12, 13 & 51 to 53 of 2023, on the file of the Tamil Nadu Real Estate Appellate Tribunal, Chennai (hereinafter referred to as "the Tribunal"). Th

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top