IN THE HIGH COURT OF JUDICATURE AT MADRAS
M. Dhandapani, J.
The Chairman & Managing Director TANGEDCO – Petitioner
Versus
Tamil Nadu Electricity Ombudsman - Respondent
W.P. NOS.27115, 27131, 27120, 27122, 27124, 27177, 27126 & 27130 OF 2021 W.P. NO. 28186 OF 2022 W.P. NOS. 34600, 34604, 34605, 34610, 34021, 34614, 34618 & 34625 OF 2023 AND W.M.P. NOS. 28598, 28599, 28587, 28590, 28594, 28603 & 28585 OF 2021 W.M.P. NOS. 4999, 3295, 2864, 4278, 4279, 4280, 4273, 5019, 21191, 21195 & OF 2022 W.M.P. NOS. 34553, 34573, 34522, 34523, 34528, 34531, 34535, 34536, 34554, 34558, 34562, 34564, 34569, 34570, 34572 OF 2023
Decided On : 07-11-2024
ORDER :
M. Dhandapani, J.
Two sets of writ petitions have been filed, viz., one challenging the order passed by the Tamil Nadu Electricity Ombudsman (for short ‘TNEO’) and the other by the Tamil Nadu Electricity Regulatory Commission (for short ‘TNERC’), in and by which both the authorities have directed the refund of the excess charges collected from the respective petitioners, who are respondents herein, with regard to installation of Distribution Transformers. The said orders are put to test by the petitioners by filing the present writ petitions.
Facts in the writ petitions assailing the order of TNEO :
2. It is the case of the petitioners that the respective 2nd respondents had developed a group housing project consisting of multiple apartments, viz., dwelling units and had sought new LT Domestic connection vide application application on various dates, as stated in the affidavit and the respective Assistant Engineer had arrived at the total required load and sanction was also accorded.
3. It is the further case of the petitioners that based on the above order, estimate was given by the Assistant Engineer vide slip for the respective 2nd respondents to pay the sum as mentioned in the slip towards for laying cable, erection of four pole structure, erection of distribution transformer, DT metering, laying of UG cable and erection of LT switch gear along with GST charges. The said amount was also paid by the 2nd respondent on 3.9.2020 and service connections were effected to the entire dwelling units.
4. It is the further case of the petitioner that after payment of the charges on 3.9.2020 and availing connection, the respective 2nd respondents preferred a complaint before the Consumer Grievance Redressal Forum, Chennai, EDC/South 2 challenging the levy of estimate charges as mentioned in the respective slips. It was the case of the respective 2nd respondents herein before the Consumer Grievance Redressal Forum, Chennai, that inclusion of price/cost of transformers, equipment, cable, line cost in the category of estimate charges is contrary to TNERC Regulations when the respective 2nd respondents had already provided sufficient space for development of substation and for erection of transformers. It was the further contention of the respective 2nd respondents that the petitioners herein did not seek the approval for levy of estimate charges from TNERC and, therefore, the respective 2nd respondents had no other option, but to pay the estimate charges due to the undue delay in processing the application of the 2nd respondent.
5. It is the further case of the petitioners that counter affidavit was filed in the said petition claiming that the estimated charges collected is as per Regulation 45 (1) and Regulation 29 (16) of the Tamil Nadu Electricity Distribution Code (for short ‘Distribution Code’).
6. It is the further case of the petitioners that the respective 2nd respondent preferred an appeal before the 1st respondent herein in which counter was also filed by the petitioners herein and after hearing both the parties, the 1st respondent passed the respective order as impunged in the respective writ petitions directing the petitioners to revise the estimate and to refund the excess charges including the equipment cost to the respective 2nd respondents within a period prescribed in the said order. Further direction was also given by the 1st respondent to revise the estimate for all such similar cases and refund the excess charges collected to the consumer. Aggrieved by the said order in and by which order of refund of excess charges was made to the 2nd respondent herein as also to the persons, who have not approached the 1st respondent, the present set of writ petitions have been filed.
Facts in the writ petitions assailing the order of TNERC :
7. It is the case of the petitioners that the respective respondents are the owners of the flat and they had applied for domestic service connection for their newly constructed apartment. It is t
Distribution transformer installation costs must be borne by the licensee, while consumers are only liable for connection supply charges.
Commission constituted under Section 17 of the 1998 Act is an expert body and the determination of tariff which has to be made by the Commission involves a very highly technical procedure, requiring ....
Electric distribution companies cannot charge consumers for transformer costs as such charges violate existing regulations; statutory directives from regulatory authorities must be adhered to without....
A distribution licensee cannot recover electricity dues from a new owner without establishing a nexus with the previous owner, and the requirement for a 'No Dues Certificate' is directory.
The jurisdiction to address disputes regarding unauthorized installations of electrical infrastructure lies with the District Magistrate, not the GRF, as per the provisions of the Electricity Act and....
Provisions for duty of distribution licensee and open access has to be read conjointly.
New owners of properties are liable to pay fixed electricity charges of prior tenants, while charges deemed unlawful cannot be enforced against them.
The distribution licensee cannot impose additional fees for transformer losses on consumers billed at low tension rates, as per established tariff regulations.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.