SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Ori) 955

IN THE HIGH COURT OF ORISSA AT CUTTACK
HARISH TANDON, CJ.
M/s. Anand Granites Exports Private Limited – Petitioner
Versus
Mr. Prabhudayal Agrawal - Opposite Party
ARBP No.01 of 2025
Decided On : 26-08-2025

Advocates Appeared:
For the Petitioner:Mr. Gautam Misra, Senior Advocate, Mr. J.R. Deo, Advocate
For the Opposite Party :Mr. Vaibhav Shukla, Advocate

The court's authority under Section 11 of the Arbitration Act restricts to determining the existence of an arbitration agreement, deferring substantive disputes to the arbitrator.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 11 - Dispute concerning a raising contract - Application filed for appointment of an arbitrator resisted on grounds of jurisdiction and scope of arbitration agreement - Court reiterates that it must first ascertain the prima facie existence of an arbitration agreement without delving into the merits of the dispute - Validity of disputes raised under a signed contract must be determined, but specific claims can be assessed by the arbitrator later. (Paras 10, 16, 25, 27)

(B) Arbitration Agreement and Clause - Definition and scope of arbitration agreements laid out in Section 7 - Judicial precedents indicate that courts must limit themselves to examining the existence of the arbitration agreement and not the merits of any ancillary disputes at this preliminary stage. (Paras 13, 18)

Facts of the case:
The petitioner sought appointment of an arbitrator under an arbitration clause in a raising contract dated 18th March, 2010 concerning mineral extraction. The opposite party contested the same citing disputes beyond the arbitration agreement and ongoing litigation regarding an irrevocable power of attorney. (Paras 1, 5)

Findings of Court:
The court found prima facie existence of an arbitration agreement, rejecting the opposition's claims about disputes falling outside its purview and appointing an arbitrator to decide the matter. (Paras 24, 27)

Issues: The core issue was whether the dispute raised was arbitrable under the agreement in light of ongoing civil litigation. (Paras 6, 10)

Ratio Decidendi: The court affirmed it must only ascertain the existence of the arbitration agreement at this stage, while substantive issues related to the dispute should be deferred to the arbitrator. (Paras 16, 27)

Result: Application for appointment of arbitrator allowed.

Table of Content
1. background of mining lease and contracts. (Para 1 , 2 , 3 , 4 , 5)
2. dispute arisen over the arbitration agreement. (Para 6 , 8 , 9)
3. arguments for and against arbitration. (Para 10 , 11)
4. court's scrutiny of arbitration agreement. (Para 12 , 13 , 14 , 15 , 16 , 17 , 18)
5. principle of competence-competence and jurisdiction. (Para 19 , 20 , 21 , 22 , 23 , 24 , 25)
6. effect of legislative changes on arbitration agreement. (Para 26)
7. final order and appointment of arbitrator. (Para 27 , 28)

JUDGMENT :

HARISH TANDON, CJ.

1. An application under Section 11 of the Arbitration and Conciliation Act, 1996 (in short, 'the Act') filed by the petitioner is resisted by the opposite party primarily on the premise that the dispute raised in the notice invoking arbitration clause contained in the raising contact dated 18th March, 2010 is beyond the purview of the arbitration agreement/arbitration clause contained therein.

2. Undeniably, the opposite party was granted mining lease for an area covering 262.27 acres of land situated in Tantra (Khata No.35), Rangua (Khata No.31) and Bandhal (Khata Nos.30 and 39) under Bonai Sub-Division of Sundargarh district in the State of Odisha on the basis of a mining lease deed dated 25th January, 2002. Previous to entering into the said raising contract dated 18th March, 2010, a similar contract was entered into between the opposite party and one M/s. Gayatri Mining Pvt. Limited on 14th August, 2009 but that could not materialize and subsequently, the opposite party cancelled the said previous contract and approached the petitioner to operate and run the said mine on the terms and conditions embodied in the raising contract dated 18th March, 2010. Indubitably, the said raising contract dated 18th March, 2010 contains an arbitration agreement/clause in the event any disputes arise between the parties thereto in relation to or touching upon any of the terms and conditions embodied therein. Simultaneously, a tripartite agreement of the even date was also executed between the parties hereto and the said M/s. Gayatri Mining Private Limited for discharge of several statutory dues including the dues of the said M/s. Gayatri Mining Private Limited to the tune of Rs.14.00 crores. The validity of the said raising contract dated 18th March, 2010 was agreed till the ultimate end of the mining lease which includes renewal and/or revival period or till the complete exhaustion of the detected mineral deposited in the schedule land, whichever is earlier.

3. In order to facilitate the smooth and continuous extraction of the minerals from the said mining lease which is commonly known as Tantra Bauxite Mines, a power of attorney was also executed in favour of an employee of the petitioner on 10th May, 2010 wherein clause 36 thereof provides that the same is irrevocable and cannot be revoked at the sweet will of the opposite party. Apropos the same, several affidavits were also executed and affirmed by the opposite party so that the period of mining lease can be renewed and/or extended to be transferred in favour of the petitioner and it appears from the documents annexed and from the stand of the parties that considerable amount of money was also paid both to the statutory authorities and also to a 3rd party in discharge of the obligation imposed upon the opposite party.

4. Amidst the aforesaid action and/or steps being taken, the Government of Odisha adopted a policy to enhance the tenure of lease to 50 years subject to fulfillment of the terms and conditions incorporated therein and to avail such opportunity, the petitioner engaged M/s. Earth and Environment Consultancy Services, a service provider to process the application for renewal and/or extension of lease and also to have clearances from various departments upon payment of the statutory dues.

5. It is a specific stand of the petitioner that despite having complied with all the statutory impositions including deposit of the statutory amount, the opp

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top