IN THE HIGH COURT OF ORISSA AT CUTTACK
HARISH TANDON, CJ., MURAHARI SRI RAMAN, J.
M/s. Jalaram Transport - Petitioner
Versus
Mahanadi Coalfields Limited and others - Opposite Parties
W.P.(C) No.37718 of 2023
Decided On : 04-02-2026
| Table of Content |
|---|
| 1. demand for penalty after significant delays. (Para 1 , 2) |
| 2. arguments regarding procedural fairness and contract terms. (Para 4 , 5) |
| 3. court analysis on penalties, contract obligations, and natural justice. (Para 6 , 7 , 8) |
| 4. quashing of penalty demand and orders for recovery. (Para 9 , 10) |
JUDGMENT :
HARISH TANDON, CJ.
1. The petitioner challenges the notice of demand dated 12th November, 2023 issued by opposite parties-MCL to recover a sum of Rs.9,15,980.70 from the running contract of the petitioner under NIT-843 dated 25th February, 2022 of Ananta OCP, Jagannath Area on account of penalty.
2. A prelude to the litigation is required to be adumbrated to consider the points raised in the instant litigation. The Notice Inviting Tender (NIT) was floated on 20th March, 2012 for transportation of crushed coal by tippers from feeder breaker of Jagannath colliery to siding I, III and IV of Jagannath Area for a total quantity of 38 lakh Tes. The petitioner was adjudged as the successful bidder and deposited the bank guarantee as earnest money and two further guarantees towards the performance security and the security deposit with opposite party No.1. The period of completion of the entire work was fixed for 365 days. Pursuant to the said NIT and the petitioner having adjudged as a successful bidder, the letter of acceptance was issued on 13th June, 2012 followed by a work order dated 21st June, 2012. The date of completion of work was fixed at 3rd July, 2013, which according to the petitioner was duly executed and the payments were released from time to time except a paltry sum of Rs.3,28,398/-.
2.1. It is stated in the petition that after a lapse of ten years, the impugned demand is raised without assigning any reason therefor, nor adhering to the principle of natural justice. It is averred in the writ petition that Clause 6.2 of the General Terms and Conditions (GTC) of the Contract clearly provides that the penalties shall be calculated on a monthly basis and in order to give an opportunity to the contractor to make up the shortfall in succeeding three months within the stipulated time of completion and on fulfilling the said shortfall, the said penalty shall be released. On the basis of the said Clause, it is a specific case of the petitioner that once the entire amount has been released except the said paltry sum, the imposition of penalty after a gap of ten years is whimsical, arbitrary and also in violation of the terms and conditions embodied in the contract.
2.2. On the other hand, the opposite parties took a stand that the petitioner failed to comply the safety terms and conditions of the contract and also to deploy those tippers which have a requisite safety features. A notice was issued to the petitioner on 9th October, 2012 with an advice to deploy those tippers which have safety features, but the same was challenged by the petitioner in W.P.(C) No.20844 of 2012 before this Court. In the said writ petition, the petitioner challenged sub-clause (1) (i) (vi) and (xviii) of Clause- 39.00 as illegal and inoperative. The interim order was passed in the said petition until 12th April, 2019 when the petitioner withdrew the same. It is averred in the counter affidavit that because of the interim order being operative, no further steps could be taken. Responding to Clause 6.2 of the GTC, it is averred that the hindrance register maintained jointly by the management and the contractor would indicate not only the daily progress, but the shortfall, if any, and, therefore, imposition of penalty for such shortfall in terms of the said Clause cannot be said to be perverse and illegal. Lastly, it is averred that since the petitioner is also awarded other contract, the said amount can be recovered from the RA bills which in fact has been indicated in the impugned letter.
3. While admitting the instant writ petition, an interim order was passed on 12th February, 2024 restraining the opposite parties from making any further r
M.P. Power Management Company Limited v. Sky Power Southeast Solar India Private Limited
Mohinder Singh Gill v. The Chief Election Commissioner, New Delhi
An authority must adhere to contract terms, including timely communication of penalties and an opportunity to rectify, or face quashing of arbitrary demands.
Point of law: Stated simply, 'unjust enrichment' means retention of a benefit by a person that is unjust or inequitable. 'Unjust enrichment' occurs when a person retains money or benefits which in ju....
Point of Law : Commercial Vehicles - Toll plazas/posts/barriers - Collection of Toll Tax – Whether rights of petitioner is violated - Conduct of parties is governed by the Contract Agreement and the ....
Public authorities must act fairly and cannot arbitrarily terminate contracts without justification, reinforcing the legitimacy of expectations within public-private partnerships.
State actions in contractual relationships must adhere to principles of fairness and non-arbitrariness as mandated by Article 14 of the Constitution of India.
The court reaffirmed that contractual disputes with an arbitration clause are not maintainable under Article 226 unless exceptional circumstances arise, emphasizing lawful forfeiture of security for ....
(1) Disputes arising out of purely contractual obligations cannot be entertained by High Court in exercise of extra-ordinary writ jurisdiction.(2) A wrong doer ought not to be permitted to make profi....
Parties to a contract must adhere to its terms despite unforeseen circumstances like force majeure, and disputes arising from such a contract should be resolved through contractual mechanisms, not ju....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.