SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Ori) 636

IN THE HIGH COURT OF ORISSA AT CUTTACK
Sanjeeb Kpanigrahi, J.
M/s. Jindal Stainless Steel Limited @ M/s. Jindal Stainless Ltd., New Delhi - Petitioner
Versus
M/s. Newton Engineering and Chemicals Ltd., Gujarat - Opposite Party
W.P.(C) No.24869 of 2025
Decided On : 22-01-2026

Advocates Appeared:
For the Petitioner: Mr. Amit Pattnaik, Adv.
For the Opposite Party : Mr. Durga Prasad Nanda, Sr. Adv. along with associates

The court emphasized that limitation is a jurisdictional issue in arbitration, and mere disagreement with findings does not warrant interference under supervisory jurisdiction.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 37 - Maintainability of Writ Petition under Article 227 - The court considered whether the claim raised was ex facie barred by limitation, highlighting that limitation is a jurisdictional issue that cannot be ignored. The petitioner argued against the findings of the Arbitral Tribunal and the appellate courts, claiming the tribunal misapplied the law regarding the commencement of claims. (Paras 24, 61)

(B) Courts and Tribunals - The court reaffirmed the principle that supervisory jurisdiction must be exercised sparingly, especially concerning arbitral awards, emphasizing that mere disagreement with findings is insufficient for interference. (Paras 29, 60)

Facts of the case:
Writ petition filed by a corporate entity questioning the dismissal of an appeal against an arbitral award, which was alleged to be barred by limitation. The petitioner contended the rights to apply under the Limitation Act were not considered effectively. (Paras 1-8)

Findings of Court:
The court held that the writ petition was maintainable in principle; however, there were no exceptional circumstances to justify intervention, and the findings on limitation were upheld as plausible. (Paras 24, 61)

Issues: The primary issue was whether a writ petition under Article 227 is maintainable against an appellate order under Section 37 of the Arbitration Act, and if so, whether the supervisory jurisdiction should be exercised. (Paras 24, 25)

Ratio Decidendi: The court clarified that while the maintainability of the writ was recognized, there was insufficient justification for interference as the findings on limitation by the Arbitral Tribunal were not shown to be perverse or without jurisdiction. (Paras 59, 61)

Result: Writ Petition dismissed.

Table of Content
1. factual background of the case (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8 , 9)
2. arguments by the petitioner regarding limitation (Para 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17)
3. arguments by the opposite party opposing the petition (Para 18 , 19 , 20 , 21 , 22 , 23)
4. consideration of maintainability of writ petition (Para 24 , 25 , 26 , 27 , 28 , 29 , 30 , 31 , 32)
5. insights on judicial restraint in arbitral matters (Para 33 , 34 , 35 , 36 , 37 , 38 , 39 , 40 , 41 , 42 , 43 , 44 , 45 , 46 , 47 , 48)
6. application of legal principles to the case (Para 49 , 50 , 51 , 52 , 53 , 54 , 55 , 56 , 57 , 58 , 59 , 60)
7. conclusion and dismissal of writ petition (Para 61 , 62 , 63 , 64)

JUDGMENT :

Sanjeeb K Panigrahi, J.

1. The present Writ Petition has been instituted by M/s Jindal Stainless Steel Limited @ M/s Jindal Stainless Limited, calling into question a chain of arbitral and post-arbitral proceedings culminating in the dismissal of an appeal under Section 37 of the Arbitration and Conciliation Act, 1996. The challenge is directed against the judgment dated 26.07.2025 passed by the learned District Judge, Khurda, Bhubaneswar in Arb. Appeal No.16 of 2024, whereby the appeal preferred by the petitioner was dismissed, affirming both the arbitral award dated 31.01.2021 and the order dated 06.08.2024 passed by the learned Senior Civil Judge (Commercial Court), Bhubaneswar.

I. FACTUAL MATRIX OF THE CASE:

2. The factual backdrop dates back to August, 2005, when the petitioner floated a tender for the supply, fabrication, erection, testing and commissioning of an L.P. piping system and storage tanks for the 2×125 MW CPP Project at Duburi, Odisha. The opposite party participated in the tender process and was selected as the lowest bidder. A letter of intent was issued on 12.12.2005, followed by a purchase order dated 29.8.2006. The work contract stipulated specific milestones, requiring commissioning of the first unit within eight months and the second unit within eleven months from the date of the letter of intent.

3. It is the admitted position that the opposite party did not complete the work within the stipulated time, despite extensions having been granted up to 30.9.2007. On 15.3.2008, the opposite party abandoned the work, compelling the petitioner to engage a third-party contractor, namely M/s Shakti Engineering, on 17.4.2008 for execution of the remaining work. These events are not in dispute between the parties.

4. On 21.8.2008, the opposite party issued a letter demanding release of the final bill, which has been consistently described as the “first demand.” The said demand was followed by a notice dated 7.1.2009 seeking payment against the final bills submitted on 21.8.2008.

5. Thereafter, on 25.4.2012, the opposite party once again issued a demand notice seeking release of outstanding dues.

6. The petitioner, by its letter dated 27.7.2012, denied the claim of the opposite party on the ground that it was barred by limitation. Subsequently, a legal notice dated 13.2.2013 was issued by the opposite party.

7. On 18.4.2013, the opposite party invoked arbitration by issuing a letter of reference under Section 21 of the Arbitration and Conciliation Act, 1996, invoking Clause 11 of the purchase order.

8. Arbitration Proceeding No.1 of 2013 culminated in an award dated 31.1.2021. By a majority view, the Arbitral Tribunal held that the claims were not barred by limitation and allowed the claims, including an additional claim inserted during the arbitral proceedings. A dissenting opinion, however, held that the claims were time-barred, having arisen from the first demand dated 21.8.2008.

9. Aggrieved, the petitioner filed an application under Section 34 of the Arbitration and Conciliation Act before the learned Senior Civil Judge (Commercial Court), Bhubaneswar, registered as Arb.(P) No.23 of 2021. By order dated 6.8.2024, the Commercial Court dismissed the application. The petitioner thereafter preferred an appeal under Section 13 of t

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top