SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Sikk) 80

THE HIGH COURT OF SIKKIM: GANGTOK
BISWANATH SOMADDER, C.J., BHASKAR RAJ PRADHAN, J.
Sikkim Urja Limited, (Formerly: Teesta Urja Limited), Through Authorized Representative Satyan Sood – Appellant
Versus
Abir Infrastructure Pvt. Ltd., Through its Managing Director – Respondent 
Arb. A. No. 01 of 2024
Decided On : 30-05-2025 

Advocates Appeared:
For the Appellant :Mr. Anubhav Sinha, Mr. Akshaya Babu V., Mr. Rinzing Dorjee Tamang and Mr. Varun Pradhan, Advocates
For the Respondents:Mr. R.S. Sravan Kumar and Mr. Sishir Mothay, Advocates, Mr. Biswabrata Basu Mallick, Ms Allakha, Mr. Pramit Chhetri and Mr. Arun Rai, Advocates.

Statutory liability to pay welfare cess under labor legislation falls upon the contractor as the employer. Such liability is inherent to the statute, cannot be reallocated via contract clauses based on administrative delays in local enforcement, and failure to apply this legal principle is a patent illegality.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Sections 34, 37 - Labour and Industrial Law - Welfare cess liability - Statutory mandate - Whether administrative implementation delay constitutes 'change in law' - Held, liability for payment of welfare cess under relevant labor enactments is a statutory obligation on the contractor as the defined employer; Implementation of such legislation is not contingent upon the constitution of state-specific boards or administrative notifications; Misinterpretation of statutory burden and deviation from binding precedents by an arbitral tribunal manifests as patent illegality and contravention of the fundamental policy of law. (Paras 35, 38, 41, 43).

(B) Appellate Jurisdiction - Scope - Interference with arbitral award - Court is empowered to set aside an award if it disregards binding legal principles, misinterprets statutes to negate mandatory obligations, or reflects perversity that shocks the conscience of the court, thereby failing the test of fundamental policy of law. (Paras 38, 43).

Facts of the case:
The appellant challenged an order of the lower court that dismissed a petition to set aside an arbitral award. The dispute arose concerning the payment of labor welfare cess. The contractor argued that because the relevant welfare legislation was enforced in the region years after the contract was signed, the obligation to pay the cess constituted a 'change in law' under the contract, shifting the liability to the entity commissioning the work. The arbitral tribunal and the lower court agreed with the contractor's position.

Findings of Court:
The Appellate Court concluded that the statutes governing the welfare levies had been in force at a national level since their enactment, long before the contract's execution. A contractor's statutory liability to pay welfare cess is an independent legal obligation that remains unaffected by the timing of state-level administrative implementation or the formation of local welfare bodies. The tribunal's decision to shift this mandatory burden was found to be legally erroneous and against the established policy of the law.

Issues: Whether the delay in the administrative adoption of welfare legislation allowed for a shifting of statutory payment liability under a 'change in law' contractual clause, and whether the award was sustainable in view of established apex court precedents regarding the nature of such welfare levies.

Ratio Decidendi: Statutory obligations cannot be bypassed through contractual interpretations which negate the specific intent of welfare legislation. Recognizing the contractor as the 'employer' under the welfare statutes, the court held that any award exempting the contractor from this primary liability, particularly in defiance of known apex court rulings, constitutes patent illegality and a breach of public policy.

Result: Appeal allowed; Impugned judgment and Arbitral Award set aside.

Table of Content
1. nature of the dispute involving the liability to pay labour welfare cess in a turnkey construction project. (Para 1 , 3 , 4 , 5)
2. parties' contentions regarding 'change in law' under the contract versus statutory liability for construction cess. (Para 6 , 7)
3. findings of the arbitral tribunal regarding the implementation date of statutes and the assignment of liability for cess. (Para 8 , 9 , 10 , 11)
4. the commercial court's interpretation of statutory implementation timing in the context of section 34 of the arbitration act. (Para 12 , 13)
5. examination of the statutory framework of the bocw act and cess act to determine liability for construction welfare cess. (Para 16 , 17 , 18 , 19 , 20 , 21 , 22 , 23 , 24 , 25 , 26 , 27 , 28 , 29 , 30 , 31 , 32)
6. critical analysis of the arbitral tribunal's failure to apply supreme court precedents and the incorrect interpretation of 'change in law'. (Para 33 , 34 , 35 , 36 , 37 , 38 , 39 , 40 , 41 , 42)
7. setting aside of the arbitral award based on patent illegality and contravention of fundamental policy of indian law. (Para 43 , 44 , 45)

JUDGMENT :

Bhaskar Raj Pradhan, J.

This is an appeal preferred under section 37 of the Arbitration and Conciliation Act, 1996 (for short, the Arbitration Act). The impugned judgment and order dated 14.08.2023 dismissed the petition filed by M/s Teesta Urja Ltd. [now, Sikkim Urja Limited (appellant)] under section 34 refusing to interfere with the arbitral award dated 01.10.2019 in favour of the respondents herein.

2. The grounds for interference under section 34 of the Arbitration Act are limited. When should a Court interfere under section 34 is clearly defined in the provision and amply clarified by the Hon'ble Supreme Court in its various judgments. On examination of the arbitral award, we find that the arbitral award is in conflict with the public policy of India, in that it is in contravention with the fundamental policy of Indian law. We also find that the arbitral award is vitiated by patent illegality appearing on the face of the award. The Arbitral Tribunal has also imposed the liability of payment of cess upon the appellant although section 3 of the Building and Other Construction Workers' Welfare Cess Act, 1996 (for short, the Cess Act, 1996) mandates that it is the respondent who are liable to pay it. While determining who is liable to pay the cess, the Arbitral Tribunal reversed the mandate of the law and imposed the liability upon the appellant instead. The arbitral award suffers from the vice of disregarding the two judgments of the Hon'ble Supreme Court in A. Prabhakara Reddy and Company vs. State of Madhya Pradesh and Others , (2016) 1 SCC 600 and M/s Dewan Chand Builders and Contractors vs. Union of India & Ors., [(2012) 1 SCC 101] Thus, the impugned judgment passed by the learned Commercial Court while exercising the powers under section 34 refusing to set aside such an arbitral award requires to be interfered with. We explain our reasons hereunder.

3. The claimant before the Arbitral Tribunal was the consortium of M/s Abir Infrastructure Pvt. Ltd. (respondent no.1 herein), M/s Navayuga Engineering Co. Ltd. (respondent no.2 herein) and M/s SEW Infrastructure Ltd. (respondent no.3 herein). The respondent therein was M/s Teesta Urja Ltd.

4. The consortium of the respondents along with M/s CGGC International Ltd, M/s CKD Hydro Power Pvt. Ltd, M/s SABIR Dam & Water Works Construction Co., was awarded the work for Turnkey execution of 1200 MW Teesta Stage-III of Hydroelectric Project in the State of Sikkim after a successful bid. For the said purpose various agreements were executed. The contracts were subject to arbitration for settlement of disputes. The contract was awarded on 18.04.2007 with subsequent amendments dated 26.05.2007. The contract was signed on 12.09.2007 and the project completed on 28.02.2017.

5. According to the Arbitral Tribunal, as stated in its award, the dispute arose with respect to the liability

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top