THE HIGH COURT OF SIKKIM: GANGTOK
BISWANATH SOMADDER, C.J., BHASKAR RAJ PRADHAN, J.
Sikkim Urja Limited, (Formerly: Teesta Urja Limited), Through Authorized Representative Satyan Sood – Appellant
Versus
Abir Infrastructure Pvt. Ltd., Through its Managing Director – Respondent
Arb. A. No. 01 of 2024
Decided On : 30-05-2025
| Table of Content |
|---|
| 1. nature of the dispute involving the liability to pay labour welfare cess in a turnkey construction project. (Para 1 , 3 , 4 , 5) |
| 2. parties' contentions regarding 'change in law' under the contract versus statutory liability for construction cess. (Para 6 , 7) |
| 3. findings of the arbitral tribunal regarding the implementation date of statutes and the assignment of liability for cess. (Para 8 , 9 , 10 , 11) |
| 4. the commercial court's interpretation of statutory implementation timing in the context of section 34 of the arbitration act. (Para 12 , 13) |
| 5. examination of the statutory framework of the bocw act and cess act to determine liability for construction welfare cess. (Para 16 , 17 , 18 , 19 , 20 , 21 , 22 , 23 , 24 , 25 , 26 , 27 , 28 , 29 , 30 , 31 , 32) |
| 6. critical analysis of the arbitral tribunal's failure to apply supreme court precedents and the incorrect interpretation of 'change in law'. (Para 33 , 34 , 35 , 36 , 37 , 38 , 39 , 40 , 41 , 42) |
| 7. setting aside of the arbitral award based on patent illegality and contravention of fundamental policy of indian law. (Para 43 , 44 , 45) |
JUDGMENT :
Bhaskar Raj Pradhan, J.
This is an appeal preferred under section 37 of the Arbitration and Conciliation Act, 1996 (for short, the Arbitration Act). The impugned judgment and order dated 14.08.2023 dismissed the petition filed by M/s Teesta Urja Ltd. [now, Sikkim Urja Limited (appellant)] under section 34 refusing to interfere with the arbitral award dated 01.10.2019 in favour of the respondents herein.
2. The grounds for interference under section 34 of the Arbitration Act are limited. When should a Court interfere under section 34 is clearly defined in the provision and amply clarified by the Hon'ble Supreme Court in its various judgments. On examination of the arbitral award, we find that the arbitral award is in conflict with the public policy of India, in that it is in contravention with the fundamental policy of Indian law. We also find that the arbitral award is vitiated by patent illegality appearing on the face of the award. The Arbitral Tribunal has also imposed the liability of payment of cess upon the appellant although section 3 of the Building and Other Construction Workers' Welfare Cess Act, 1996 (for short, the Cess Act, 1996) mandates that it is the respondent who are liable to pay it. While determining who is liable to pay the cess, the Arbitral Tribunal reversed the mandate of the law and imposed the liability upon the appellant instead. The arbitral award suffers from the vice of disregarding the two judgments of the Hon'ble Supreme Court in A. Prabhakara Reddy and Company vs. State of Madhya Pradesh and Others ,
3. The claimant before the Arbitral Tribunal was the consortium of M/s Abir Infrastructure Pvt. Ltd. (respondent no.1 herein), M/s Navayuga Engineering Co. Ltd. (respondent no.2 herein) and M/s SEW Infrastructure Ltd. (respondent no.3 herein). The respondent therein was M/s Teesta Urja Ltd.
4. The consortium of the respondents along with M/s CGGC International Ltd, M/s CKD Hydro Power Pvt. Ltd, M/s SABIR Dam & Water Works Construction Co., was awarded the work for Turnkey execution of 1200 MW Teesta Stage-III of Hydroelectric Project in the State of Sikkim after a successful bid. For the said purpose various agreements were executed. The contracts were subject to arbitration for settlement of disputes. The contract was awarded on 18.04.2007 with subsequent amendments dated 26.05.2007. The contract was signed on 12.09.2007 and the project completed on 28.02.2017.
5. According to the Arbitral Tribunal, as stated in its award, the dispute arose with respect to the liability
A. Prabhakara Reddy and Company vs. State of Madhya Pradesh and Others
M/s Dewan Chand Builders and Contractors vs. Union of India & Ors.
Statutory liability to pay welfare cess under labor legislation falls upon the contractor as the employer. Such liability is inherent to the statute, cannot be reallocated via contract clauses based ....
The interpretation of the Building and Other Construction Workers Act and the Cess Act requires the establishment of welfare boards for the effective levy and collection of cess; until then, contract....
(1) Cess could only be recovered in the manner stipulated in Cess Act and Rules framed thereunder.(2) A contractor who enters into a pure Supply Contract is statutorily exempted from levy under BOCW ....
Dredging activities fall within the definition of construction work under the BOCW Act, affirming cess obligations for such activities.
The main legal point established in the judgment is the importance of interpreting the statute by considering the text and context, and the applicability of the enabling provision of section 3(1-A) a....
The main legal point established in the judgment is that the labour cess is not leviable on the supply of materials and consultancy charges under the Building and Other Construction Workers' Welfare ....
The court held that deductions for the cess on construction payments are valid under the relevant welfare legislation, affirming that activities like laying pipelines constitute construction work.
The imposition of 1% cess under the Building and Other Construction Workers Act is a statutory obligation aimed at benefiting workers, and is applicable despite claims regarding the Factories Act exe....
Taxes not to be imposed save by authority of law - Article 265 of Constitution is the source of power for the Union and States to impose taxes in accordance with law. Article 265 of the Constitution ....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.