SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Sikk) 91

IN THE HIGH COURT OF SIKKIM
MEENAKSHI MADAN RAI, J.
Tt Energy Private Limited Petitioner – Appellant 
Versus
Principal Chief Engineer Cum Secretary, Respondents Energy And Power Department, Government Of Sikkim - Respondent 
I.A. No.01 of 2025 in WP(C) No.68 of 2025
Decided On : 30-10-2025

Advocates:
Advocate Appeared:
For the Appellant :Mr. Karma Thinlay, Senior Advocate. Mr. T. R. Barfungpa, Advocate. Ms. Mani Gupta, Advocate. Ms. Pravin Manger, Advocate.
For the Respondent:Mr. Aarohi Bhalla, Mr. Thinlay Dorjee Bhutia, Ms. Pema Bhutia, Advocate.

Equitable remedies, such as interim injunctions, are discretionary and will be denied when a petitioner suppresses material facts about prior legal disputes, demonstrates unreasonable delay (laches), or fails to approach the court with clean hands.

Headnote:(A) Writ Jurisdiction - Interim Relief - Concealment of material facts - Doctrine of Clean Hands - Petitioner challenged tender process for public project - Records revealed petitioner previously initiated arbitration proceedings regarding contract termination nearly a decade prior and subsequently abandoned them - Failure to disclose history of dispute and suppression of material facts regarding arbitration amounts to lack of good faith - Equitable relief is discretionary and cannot be granted to a party who fails to approach court with clean hands and remains silent for an inordinate period. (Paras 3, 4)

Facts of the case:
The petitioner sought an interim stay on a tender process for a hydroelectric project. The petitioner claimed a prior entitlement based on an agreement from 2008, alleging the contract was illegitimately terminated in 2012. The respondent contested the application on the grounds that the petitioner concealed the fact that they had formally invoked an arbitration clause in 2015 but failed to participate in the proceedings, remaining silent for approximately ten years before initiating the current litigation.

Findings of Court:
The court observed that the petitioner failed to disclose the existence of prior correspondence and the specific steps taken to initiate arbitration, which were abandoned without explanation. The court noted that the petitioner failed to demonstrate any urgency or activity regarding the project for a decade, thereby sleeping over their legal rights and failing to display the requisite diligence expected when seeking equitable relief.

Issues: Whether the court should grant an interim stay on the procurement process in light of the petitioner's concealment of prior legal actions and whether the petitioner’s delay in challenging the contract termination precludes entitlement to equitable relief.

Ratio Decidendi: Equitable remedies are granted only to those who act with transparency and diligence. A party who suppresses material information concerning the history of a contract dispute and remains inactive for a significant period cannot successfully seek a discretionary stay, as they have not approached the court with clean hands.

Result: Application for interim stay rejected.

Table of Content
1. petitioner seeks interim stay of rfp based on alleged arbitrary termination of 2008 project agreement. (Para 1 , 2)
2. respondent argues maintainability challenges due to prior arbitration invocation and subsequent abandonment of claim. (Para 3)
3. court denies interim relief for failure to approach with clean hands and significant unexplained delay. (Para 4)
4. formal rejection and disposal of the interim application. (Para 5)

ORDER (ORAL) :

1. I.A. No.01 of 2025 has been filed in the instant Writ Petition. The I.A. is an application seeking interim stay of Request for Proposal (RFP) dated 19-09-2025, inviting application/proposal for development of Ting Ting hydroelectric project on river, Rathong Chu on „as is where is‟ basis by Respondent No.1.

2. Learned Senior Counsel for the Petitioner submits that, the project for which the RFP was issued on 19-09-2025, was initially conceived by the Petitioner in the year 2008 and the project was to have been set up by the Petitioner. After all essential steps were taken by the Petitioner for initiating the project and the Agreement settled on 03-09-2008, the Respondent No.1 vide a letter dated 10-02-2012, addressed to the Petitioner enclosed the Notification issued by Respondent No.2 being Notification bearing No.12/HOME/2012, dated 08-02-2012, suddenly ordering closure of the project “in public interest” with immediate effect. After such closure, although several requests were made to the Government by the Petitioner to revive the project no heed was paid. The communication of 10-02-2012, it is urged, did not have a legal basis for the reason that, the contract between the Petitioner and the Respondent No.1 specified that it could be terminated only on three grounds viz.,;

Article 5 TERMINATION AND TAKING OVER OF THE PROJECT

5.1. In the event it is eventually confirmed as impossible or impractical to start the construction of the Project within six months from the date of obtaining all the clearances, for reasons exclusively attributable to the Company, the Government reserves the right to terminate the Agreement.

5.2. In the event of stoppage of construction on the main Project components by the Company, for a period of more than twelve months for reasons not covered under Force Majeure and for reasons attributable to the Company and/or abandonment of the Project by the Company, the Government shall, after giving due opportunity to the Company to rectify the same, have the right to terminate this Agreement. In the event of termination of this Agreement under this clause, the Government shall have the option to take over the Project after assuming all the Debt servicing obligations of the Company, to the extent drawn for the Project, as on the date of termination. Notwithstanding any investment by the Government under this Clause, the Company shall be liable to pay all the due owed to the Government by the Company pursuant to this Agreement.

5.3. After the expiry of the Agreement Period referred to in Clause 2.2, the Project including its all assets and works shall be transferred to the Government free of cost and in good operating conditions.”

(i) That, the Respondent No.2 did not put forth any of the grounds in the said correspondence for terminating the contract but merely ordered the closure of the project “in public interest”. That, in the months of March and June, 2025, the Petitioner had issued letters to the authorities of the Government for revival of the project, however no steps towards this end were taken. To the surprise of the Petitioner the RFP was again issued on 19-09-2025 with last date for submission of bid fixed on 18-11-2025, on which dates the bids will also be opened. That, in the circumstances a major part of the project having been initiated by the Petitioner, the project ought to have been revived and allowed to be taken over by the Petitioner, instead of issuance of a fresh RFP. Hence, the prayer for stay of the RFP.

3. Resisting the arguments adv

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top