IN THE HIGH COURT OF ALLAHABAD
PANKAJ MITHAL, SAURABH LAVANIA, JJ.
M/s ATS Reality Pvt.Ltd.Thru. Auth. Sign. Mr.Shailendra Kumar - Appellant
Versus
U.P.Real Estate Appellate Tribunal Lko. & Ors. - Respondents
Misc. Bench No.23900 of 2020
Decided on : 14-12-2020
Constitution of India, 1950 – Article 226 – Real Estate (Regulation and Development) Act, 2016 – Section 43 – Delayed Period – Compensation – Petitioner is a Private Limited Company engaged in the promotion of development and construction work. It works as a promoter. – In respect of one of it's scheme ATS ALLURE, the petitioner is registered as a promoter with RERA (Real Estate Regulatory Authority). – Eight complaints were made by different allottees in connection with the above Scheme alleging delay in possession, charging of interest for the delayed period and claiming charges/compensation on account of inordinate delay in putting allottees in possession. – All the aforesaid complaints were decided by RERA vide judgment and order wherein apart from other directions, the petitioner was directed to put the allottees in possession of the respective units allotted to them latest by 31.3.2021 and for payment of interest @ MCLR + 1% from 13.11.2017 till the date of offer of the possession excluding the lockdown period 24.3.2020 to 30.9.2020 due to COVID-19 pandemic. – The interest amount was directed to be adjusted in the final outstanding balance to be paid by the allottees and in the event, the interest payable exceeds the balance amount, the same was directed to be paid as directed above. – Aggrieved by the aforesaid order petitioner preferred a statutory appeal before the Real Estate Appellate Tribunal – Similar appeals were also preferred by the other allottees against the orders passed by RERA in their respective complaints. – They all remained defective as the requisite amount required to be paid as a pre-condition for entertaining and hearing the appeals was not deposited by the petitioner but were clubbed together. –
Finding of the Court:
Court have not been addressed so as to assail the order dated 25.6.2020 passed by RERA obviously for the reason that judicial review of it under Article 226 of the Constitution of India is not permissible when there is a statutory appeal provided against it and the same has failed for one reason or the other. – Court may usefully refer to the exposition of the Apex Court in Titaghur, [Titaghur Paper Mills Co. Ltd. & Anr. Vs. State of Orissa & Ors., [(1983) 2 SCC 433], wherein it is observed that where a right or liability is created by a statute, which gives a special remedy for enforcing it, the remedy provided by that statute must only be availed of. – Court, however, added a word of caution and expounded that the constitutional Court would certainly take note of the legislative intent manifested in the provisions of the Act and would exercise its jurisdiction consistent with the provisions of the enactment. – To put it differently, the fact that the High Court has wide jurisdiction under Article 226 of the Constitution, does not mean that it can disregard the substantive provisions of a statute and pass orders which can be settled only through a mechanism prescribed by the statute. –
Result: Writ Petition Dismissed
JUDGMENT :
1. Heard Sri Prashant Chandra, Senior Advocate assisted by Sri Sushant Prakash and Ms. Mahima Pahwa, learned Counsel for the petitioner, Sri Shobhit Mohan Shukla, learned Counsel for respondent Nos.2, Sri Anand Kumar Singh, learned Standing Counsel for respondent No.3/State and Mr. Prashant Kumar, learned Counsel for respondent No.4/Yamuna Expressway Industrial Development Authority.
2. The petitioner is a Private Limited Company engaged in the promotion of development and construction work. It works as a promoter. In respect of one of it's scheme ATS ALLURE, the petitioner is registered as a promoter with RERA (Real Estate Regulatory Authority). Eight complaints were made by different allottees in connection with the above Scheme alleging delay in possession, charging of interest for the delayed period and claiming charges/compensation on account of inordinate delay in putting allottees in possession.
3. All the aforesaid complaints were decided by RERA vide judgment and order dated 25.6.2020 wherein apart from other directions, the petitioner was directed to put the allottees in possession of the respective units allotted to them latest by 31.3.2021 and for payment of interest @ MCLR + 1% from 13.11.2017 till the date of offer of the possession excluding the lockdown period 24.3.2020 to 30.9.2020 due to COVID-19 pandemic. The interest amount was directed to be adjusted in the final outstanding balance to be paid by the allottees and in the event, the interest payable exceeds the balance amount, the same was directed to be paid as directed above.
4. Aggrieved by the aforesaid order dated 25.06.2020, petitioner preferred a statutory appeal before the Real Estate Appellate Tribunal (hereinafter referred to as 'the Tribunal']. Similar appeals were also preferred by the other allottees against the orders passed by RERA in their respective complaints. They all remained defective as the requisite amount required to be paid as a pre-condition for entertaining and hearing the appeals was not deposited by the petitioner but were clubbed together.
5. All appeals (total 10) were dismissed vide order dated 18.10.2020 as despite several opportunities, the petitioner failed to comply with the mandatory condition contained in 43 (5) of the Real Estate (Regulation and Development) Act, 2016 [hereinafter referred to as the 2016 Act']. The Tribunal held that it has no discretionary power to permit the promoter to deposit only 30% of the total amount directed to be paid as compensation and interest to the allottees.
6. Sri Prashant Chandra, Senior Counsel appearing for the petitioner submitted that the petitioner had deposited 30% of the amount as contemplated under Section 43 (5) of the 2016 Act and as such, the appeal was competent which could not have been dismissed. The Tribunal has manifestly erred in interpreting Sub-Section (5) of Section 43 of the 2016 Act to hold that the promoter is liable to deposit the whole amount directed to be paid, whereas the condition is only for payment of 30% of the penalty or the total amount including interest and compensation. If the said condition is read otherwise it would make the condition to be unreasonable and onerous and in turn, would render the provision of statutory appeal to be illusory and negatory.
7. In response to the argument so advanced on behalf of the petitioner, Sri Shobhit Mohan Shukla, learned Counsel for RERA, Sri Anand Kumar Singh, learned Standing Counsel and Sri Prashant Kumar, learned Counsel for respondent No.4 submitted that the language of the proviso to Sub-Section (5) of Section 43 of the 2016 Act is plain and simple. It provides that the appeal shall not be entertained, if the promoter has not deposited with the Tribunal at least 30% of the penalty or the total amount payable to the allottee including interest and compensation, if any, or both as the case may be for hearing of the appeal. It has also been submitted by them that the validity of Sub-Section (5) of Sectio
Mafatlal Industries Ltd. & Ors. vs. Union of India & Ors. [(1997) 5 SCC 536]
Secretary of State v. Mask & Co. (AIR 1940 PC 105)
Titaghur Paper Mills Co. Ltd. & Anr. Vs. State of Orissa & Ors.
The main legal point established in the judgment is the binding effect of the settlement between the parties, the waiver of the right to seek re-employment by the workmen, and the entitlement of the ....
A lockout is justified if it is declared in response to an illegal strike or a strike that is in breach of a settlement or award.
The combination of eyewitness testimonies, recovery of the weapon used, and forensic examination results can establish guilt in criminal cases, even based on circumstantial evidence.
The conviction of an accused person under Section 27(3) of the Arms Act is not permissible in law if the accused is also charged with committing murder under Section 302 of the Indian Penal Code.
The court can enhance compensation based on the deceased's income and family dependency, and adjust the multiplier used by the Tribunal if found unjustified.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.