IN THE HIGH COURT OF ALLAHABAD
Ashwani Kumar Mishra, Syed Qamar Hasan Rizvi, JJ.
M/s D Kumars and Company – Petitioner
Versus
State of UP and Others – Respondents
WRIT - C No. - 7729 of 2024
Decided On : 21-03-2024
Completion Certificate - Urban Planning and Development - U.P. Urban Planning and Development Act, 1973, Section 15-A - The court discussed the background facts of the case, the exchange deed, ongoing civil suit, compounding plan, and the authority's refusal to issue a completion certificate. The court highlighted the provisions of Section 15-A of the U.P. Urban Planning and Development Act, 1973 and emphasized that the authority's permission to construct 14 units should have led to the issuance of a completion certificate, despite the ongoing dispute over two units. The court issued a writ of mandamus to the Vice Chairman of the Prayagraj Development Authority to consider the petitioner's application for a completion certificate within four weeks.
Fact of the Case:
The petitioner sought a completion certificate for 14 units after the authority permitted construction of 14 units following an ongoing civil suit over two units. The authority refused to issue the completion certificate, citing the ongoing dispute.
Finding of the Court:
The court found that the authority's refusal to issue the completion certificate despite permitting construction of 14 units was contrary to the provisions of Section 15-A of the U.P. Urban Planning and Development Act, 1973.
Issues: The main issue was the authority's refusal to issue a completion certificate for 14 units despite permitting their construction due to an ongoing civil suit over two units.
Ratio Decidendi: The court held that the authority's permission to construct 14 units should have led to the issuance of a completion certificate, and the authority's refusal was contrary to the statutory provisions.
Final Decision: The court issued a writ of mandamus to the Vice Chairman of the Prayagraj Development Authority to consider the petitioner's application for a completion certificate within four weeks.
JUDGMENT :
1. This writ petition arises out of an order passed by the Vice Chairman, Prayagraj Development Authority, dated 15.2.2024, contained in Annexure No. 1 to the writ petition, whereby petitioner’s application submitted for issuing completion certificate has not been accepted. The application itself was filed pursuant to the liberty granted by this Court in petitioner’s previous writ petition no. 42231 of 2023. The petitioner submits that the order impugned is wholly arbitrary and is in teeth of the previous adjudication made by this Court in petitioner’s earlier writ.
2. The impugned order of the Vice Chairman runs into eight pages. Paragraph No. 1 to 21 of the order notices facts relating to the controversy raised. The findings and conclusion in the order under challenge is contained in para 22, which is reproduced hereinafter:-
3. Although the Vice-Chairman has recorded in his order that there is no hindrance in issuance of completion certificate in respect of 14 units yet the completion certificate has not been issued to the petitioner.
4. In order to appreciate the controversy raised some of the background facts are required to be noticed. A building plan was initially approved by the Prayagraj Development Authority on 11th of March, 2019 in favour of the petitioner for construction of 16 residential units, on a parcel of land being part of freehold plot no. 35 and 35A, Lukerganj, Prayagraj. The construction project was got registered with U.P. Real Estate Regulation Authority on 15.10.2019. This registration was initially valid for a period of three years and is stated to have been extended upto 2.10.2023. It transpires that the plot on which these constructions were permitted to be raised belonged partly to the petitioner and rest to Rajesh Kumar Athwani, Deepak Kumar and Umesh Athwani. These private individuals had transferred part of their share earlier in favour of the present petitioner.
5. It transpires that an exchange deed was executed between petitioner’s vendor and Respondent No. 5 in the present petition on 06.05.2017 as a result of which 133.4 sq.meter land falling in the project area was exchanged with 96.6 sq.meter land belonging to petitioner’s vendor. This exchange deed contained a stipulation in Clause-6, which is reproduced hereinafter:-
6. The fifth respondent apparently objected to the ongoing constructions commenced by the petitioner in terms of the sanctioned map on the ground that their right to passage, existing between the 16 row houses would be obstructed and thereby the sixth clause of the exchange deed would stand violated. This was so as no passage was provided in terms of Clause-6 in the building plan sanctioned on 11.3.2019. Consequently, a suit being Original Suit No. 187 of 2021 came to be instituted by respondent no. 5 and others before the Civil Court at Prayagraj. In the said suit the present petitioner is arrayed as the only defendant. Prayer in the nature of mandatory injunction has been claimed in the suit, which is reproduced hereinafter:-
7. Other ancillary reliefs were also sought in the matter. It is admitted that the suit is pending and there is no interim injunction granted to t
The authority's permission to construct 14 units should have led to the issuance of a completion certificate, and the authority's refusal was contrary to the statutory provisions.
The completion certificate issued must be strictly in accordance with the sanctioned plan and specifications, and the responsibilities of the promoter include providing and maintaining essential serv....
RERA Authority has no jurisdiction to review municipal completion certificates issued prior to the RERA Act's enforcement, maintaining their validity unless declared otherwise by competent municipal ....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.