IN THE HIGH COURT OF ALLAHABAD
SHEKHAR B. SARAF, J.
National Highways Authority of India - Appellant
Versus
Shri Krishna Uchchter Madhyamic Vidhyalaya and others – Respondents
Appeal under Section 37 of Arbitration and Conciliation Act 1996 Defective No. 108 of 2024
Decided on : 12-04-2024
Delay - Appeal - Section 34, 37 of the Arbitration and Conciliation Act, 1996 - The court emphasized strict adherence to limitation periods, allowing delays only in exceptional circumstances, and underscored the importance of providing compelling reasons for any delay in filing appeals.
Fact of the Case:
The appellant filed an appeal under Section 37 of the Arbitration and Conciliation Act, 1996, after a significant delay of 552 days, following a previous dismissal of their application under Section 34 as time-barred.
Finding of the Court:
The court found that the appellant failed to provide sufficient cause for the delay in filing the appeal, which was beyond the permissible period, and noted the lack of compelling reasons for condonation.
Issues: Whether the delay in filing the appeal under Section 37 of the Arbitration and Conciliation Act could be condoned given the significant lapse of time and the reasons provided by the appellant.
Ratio Decidendi: The court held that delays in filing appeals under the Arbitration Act must be strictly scrutinized, and only short delays can be condoned in exceptional cases where sufficient cause is demonstrated.
Result: The delay condonation application is rejected, and the appeal is dismissed as barred by limitation.
JUDGMENT :
Hon'ble Shekhar B. Saraf, J.
Civil Misc. Delay Condonation Application No. 2 of 2024 :
Heard Sri Dhananjay Awasthi, learned counsel appearing on behalf of the appellant.
2. This is an appeal under Section 37 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the 'Act') arising out of an order passed under Section 34 of the Act.
3. It is to be noted that the application filed by the appellant before the Court below under Section 34 of the Act was also delayed by four months and the same was dismissed as time barred.
4. There is furthermore an inordinate delay of 552 days in filing this appeal under Section 37 of the Act.
5. In M/s. N.V. International v. State of Asam and others, 2020 (2) SCC 109 [Coram : Rohinton Fali Nariman and S. Ravindra Bhat, JJ.] and Government of Maharashtra (Water Resources Department) Represented by Executive Engineer v. M/s. Borse Brothers Engineers & Contractors Pvt. Ltd., (2021) 6 SCC 460 [Coram : Rohinton Fali Nariman, B.R. Gavai and Hrishikesh Roy, JJ.] the Supreme Court has stated that such a delay in filing an appeal under Section 37 of the Act cannot be allowed.
6. The issue with regard to filing an appeal under Section 37 of the Act is no longer res integra as the same has been settled by the Supreme Court. One may rely on the judgement in M/s. N.V. International (Supra) the relevant paragraph thereof is delineated below :
''4. We may only add that what we have done in the aforesaid judgment is to add to the period of 90 days, which is provided by statute for filing of appeals under Section 37 of the Arbitration Act, a grace period of 30 days under Section 5 of the Limitation Act by following Lachmeshwar Prasad Shukul and others (supra), as also having regard to the object of speedy resolution of all arbitral disputes which was uppermost in the minds of the framers of the 1996 Act, and which has been strengthened from time to time by amendments made thereto. The present delay being beyond 120 days is not liable, therefore, to be condoned.''
7. Furthermore, paragraph No. 61 of the judgment in Government of Maharashtra (Water Resources Department) Represented by Executive Engineer (Supra) is required to be looked into. The relevant paragraph is delineated below :
''61. Given the aforesaid and the object of speedy disposal sought to be achieved both under the Arbitration Act and the Commercial Courts Act, for appeals filed under Section 37 of the Arbitration Act that are governed by Articles 116 and 117 of the Limitation Act or Section 13(1A) of the Commercial Courts Act, a delay beyond 90 days, 30 days or 60 days, respectively, is to be condoned by way of exception and not by way of rule. In a fit case in which a party has otherwise acted bona fide and not in a negligent manner, a short delay beyond such period can, in the discretion of the Court, be condoned, always bearing in mind that the other side of the picture is that the opposite party may have acquired both in equity and justice, what may now be lost by the first party's inaction, negligence or laches.''
8. A coordinate Bench of this Court in National Highway Authority of India v. Smt. Sampata Devi and others, 2023(12) ADJ 787 [Coram : Om Prakash Shukla, J.], in similar facts and circumstances, discussed in great detail a catena of judgments of the Supreme Court and has come to the following conclusion :
''(44) In view of the authoritative Judgments of the Apex Court in M/s. Borse Brothers Engineers & Contractors (supra), it must be held that an appeal under Section 37 of the Arbitration and Conciliation Act, 1996 should be filed within 60 days from the date of the order as per Section 13(1A) of the Commercial Courts Act, 2015. However, in those rare cases where the specified value is for a sum less than INR 3,00,000.00 then the appeal under Section 37 would be governed by Articles 116 and 117 of the Schedule of the Limitation Act, as the case may be.
(45) Further, Section 5 of the Limitation Act will apply to the a
AI
The court established that delays in appeals under the Arbitration Act are to be strictly limited, with condonation only in exceptional circumstances where compelling reasons are provided.
The court emphasized that delay in filing appeals under the Arbitration Act must be justified by sufficient cause, with negligence being insufficient for condonation.
The court emphasized the strict timelines prescribed in the Arbitration and Conciliation Act and the Limitation Act, and held that delays beyond the statutory periods cannot be condoned.
Timely filing of appeals under the Arbitration and Conciliation Act is crucial; bureaucratic delays are inadequate reasons for condoning significant delays.
The court emphasized that appeals under the Arbitration Act must adhere to strict timelines, and administrative delays do not constitute sufficient cause for condonation of delay.
The court established that the limitation period for appeals under the Arbitration Act is 60 days as per the Commercial Courts Act, but delays can be condoned based on sufficient cause, including rel....
The main legal point established in the judgment is that the doctrine of condonation of delay should be applied judiciously, taking into account the circumstances and the impact of external factors s....
The Court held that the 60-day limitation for appeals under the Arbitration Act is strict and can only be extended in exceptional cases where sufficient cause is demonstrated, which was not establish....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.