IN THE HIGH COURT OF UTTARAKHAND AT NAINITAL
MANOJ KUMAR TIWARI, PANKAJ PUROHIT, JJ.
Jagdish Singh Suyal - Petitioner
Versus
State of Uttarakhand & Others - Respondents
Writ Petition (M/S) No. 2252 Of 2020
Decided On : 23-11-2023
Tender Technical Committee - Non-Responsive Technical Bid - Clause 4.2 (g) - Pradhan Mantri Gram Sadak Yojana - [Clause 4.2 (g)]
Fact of the Case:
The petitioner, a Civil Contractor, challenged the rejection of his technical bid for the reconstruction and development of rural roads under Pradhan Mantri Gram Sadak Yojana.
Finding of the Court:
The court found that the rejection of the petitioner's bid was justified as it did not meet the requirement of condition contained in Clause 4.2 (g) of the Standard Bidding Document.
Issues: The issues revolved around the rejection of the petitioner's technical bid and the fairness of the tender process.
Ratio Decidendi: The employer's decision regarding qualifications and eligibility of a bidder has to be respected, and interference would be warranted only when the decision is so palpably wrong or unjust, which no reasonable person could have taken.
Final Decision: The court dismissed the writ petition, vacated the interim order, and upheld the rejection of the petitioner's bid.
JUDGMENT :
(Manoj Kumar Tiwari, J.)
Petitioner is a Civil Contractor. He responded to a notice inviting tender issued by respondent no. 2, on 28.08.2020, for the purpose of reconstruction and development of rural roads under Pradhan Mantri Gram Sadak Yojana. Petitioner’s technical bid was initially found to be responsive. Rival bidders made compliant that petitioner did not meet requirement of condition contained in Clause 4.2 (g) of Standard Bidding Document, therefore, his technical bid is liable to be rejected. The Tender Technical Committee considered the complaint and declared petitioner’s technical bid to be non-responsive. Thus, feeling aggrieved by the decision taken by Tender Technical Committee, on 20.11.2020, petitioner has approached this Court, seeking the following reliefs:
I. Issue an order, direction or writ in the nature of certiorari quashing the order dated 23.11.2020 opening and accepting the financial bid of the Respondent no. 4 for tender work “Kharlekh- Bhanar Motor Road KM 1 to Naikana- Basora Motor Road (Stage II works) Phase XVII” assigned Package No. UT- 02-70; (Annexure No. 10)
II. Issue a writ, order or direction in the nature of mandamus commanding and directing the respondent No. 2 to re-open the financial bid for the tender process for tender work “Kharlekh- Bhanar Motor Road KM 1 to Naikana- Basora Motor Road (Stage II works) Phase XVII” assigned Package No. UT- 02-70 after accepting the technical bid of the petitioner or in alternate issue a fresh tender for the Construction and Maintenance of Kathapuriyachina-Seraghat to Nayalamafi Motor Road Stage - I&II length 5.425;”
2. Petitioner’s technical bid has been declared to be non-responsive on the ground that it does not meet requirement of condition contained in Clause 4.2 (g), which is reproduced below:
3. From the aforesaid condition, it is apparent that the certificate issued by the banker should not be more than 3 months old. The certificate submitted by the petitioner with his technical bid is at page no.29 of the writ petition. The said certificate does not bear any date. Since Clause 4.2 (g) of the Standard Bidding Document provides that the certificate should not be more than 3 months old, therefore, in the absence of date of issuance indicated by the banker in the certificate, the employer cannot ascertain as to whether the certificate is more than 3 months old or not. Thus, the decision taken by Tender Technical Committee on the complaint made by rival bidders cannot be said to be unjust or unreasonable. Law is well settled that, in matters of Government Contract, employer’s decision regarding qualifications and eligibility of a bidder has to be respected and interference would be warranted only when the decision, so taken, is so palpably wrong or unjust, which no reasonable person could have taken. This does not appear to be the case here, as rejection of petitioner’s bid is referable to Clause 4.2 (g) of the Standard Bidding Document.
4. Learned counsel for the petitioner then contended that the complaints made by rival bidders against acceptance of petitioner’s technical bid, were not communicated to him. Thus, according to him, impugned decision has been taken behind the back of the petitioner, without providing him opportunity of hearing.
5. Learned counsel for respondent no.4, however, submits that no
AI
The employer's decision regarding qualifications and eligibility of a bidder must be respected, and interference is warranted only if the decision is unjust or unreasonable.
In tender matters, judicial review is limited; courts defer to tender authority's bid responsiveness assessment unless arbitrary, mala fide or perverse, prioritizing public interest in infrastructure....
Judicial review in tender matters limited to arbitrariness or mala fides; courts defer to authority's bid compliance assessment, refusing substitution unless perverse.
Technical bid non-responsive for missing mandatory physical affidavit; no evaluation or appeal period applies; limited judicial interference in tenders.
Failure to submit mandatory documents leads to rejection of technical bids as non-responsive, with no grounds for procedural violation.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.