SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2022 Supreme(MP) 1263

IN THE HIGH COURT OF MADHYA PRADESH BENCH AT INDORE
Vivek Rusia, J.
Rajsheel Builders And Developers – Appellant
Versus
Shakuntlabai W/o Shri Kanhaiyalal Hardia & Ors. – Respondents
Arbitration Case No. 105 of 2018
Decided On : 14-10-2022

Advocates Appeared:
Shri Ashok Kumar Sethi, Senior Advocate With Shri Rahul Sethi, Advocate For The Applicant., for the Appellant; Shri Vinay Saraf, Senior Advocate With Shri Bharat Yadav, Advocate Appeared For The Respondents.., for the Respondent

The main legal point established in the judgment is the principle of minimal judicial intervention in the arbitral process, emphasizing the competence of the arbitrator to decide all preliminary issues and objections.

Headnote:

Arbitration & Conciliation Act - Appointment of Independent Arbitrator - 11(6) - 1996 - [Clause 23, Section 11(6)(a), Section 69, Section 16] - The court examined the existence of the arbitration agreement and appointed an arbitrator. The court's decision was influenced by the interpretation of the arbitration clause, survival of the clause even after the expiration of the agreement, and the principle of minimal judicial intervention in the arbitral process.

Fact of the Case:

The applicant, a partnership firm, entered into an agreement with the respondents for land development. Dispute arose when the respondents allegedly failed to fulfill their obligations. The applicant sought the appointment of an independent arbitrator under section 11(6) of the Arbitration & Conciliation Act, 1996.

Finding of the Court:

The court found that the existence of an arbitration clause in the agreement was not in dispute and appointed an arbitrator to adjudicate the issues. The court emphasized that all other issues were to be decided by the arbitrator, in line with the legislative mandate.

Issues: The issues included the existence of the arbitration agreement, non-performance of contractual obligations, and the survival of the arbitration clause after the expiration of the agreement.

Ratio Decidendi: The court's decision was based on the interpretation of the arbitration clause, the principle of minimal judicial intervention in the arbitral process, and the legislative policy to restrict judicial intervention at the pre-reference stage.

Final Decision: The court appointed an arbitrator and directed the parties to appear before the arbitrator on a specified date.

JUDGMENT

Passed on 14th October, 2022

The applicant has filed this application u/s. 11(6) of the Arbitration & Conciliation Act, 1996 (hereinafter referred to as the Act of 1996)seeking the appointment of an independent Arbitrator in order to resolve the dispute between the parties.

The facts of the case, as pleaded in this application are as under :

1. The applicant is a partnership firm engaged in the business of construction and development. Mr. Shailendra Agrawal is the partner of the applicant firm. The respondents are the owners of land bearing Survey No.108/3/3 area 0.405 Hect. and Survey No.108/8 area 0.177 Hect., total area 0.582 Hect. situated at Village Chitawad, Tehsil and District Indore. For the development of the above lands, the respondents engaged the applicant by way of an agreement dated 27.9.2010. As per the terms and conditions of the agreement, the respondents were required to provide the land diverted and to get the layout sanctioned. It was also agreed between the parties that after development and construction the developed areas would be divided between the parties in the ratio of 60:40, which means the applicant would get 60% of the area and the respondents would get 40% of it. The applicant was to do the entire development work at its own cost. The applicant also agreed to give a refundable security deposit of Rs.10,00,000/- and out of which Rs.5,00,000/- was paid at the time of execution of the agreement. Rs.2,00,000/- was to be spent on diversion and permission. Rs. 3,00,000/- was payable at the time of commencement of the construction work.

2. The applicant obtained a colonizer license and applied for sanctioning of site-plan on 30.11.2010 . The Joint Director, Town & Country Planning sanctioned the plan on 1.3.2014. According to the applicant, preliminary work i.e. boring, levelling, filling, etc. was done, but the respondents have failed to get the land diverted u/s. 172 of the M.P. Land Revenue Code. The applicant vide letter/notice dated 26.3.2015 called upon the respondents to get the said land diverted.

3. The applicant came to know that the respondents are intending to dispose of the said land, hence got published a public notice on 1.5.2015 followed by filing an objection before the Sub Registrar, Registration on 27.6.2015. Meanwhile, the applicant applied for modification of the sanctioned plan. On repeated requests when the land was not got diverted by the respondents, a legal notice was sent through an Advocate on 6.4.2016 calling upon them to perform their part of the contract and not to indulge in violation of the terms and conditions of the agreement. No reply was received from the respondents. Vide notice dated 30.9.2016, the applicant has called upon the respondents to appoint an Arbitrator in terms of Clause 23 of the agreement dated 27.9.2010. The applicant has filed the present application u/s. 11(6) of the Act of 1996 for the appointment of an independent Arbitrator.

The respondents are the joint owner of the land in question, respondent No.4 - Nitin Hardia passed away during pendency of this AC, he is being represented by legal heirs

The facts as pleaded in reply are as under :

4. Respondents No.1, 2 and 3 have denied each and every allegation made in the application, except the execution of the agreement dated 27.9.2010 and the arbitration clause contained therein. They specifically denied the receipt of Rs.5,00,000/-, hence according to them there was no valid agreement that came into force and as such this agreement is not enforceable. It is submitted that as per provisions of Section 7 of the Act of 1996, Clause 23 of the agreement does not constitute an arbitration agreement. It is also pleaded that the applicant is not a registered partnership firm, therefore, in view of Section 69 of the Indian Partnership Act, the present application u/s. 11(6) of the Act of 1996 is not maintainable and the same is liable to be dismissed. It is further submitted that the agreement was executed

      Click Here to Read the rest of this document
      1
      2
      3
      4
      5
      6
      7
      8
      9
      10
      11
      SupremeToday Portrait Ad
      supreme today icon
      logo-black

      An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

      Please visit our Training & Support
      Center or Contact Us for assistance

      qr

      Scan Me!

      India’s Legal research and Law Firm App, Download now!

      For Daily Legal Updates, Join us on :

      whatsapp-icon Back to top