2025 Supreme(MP) 174
IN THE HIGH COURT OF MADHYA PRADESH
Vivek Rusia and Gajendra Singh, JJ.
Union of India v. Nataskee Incorporation
Arbitration Appeal No. 57 of 2025 (I); Decided on 2.5.2025
Aviral Vikas Khare for appellant; Brijesh Garg and Vishal Lashkari for respondent.
Headnote:
Arbitration and Conciliation Act, 1996 -- S. 9 -- interim relief -- temporary injunction against new tender as interim relief in favour of respondent -- respondent successful bidder in tendering process -- failed to submit requisite performance guarantee within stipulated period of 21 days -- furnished aforesaid guarantee within further 60 days without availing benefit of provision for extension of time on payment of penal interest -- can at most claim compensation for wrong action of appellant despite good prima facie case in arbitration proceedings -- order granting interim relief of temporary injunction set aside. 2022 SCC Online SC 1219 and C. A. No. 1846 of 2022 decided on 7.3.2022 (SC) followed. (1993) 1 SCC 230, (2004) 3 SCC 155, (2007) 7 SCC 125, AIR 2010 SC 3221, 2012 SCC Online Bom. 1536, (2019) 5 SCC 755, AIR 2019 Del. 4, AIR 2022 Tel. 51, AIR 2022 Tel. 146, W. P. No. 4318 of 2022 decided on 14.10.2024 and W.P. No. 14395 of 2023 decided on 24.2.2025 referred to. [Paras 21, 24 & 25]
ekè;LFke~ v©j lqyg vfèkfu;e] 1996 & èkkjk 9 & varfje vuqr¨"k & çR;FkÊ d¢ i{k esa varfje vuqr¨"k d¢ :i esa uà fufonk d¢ fo#) vLFkk;h O;kns'k & çR;FkÊ fufonk çfØ;k esa lQy c¨yh yxkus okyk & visf{kr laiknu çfrÒwfr bDdhl fnu dh vuqcafèkr dkykofèk d¢ Òhrj çLrqr djus esa vlQy jgk & 'kkfLrd C;kt d¢ lank; ij le;o`f) d¢ micaèk dk Qk;nk fy, fcuk vxys lkB fnu d¢ Òhrj iwo¨Zä çfrÒwfr çLrqr dh & ekè;LFke~ dk;Zokgh esa vPNs çFken`"V~;k ekeys d¢ ckotwn vihykFkÊ dh n¨"kiw.kZ dkjZokà d¢ fy, çR;FkÊ] vfèkd&ls&vfèkd] çfrdj dk nkok dj ldrk gS & vLFkk;h O;kns'k dk varfje vuqr¨"k çnku djus okyk vkns'k vikLrA 2022 ,llhlh vkWuykbu ,llh 1219 rFkk flfoy vihy Øekad 1846 lu~ 2022 fu.kÊr fnukad 7-3-2022 ¼mPpre U;k;ky;½ vuqlfjrA ¼1993½ 1 ,llhlh 230] ¼2004½ 3 ,llhlh 155] ¼2007½ 7 ,llhlh 125] ,vkbvkj 2010 ,llh 3221] 2012 ,llhlh vkWuykbu cacà 1536] ¼2019½ 5 ,llhlh 755] ,vkbvkj 2019 fnYyh 4] ,vkbvkj 2022 rsya- 51] ,vkbvkj 2022 rsya- 146] fjV ;kfpdk Øekad 4318 lu~ 2022 fu.kÊr fnukad 14-10-2024 rFkk fjV ;kfpdk Øekad 14395 lu~ 2023 fu.kÊr fnukad 24-2-2025 fufnZ"VA ¼iSjk 21] 24 ,oa 25½
ORDER
Rusia, J:--
1. This Arbitration Appeal under section 37 of the Arbitration and Conciliation Act, 1996 has been preferred against the order dated 25.2.2025 passed by the learned District Judge, Commercial Court, Indore in MJC AV No. 12 of 2025 whereby the learned Court while exercising powers under section 9 of the Arbitration and Conciliation Act, 1996 granted interim relief in favour of the Respondent.
THE FACTS OF THE CASE, IN SHORT, ARE AS UNDER:-
2. Appellant No.2 i.e. Divisional Manager, Western Railway, Ratlam had issued a Notice Inviting Tender (NIT) bearing No. EL-2024-2025-09 dated 27.7.2024 of installation of Solar Grid systems at various locations within the Ratlam Railway Division. The Respondent participated in the tendering process and was declared the lowest bidder (L1).
3. Consequently, a Letter of Acceptance (LOA) was issued in favour of the respondent on 29.11.2024. As per the terms of the LOA and the Indian Railways General Conditions of Contract (GCC), 2022, the Respondent was mandatorily required to submit a Performance Guarantee (PG) within 21 days, i.e., on or before 20.12.2024 with a provision for extension up to 60 days i.e. till 27.1.2025 on payment of penal interest.
4. The Respondent however failed to submit the requisite Performance Guarantee within 21 days and did not seek any extension from the competent authority before the expiry of the stipulated period. The respondent unilaterally sought to submit the Performance Guarantee beyond the permitted period without the payment of penal interest and thereby breached the mandatory terms of the LOA. As a consequence of the said breach and in accordance with the stipulations of the LOA and the GCC the Appellants rescinded the LOA on 29.1.2025.
5. Being aggrieved, the respondent approached the Commercial Court, Indore under section 9 of the Arbitration Act, 1996 seeking interim protection against the rescission of the LOA and to restrain the appellants from awarding the work to any other party. The Respondent claimed the existence of an arbitration clause within the standard contract documents to contend that the dispute is arbitrable. Whereas, the appellants contested the maintainability of the application on the ground that no concluded contract had come into existence and thus recourse to section 9 of the Arbitration and Conciliation Act was wholly misconceived.
6. Despite the objections raised by the appellants, the learned commercial court vide order dated 25.2.2025 allowed the application of the respondent to stay the operation of the tender and also restrained the appellants from awarding the work to any other bidder. Learned Court held that the Letter of Acceptance when read together with GCC, 2022 indicated the existence of an arbitration agreement sufficient to invoke section 9 despite the formal contract not being executed. The Court further observed that the delay in submission of the Performance Guarantee was marginal and denying interim protection would result in irreparable harm to the respondent who had already undertaken substantial preparation and investment. Consequently, balancing equities and public interest, it restrained the appellants from continuing with the fresh tender process.
7. Aggrieved by this order the appellants have now approached this Court seeking that the impugned order dated 25.2.2025 passed by the Commercial Court, Indore be set aside and the order dated 29.1.2025 rescinding the LOA be upheld also that the appellants be permitted to proceed with the execution of the tender work.
SUBMISSION OF APPELLANTS
8. The learned counsel for the appellants submitted that the learned Commercial Court erred in exercising jurisdiction under section 9 of the Arbitration & Conciliation Act in the absence of a concluded arbitration agreement between the parties. Learned counsel submitted that the issuance of a letter of acceptance without execution of a formal contract does not satisfy the mandatory requirement under section 7 of the A