SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2024 Supreme(MP) 727

IN THE HIGH COURT OF MADHYA PRADESH AT JABALPUR 
Sushrut Arvind Dharmadhikari, Anuradha Shukla, JJ.
M/s Parasia Engineering Pvt.Ltd. – Petitioner
Versus
The State Of Madhya Pradesh And Others – Respondents
Arbitration Revision No. 31 of 2023
Decided On : 20-11-2024

Advocates:
Advocate Appeared:
For the Petitioner:Shri Navneesh Jauhari, Advocate
For the Respondent:Shri Praveen Namdeo, Government Advocate

Compliance with dispute resolution timelines in contracts is mandatory, and failure to adhere renders arbitration petitions non-maintainable under specified legal frameworks.

Headnote:(A) M.P. Madhyastham Adhikaran Adhiniyam, 1983 - Sections 7-B(1)(a), 7-B(1)(b), and 7-B(2-A) - Arbitration - Maintainability of reference petition - Revision petition dismissed as not maintainable due to non-compliance with limitation as set out in the terms of the contract and Adhiniyam - Time frame for approaching final authority is mandatory and failure to adhere renders the petition void. (Paras 4, 26)

(B) Contractual obligations - Clause-29 - Mandatory requirement to file quantified claims within 30 days post-termination of the contract - Tribunal jurisdiction can only be invoked post compliance of this procedure. (Paras 20, 24)

Facts of the case:
The petitioner, a contractor, was awarded a work contract which was rescinded due to non-completion. The petitioner approached the Tribunal after a significant delay post rescission, seeking claims that were deemed time-barred by the Tribunal.

Findings of Court:
The petitioner failed to approach the final authority within the stipulated time frame as required under the contract, making the reference petition non-maintainable.

Issues: The court examined whether the reference was filed within the permissible timeframe and legality of the rescission of the contract.

Ratio Decidendi: The court reiterated that adherence to the time constraints laid out in the agreement is essential for maintainability of an arbitration petition, citing established jurisprudence.

Result: Revision petition dismissed.

Table of Content
1. factual background of the arbitration revision (Para 1 , 2)
2. arguments presented by both parties regarding limitation and compliance (Para 3 , 6 , 7 , 8 , 9 , 10 , 11)
3. court's observations on the tribunal's jurisdiction and compliance with contractual clauses (Para 4 , 12 , 14 , 15 , 16 , 17 , 19 , 21 , 24)
4. legal reasoning determining the non-compliance with requirements (Para 18 , 20 , 23 , 25 , 26)
5. ratio decidendi on contestable timelines in resolutions. (Para 22)
6. final dismissal of the revision petition (Para 27)

ORDER :

Sushrut Arvind Dharmadhikari, J.

This Arbitration Revision under Section 19 of the M.P. Madhyastham Adhikaran Adhiniyam, 1983 (for short, ‘the Adhiniyam’) has been filed assailing order dated 09.02.2023 passed in Reference Case No.25/2009 by learned M.P. Arbitration Tribunal, Bhopal (for short, ‘the Tribunal’) whereby the revision filed before the Tribunal has been dismissed as not maintainable on the ground of limitation holding that the petitioner has not filed the petition in compliance with the provision of Section 7 -B(1)(b) of the Adhiniyam as he has failed to approach the final authority within the stipulated time as per the terms of clause 29 of the contract agreement and Section 7 -B(1)(a) of the Adhiniyam.

2. Facts of the case in nutshell are that the respondents awarded work contract in favour of the petitioner vide Agreement No. 42/2003- 04 for construction of I.R.Q.P. work in Km. 39 to 51 of NH-75 (Ext.) and work order was issued on 17.03.2004. The stipulated period for execution of the contract was seven months including rainy season., Accordingly, due date for completion of the work was 16.10.2004. However, the work was not completed even uptil 30.12.2005 despite of extension and prior to the extended date, vide letter dated 29.12.2005, the contract was rescinded by the respondents. According to the petitioner, vide letter dated 07.01.2006, a representation was submitted under clause-29 of the contract before the Superintending Engineer against rescission of the contract which was rejected without giving any opportunity of hearing to the petitioner. Thereafter the petitioner made the same request to Chief Engineer seeking his decision, who in turn, returned the representation directing to submit the same before the Superintending Engineer. In compliance, the petitioner had put up his case before the Superintending Engineer on 22.03.2006. Again, the petitioner submitted a letter dated 05.05.2006 to the Chief Engineer and thereafter submitted quantified claim before the Superintending Engineer on 28.07.2008 who did not decide the same, then the petitioner vide letter dated 04.12.2008 referred its claim to the Chief Engineer who also did not decide the same and it remained pending. Thereafter, the petitioner filed Reference Petition No.25/2009 before the Tribunal.

3. Before the Tribunal, respondents have filed a written reply stating therein that on account of non-execution of the contract as per the terms of the contract, the contract was rescinded after giving notice to the petitioner, therefore, it cannot be said that the rescission order is illegal. It is also stated that the petitioner, during the stipulated period, never achieved the proportionate progress of work at any point of time and on the request of the petitioner, time was extended twice i.e. till 31.05.2005 and 30.12.2005 and at the time of last extension, warning was given that no further extension would be granted and this extension was given reserving the right to recover the liquidated damages. It is further stated that the allegation regarding non-payment is also incorrect and the department was not under obligation to ensure material by way of assisting or facilitating for getting new lease for mining and there were no instructions to stop the work and for waiting for further instructions on account of work carried out at U.P. Irrigation Canal and Bansagar Sihawal Canal. It was submitted that it cann

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top