2024 Supreme(MP) 795

IN THE HIGH COURT OF MADHYA PRADESH AT GWALIOR
MILIND RAMESH PHADKE, J.
Naval Kishore (Dead) through LRs. Smt. Savitri Devi - Appellant
Versus
Neksey S/o Shri Jugtiram (Dead) thorugh LRs. Smt. Madhuri - Respondent 
Misc. Petition No. 6784 of 2024
Decided On : 13-12-2024

Important Points

In execution proceedings, notice to any one of joint tenants suffices; further notices to unserved legal representatives are unnecessary if execution application is within two years of the decree.

Subject

Civil Law - Execution Proceedings

Act Referred

CONSTITUTION OF INDIA: Art.227
CIVIL PROCEDURE CODE: O.21 R.12

Headnote

(A) Constitution of India - Article 227 - Code of Civil Procedure, 1908 - Order 21 Rule 12 and Rule 22 - Execution proceedings - Petitioner challenges directive of the Executing Court to issue notices to legal representatives of deceased tenant. It was determined that such notice was not required since one co-tenant was served; thus the execution should proceed. (Paras 1 & 2)

(B) Legal principle - Execution proceedings require proper notice only if applied post two years from the decree date; herein, execution was within the two-year limit making notices unnecessary. (Paras 2)

Facts of the case:
The petition was filed against the proceedings dated 25.11.2024 where notices were ordered for unserved legal representatives of a deceased tenant, while one legal representative had already been served.

Findings of Court:
The court upheld that service of notice to one legal representative suffices, allowing the execution to proceed.

Issues: Whether further notices were necessary for unserved legal representatives in execution proceedings.

Ratio Decidendi: Service of notice to any one of joint tenants suffices for execution; notices to others unnecessary under Order 21 Rules as no delay in execution.

Result: Petition disposed of with direction to execute decree within three months.

Advocates:
Advocate Appeared:
For the Appellant : Anand Vinod Bhardwaj

Table of Content
1. requirement for notice in execution cases (Para 1)
2. joint tenant notice sufficiency (Para 2)
3. direction for execution timeline (Para 3 , 4)
ORDER :

1. The instant petition under Article 227 of the Constitution of India is preferred against the proceeding dated 25.11.2024 passed by 16th Civil Judge, Junior Division, Gwalior in Executing Case No.75/2024, whereby on an application preferred by one of the legal representatives of deceased tenant, the Executing Court has directed to get the service effected on the other legal representative when admittedly as per provisions of Order 21 rule 12 of the Code of Civil Procedure, 1908, no notices were required to be issued. Further, learned counsel while placing reliance in the matter of Kanji Manji v. The Trustees of the Port of Bombay , AIR 1963 SC 468 ; had contended that notice to the one of the co-tenant would be sufficient, as the present respondents are legal representatives of the original tenant i.e. Neksey S/o Shri Jugtiram and since one of legal representatives of respondent No.2 had already been served, the trial Court should have proceed to decide the said execution.

2. After hearing learned counsel for the petitioner, this Court finds force in his arguments, as firstly under Order 21 Rule 22 CPC notices were required to be issued to a person against whom execution is applied for requiring him to show cause as to why the decree should not be executed, if the application for execution is made after more than two years from the date of a decree and as herein case the date of judgement and decree is 29.01.2024 and application for execution was filed on 06.05.2024, which was well within a period of two years, therefore, no notices were required to be issued to the judgement debtor. Otherwise also, as per the dictum of the Apex Court in the matter of Kanji Manji v. The Trustees of the Port of Bombay (Supra); when present respondents No.1 and 2 are joint tenant holders/judgement debtors, then service of notice to any one of them could be sufficient and as no notices are required to be issued to others. Be that as it may, notices were directed to be issued and were served upon one of the legal representative/judgement debtor, therefore, the Executing Court was required to proceed in the matter instead of directing further issuance of notice to the unserved judgement debtor.

3. After considering as aforesaid, this Court deems it expedient to direct the Executing Court to get the decree executed as expeditiously as possible within a period of three months from the date of receipt of certified copy of this order.

4. With the aforesaid direction, the present petition stands disposed of. Certified copy as per rules.

1