IN THE HIGH COURT OF MEGHALAYA AT SHILLONG
H.S. THANGKHIEW, J.
North Eastern Electric Power Corporation Limited - Petitioner
Versus
M/s Astra Construction Pvt. Ltd. - Respondent
CRP No. 13 of 2023
Decided On : 21-08-2023
| Table of Content |
|---|
| 1. brief facts of the arbitral case. (Para 1) |
| 2. preliminary objections on maintainability raised by the respondent. (Para 2 , 3) |
| 3. petitioner's arguments concerning execution and stay. (Para 4 , 5 , 6 , 8) |
| 4. court's consideration of the requests under article 227. (Para 9 , 10) |
| 5. analysis of applicable law regarding automatic stays. (Para 11 , 12) |
| 6. final order dismissing the petition and expectation for swift conclusion of proceedings. (Para 13 , 14 , 15) |
JUDGMENT :
H.S. Thangkhiew, J.
1. The brief facts of the case are that on 05.06.2015, an arbitral award was passed in favour of the respondent, to which the petitioner filed an application under Section 34 before the learned Commercial Court on 31.08.2015, for setting aside the said award. Seven years after the passing of the award, the respondent on 14.12.2022, filed for execution of the award before the Commercial Court. The maintainability of the petition for execution was raised by the petitioner on the ground that when the application under Section 34 had been filed on 31.08.2015, the position of law existing then, as per the un-amended A&C Act, of 1996 was that an automatic stay of the award under challenge, immediately came into operation. It was contended that though subsequent amendments had done away with the automatic stay rule, however, the same would apply only prospectively and the petitioner could not be divested of the benefit of automatic stay, which had accrued to it as far back as on 31.08.2015. The learned Commercial Court by the first impugned order dated 15.03.2023, rejected the challenge to maintainability raised by the petitioner, who then on the same day itself, filed another application under Section 34 read with Section 36 of the A&C Act, 1996 for stay of the award. Thereafter, another petition on 23.03.2023 under Order 21 Rule 28 read with Section 47 of the CPC, was filed by the petitioner for stay of the execution proceedings in the Execution Case. Both these applications dated 15.03.2023 and 23.03.2023, were then rejected by order dated 30.05.2023 by the learned Commercial Court. As such, these two impugned orders dated 15.03.2023 and 30.05.2023 have now come to be challenged before this Court by way of the instant application under Article 227 of the Constitution of India.
2. At the outset, the respondent counsel Mr. P. Jain, has raised preliminary objections on the ground that the present petition is premature, as the application for stay sought by the petitioner is yet to be decided finally by the learned Commercial Court, and as such there is no cause of action, let alone any grounds for interference under Article 227 of the Constitution of India. It has also been contended that the petitioner, has not established as to how the present common petition is maintainable against first, the impugned order dated 15.03.2023 passed in deciding the maintainability of the petition under Section 36 of the A&C Act, 1996 and secondly, against the order dated 30.05.2023 passed in the two applications filed under Order 21 Rule 29 read with Section 47 CPC and Section 36 read with Section 34 respectively, seeking stay of the Execution proceedings and the Arbitral Award. No pleadings are present it is asserted, or any explanation offered as to how orders passed under A&C Act could be challenged under Article 227 as in any case, orders arising out of Section 34 or related thereto, would lie exclusively under the A&C Act.
3. It has also been submitted that the application of the petitioner under Section 36 is yet to be decided, and the deposit as directed by the learned Commercial Court, is in accordance with the law laid down by the Supreme Court mandating 100% deposit as the standard rule in case of execution of arbitral awards. In this context, reliance has been placed upon the cases of (i) Toyo Engineering Corporation vs. Indian Oil 2021 SCC Online SC 3455 (ii) SREI Infrastructure Finance Ltd. vs. Candor Gurgaon Two Developers and Projects Pvt. L
Board of Control for Cricket in India vs. Kochi Cricket Pvt Ltd
Union of India vs. Vedanta Ltd.
Ssangyong Engineering and Construction Company Ltd. vs. National Highway Authority of India
The main legal point established in the judgment is that the unamended Section 36 of the Arbitration and Conciliation Act does not provide for automatic stay of the award pending the application unde....
The court emphasized the limited scope of interference by the court in arbitration proceedings and the need to make a prima facie case for granting a stay of execution of the arbitration award.
An unconditional stay of an arbitral award is impermissible unless specific statutory conditions under Section 36(3) of the Arbitration Act are fulfilled.
The Amendment to Section 36 clarifies there is no automatic stay of arbitral awards upon filing a Section 34 application, affecting the calculation of limitation periods for enforcement.
Execution of an arbitral award requires compliance with the 90-day limitation under Section 34; execution petitions filed before this period are impermissible.
The Court emphasized the importance of adhering to the statutory provisions of the Arbitration and Conciliation Act, particularly regarding the filing of Section 34 applications during the pendency o....
The court emphasized that conditions for staying an arbitral award must be reasonable and justified, adhering to established legal principles.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.