S.C. Gupte, J.
Jerson John Braganza —Applicant
versus
John Braganza & Ors. —Defendants
Notice of Motion Nos.659 of 2014 & 4016 of 2007 In Suit No.2975 of 2007
Decided on 26.4.2016

Important Points

IMPORTANT POINT
Mere possession, however long, does not entitle possessor to raise plea of adverse possession.

Subject

Limitation - Adverse Possession

Act Referred

LIMITATION ACT : Art.65

Headnote

Limitation Act, 1963—Article 65—Adverse possession—Bar of limitation—Onus is on defendant to prove adverse possession—In order to constitute adverse possession, possession proved must be adequate in continuity, in publicity and in extent so as to show that it is adverse to true owner—Such possession must be coupled with ‘animus possidendi’—Possessor claiming such possession must show a requisite animus of asserting such possession through period of prescription—Defendants have not so far proved any of their documents showing possession since 1963—There was simply a case of long continuous possession on part of Defendant which he was entitled to protect against world at large save and except true owner—Owner himself is entitled to recover possession based on his title by due process of law—Defendants have failed to establish adverse possession for statutory period of twelve years—Consequently, their plea of bar of limitation fails. (Paras 4, 7, 8, 11, 12 and 13)

       Result: Notice of Motion disposed of.

Advocates:
Counsel for the Parties:
For the Applicant:Mr. R.A. Thorat, Senior Advocate alongwith Mr.P.J. Thorat, Advocate
For the Defendants:Mr.Anil D’souza, Advocate

ORDER

S.C. Gupte, J.—The Plaintiff has filed the present suit for possession of the suit premises. The Plaintiff has taken out a notice of motion in the suit (Notice of Motion No.4016/2007) for appointment of Court Receiver and interlocutory injunction restraining the Defendants from creating third party rights in respect of the suit premises. During the pendency of the suit, the original Defendant expired and his heirs were brought on record as Defendant Nos.1(a), 1(b) and 1(c).

These Defendants object to the maintainability of the suit on the ground of bar of limitation and have moved a notice of motion (Notice of Motion No.659/2014) for framing and deciding a preliminary issue in that behalf. By his order dated 29 January 2015, a learned Single Judge of this Court was pleased to frame the following issue as a preliminary issue :

“Whether the suit is filed within the period provided under Law of Limitation?”

The parties have chosen not to lead any oral evidence on the preliminary issue and instead argue the same on pleadings and admitted documents. This order disposes of the preliminary issue.

2. The Plaintiff’s case in brief may be set out thus:

The Plaintiff claims to be an absolute owner and as such seized and possessed of the suit property. The suit property is part of a larger property consisting of a plot of land admeasuring 14770.60 sq.mtrs. being part of Survey Nos.32, 33 and 36 and bearing CTS Nos.70, 71, 72, 73, 74, 75, 84A and 84/7 of Village Kurar and situate at Pratap Nagar, Daftary Road, Malad (East), Mumbai – 400 097. Out of this larger property, the Defendant is said to be in possession of a plot of land admeasuring 1474 sq.yards bearing Survey No.33, Hissa No.1 corresponding CTS No.72 of Village Kurar together with the structures standing thereon (hereinafter referred to as “the suit premises”). The Plaintiff has traced his title to the larger plot of land, including the suit premises. By a Deed of Conveyance dated 13 June 1975 duly registered with the Sub-Registrar of Assurances, Bombay, the larger plot of land, originally jointly owned by one Shantaram Bhalchandra Sukhtankar (“Shantaram”) and Sitaram Bhalchandra Sukhtankar (“Sitaram”), was released and transfered unto Sitaram by Shantaram. By a Deed of Partnership dated 30 November 1976 Sitaram entered into partnership with Prataprai Nandlal Kothari (“Prataprai”), father of the Plaintiff herein, to carry on business in the firm name and style as Nilesh Construction Company for redevelopment of the larger plot of land. The larger plot of land was brought into the joint stock of the firm as capital of Sitaram. The partnership was subsequently dissolved by a duly registered Deed of Dissolution dated 30 April 1977 executed between the partners. By that Deed of Dissolution, Sitaram released his right, title and interest in the larger plot of land in favour of Prataprai for consideration received thereunder. The larger plot of land is shown in the revenue records in the name of Prataprai. Prataprai exercised his ownership rights in respect of the land inter alia by filing an application for exemption under Section 20 of the Urban Land (Ceiling and Regulation) Act, 1976 as also converting the same from agricultural to non-agricultural use by N.A. orders. Prataprai also obtained municipal sanction to the building plans for construction of building/s on the larger plot of land. It is the Plaintiff’s case that the Defendant is an encroacher in respect of a portion of the larger plot of land, namely, the suit premises. Sometime in 1981, the Defendant filed a suit, being Suit No.3120/1981, against Prataprai in the City Civil Court at Bombay for permanent injunction restraining Prataprai from disturbing the alleged possession of the Defendant in respect of the suit premises otherwise than in accordance with due process of law. The City Civil Court, after recording evidence of both parties, decreed the suit in favour of the Defendant. That decree was challenged by Prat