IN THE HIGH COURT FOR THE STATE OF TELANGANA AT HYDERABAD
SUREPALLI NANDA, J.
M/s S.K. Swamy and Company – Petitioner
Versus
Union of India and Others – Respondents
Writ Petition No. 35956 of 2015
Decided On : 03-06-2024
Contract - Writ of Mandamus - Section 70 of the Contract Act, 1872; General Conditions of Contract (GCC) Clauses 39, 43 - The court upheld the petitioner's claims for additional work payments based on approved variations and recommendations from the Pre-Arbitration Committee, emphasizing the binding nature of such approvals.
Fact of the Case:
The petitioner, a civil contractor, sought payment for additional work done under a contract with the respondents, which was approved by the Chief Engineer. The respondents withheld payment despite recommendations from a Pre-Arbitration Committee supporting the petitioner's claims.
Finding of the Court:
The court found that the petitioner had completed the work as per the contract and that the claims for additional payments were justified based on the approvals and recommendations from the relevant authorities.
Issues: Whether the petitioner is entitled to the amounts recommended by the Pre-Arbitration Committee for additional work done under the contract.
Ratio Decidendi: The court held that the recommendations of the Pre-Arbitration Committee, along with the approvals from the Chief Engineer, were binding and that the respondents could not deny payment without valid grounds.
Result: The Writ Petition is allowed, directing the respondents to release the amounts due to the petitioner as per the recommendations of the Pre-Arbitration Committee.
ORDER :
1. Heard Sri A. Sudershan Reddy, the learned Senior designate counsel appearing on behalf of Petitioner, the learned Deputy Solicitor General of India appearing on behalf of respondent No. 1 and Smt. Anjali Agarwal appearing on behalf of respondent Nos.2 and 3.
2. The petitioner approached the Court seeking prayer as under:
3. PERUSED THE RECORD:
Approval of Chief Admn. Officer/Con/SC is hereby communicated for the variation to a net and gross value of Rs.12,44,85,096.85Ps. Variation statement is sent herewith, in duplicate, alongwith rate analysis for verification and early return.
The subject work was awarded to M/s. S.K. Swamy & Co. Bangalore at an agreement value of Rs.8,36,88,936.85 Ps.
Dy. CE/C/GTL has submitted First variation vide letter dated 18-03-2011(P-178)
Dy. CE/C has mentioned in the letter that during execution it is necessitated to operate one additional NS item extra over item No. 1 & 2 of Schedule-A for cutting rock and scooping out the debris outside the area to enable to complete the box pushing. Accordingly the variation statement is submitted duly proposing additional NS item for extra over for box pushing hard rock strata for a quantity of 2.875 Sqm per RM with a rate of Rs.14,325/-amounting to Rs.4,11,84,375/- which works out to gross excess of 49.12% over the agreement value.
As per the details of rate for additional NS item submitted by Dy.CE/.C
Rate for R M-Rs.6,73,000 (Agt.No. 11/Dy.CE/CN/MAS/2009, dated 06.04.2009)
Box size 5.50 x 3.66m=20.13 Sqm per RM
Rate for Sq m per RM=6,73,000/20.13=33,432.69 Rate for Sq.m per R M for item No. 1 & 2
Of Schedule-A of the same Agt. =19,107.73
Difference in Rate
14,324.95 or Say
Rs.14,325 Sq.m per RM
However, CAO/C has approved this proposal for a quantity 3840 Sqm pr RM with a rate of Rs. 10,624/- vide N-
8. Therefore the details for additional NS item will be as below:
| S. No. | Description of item | Qty | Rate | Unit | Amount in Rs. | Remarks |
| 1 | Extra over item No. 1&2 of Schedule-A for cutting rock by approved methods such as chemical disintegration of rock by any other approved method and scooping out the debris out side the area with all contractors materials, labour, tools, plant and machinery all lead lift and lift ect., complete as directed by the Engineer-in-Charge | 3840 | 10,624.00 | Sq. m. per R.M. | 4,07,96,160.00 | While executing of thrust bed, the front face of box pushing encountered with full of rock which cannot be removed by ordinary blasting under the traffic |
Original Agt.Value Rs.8,36,88,936.85
Value of one addl.N.S.item Rs.4,07,96,160.00
Net & Gross value Rs.12,44,85,096.85
Net & Gross excess and
percentage Rs.4,07,96,160.00 (i.e.48.75%)
Negotiations required for
one addl NS item Rs.4,07,96,160.00
Dy.CE/C has certified that there is no vitiation due to variation, since no savings occurred vide letter date 18.03.2011 (F-178).
Administrative approval of CE/C is required to the First variation in terms of item no. 9 of part A of SOP 2009, to process further with Finance for concurrence. Since the overall excess is exceeded beyon
Unitech Ltd. & Others Vs. Telangana State Industrial Infrastructure Corporation (TSIIC) & Others
M/s. Radhakrishnan Industries Vs. State of Himachal Pradesh
Magadh Sugar and Energy Limited Vs. State of Bihar and Others
Court exercising jurisdiction under Article 226 of the Constitution of India is also a Court of Equity It will have to be mindful of interests of justice and ensure that in rigidly applying technical....
A writ petition is not the appropriate remedy for disputes relating to contractual obligations. Such disputes should be resolved through civil suits.
The jurisdiction of the court under Article 226 of the Constitution cannot be ousted by an agreement executed between the parties.
Contractual agreement - Whether existence of arbitral agreement between parties that High Court of Delhi alone will have jurisdiction to try dispute arising out of contract is enforceable in law - Un....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.