IN THE HIGH COURT OF DELHI AT NEW DELHI
Harish Vaidyanathan Shankar, J
National Highways Authority Of India – Appellant
Versus
Patel Knr Heavy Infrastructure Pvt Ltd – Respondent
O.M.P. (COMM) 195/2023
| Table of Content |
|---|
| 1. overview of the dispute regarding bit thickness and arbitral award validity. (Para 1 , 2 , 3 , 4 , 5) |
| 2. dispute on contractual interpretation of pavement maintenance standards. (Para 6 , 7 , 8 , 9 , 10 , 11 , 12) |
| 3. contention regarding liquidated damages and penalties for maintenance delays. (Para 13 , 14 , 15 , 16 , 17 , 18) |
| 4. respondent arguments affirming tribunal decision and contractual distinctions. (Para 19 , 20 , 21 , 22 , 23 , 24 , 25 , 26) |
| 5. court analysis concluding the arbitral award is a plausible, reasonable interpretation. (Para 27 , 28 , 29 , 30 , 31 , 32 , 33 , 34 , 35 , 36 , 37 , 38 , 39 , 40 , 41 , 42 , 43 , 44 , 45 , 46 , 47 , 48 , 49 , 50 , 51 , 52 , 53 , 54 , 55 , 56 , 57 , 58) |
J U D G M E N T
HARISH VAIDYANATHAN SHANKAR, J.
1. The present Petition under Section 34 of the Arbitration and Conciliation Act, 19961A&C Act, has been preferred assailing the Arbitral Award dated 16.01.20232Impugned Award, rendered by the majority of the members of the learned Arbitral Tribunal, as well as the dissenting Award dated 23.01.20233Dissenting Award passed by the learned third Arbitrator.
2. By way of the Impugned Award, the learned Arbitral Tribunal has, in sum and substance, allowed the claim of the Respondent towards the cost incurred on account of the additional thickness of 10 mm Bituminous Concrete4BC applied as a renewal coat on the Project Highway5Project Highway, which constitutes the core subject matter of the present challenge.
3. Further, the limited challenge raised herein to the dissenting Award pertains to the rejection of the Counter-Claim preferred by the Petitioner and, to that extent, is in consonance with and supportive of the Majority Award.
BRIEF FACTS:
4. The facts germane to the institution of the present Petition are as follows:
a. The Petitioner herein invited proposals for Design, Construction, Development, Finance, Operation and Maintenance of “2 lane portion from Km 230/000 to Km 278/000, covering 53.017 kilometres” NH-7 on a Build-Operate-Transfer Annuity basis vide notice dated 07.07.2006, subject to the terms and conditions contained in the tender notice.
b. The Respondent emerged as the successful bidder. Consequent thereof, a letter of acceptance was issued by the Petitioner to the Respondent dated 30.03.2007 and thereafter, the parties entered into a Concession Agreement dated 05.09.20076Agreement.
c. The work scope, as laid down in the Agreement, was as follows:
i. To develop, design, engineer, finance, construct, operate and maintain the project highway during the concession period.
ii. Upon completion of the Project highways and during the operations period, to manage, operate and maintain the project highway and regulate the use thereof by third parties,
iii. to allow NHAI to levy, demand, collect and appropriate the fees from vehicles and persons liable to payment of fees for using the project Highways or any part thereof as per Article VII,
iv. perform and fulfil all of the Concessionaire's obligations under this agreement,
v. bear and pay all expenses, cost and charges incurred in the fulfilment of all the Concessionaire's obligations under this Agreement, and
vi. not assign or create any lien or encumbrance on the concession hereby granted on the whole or any part of the Project Highways, nor transfer, lease, or part possession therewith, save and except as expressly permitted by the agreement or the substitution Agreement.
d. The date for commencement of the Project was 02.03.2008 with a total concession period of 20 years, which included a construction period of 2 years and Operation and Management of 18 years.
e. For the sake of clarity, the timeline and milestones that were decided as per the Agreement are tabulated herein below:
| PARTICULARS | DATE/PERIOD |
|---|---|
| Date of signing the Concession Agreement | 05.09.2007 |
| Period of Concession Agreement | 20 years |
| Construction Period | 24 months |
| Development period | 05.09.2007 - 02.03.2008 (180 days) |
| Scheduled Project | |
OPG Power Generation (P) Ltd. v. Enexio Power Cooling Solutions (India) (P) Ltd.
Ssangyong Engg. & Construction Co. Ltd. v. NHAI
ONGC Ltd. v. Western Geco International Ltd.
State of Chhattisgarh v. SAL Udyog (P) Ltd.
Patel Engg. Ltd. v. North Eastern Electric Power Corpn. Ltd.
DMRC Ltd. v. Delhi Airport Metro Express (P) Ltd.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.