COURT OF APPEAL PUTRAJAYA
KINU SDN BHD – Appellant
Versus
KERAJAAN MALAYSIA (JABATAN KERJA RAYA MALAYSIA) – Respondent
[Civil Appeal No: W-01(C)(A)-523-08-2024]
| Table of Content |
|---|
| 1. appeal from high court dismissal of cipaa application. (Para 1 , 4 , 9) |
| 2. dispute over money 'due or payable' under cipaa. (Para 2 , 3 , 10 , 11) |
| 3. high court's interpretation of principal's liability. (Para 5 , 6 , 7 , 12) |
| 4. definition of 'principal' under cipaa. (Para 13 , 14 , 15) |
| 5. cipaa applies to all construction contracts. (Para 21 , 22 , 23) |
| 6. principal's obligations and rights under cipaa. (Para 24 , 25 , 26) |
| 7. interpretation of payment obligations under cipaa. (Para 31 , 32) |
| 8. requirements for direct payment under cipaa. (Para 39 , 40 , 41) |
| 9. evidential burden in cipaa applications. (Para 51 , 52 , 53) |
| 10. consequences of principal's non-compliance with notice requirements. (Para 56 , 57 , 58) |
| 11. retention sums and their treatment under cipaa. (Para 69 , 70 , 71) |
| 12. adverse inferences drawn from failure to produce evidence. (Para 81 , 82 , 83) |
| 13. clarification of terms 'due or payable' in cipaa. (Para 110 , 112 , 113) |
| 14. court's decision to allow appeal and order direct payment. (Para 124) |
[1] This is an appeal from a decision of the High Court that had dismissed a s 30 of the Construction Industry Payment and Adjudication Act 2012 ("CIPAA") application by the successful claimant (subcontractor) in an adjudication decision for an order to compel the principal (employer) to make direct payment to it on account of money "due or payable" by the principal to the unsuccessful respondent in the adjudication who is the main contractor.
[2] The issues raised in this appeal were whether retention sum retained by the principal from certified amounts due to the main contractor was money "due or payable" to the main contractor from the principal and whether on the balance of probabilities the subcontractor had proved that there was money "due or payable" from the principal to the main contractor when the request for payment was served on the principal under s 30(1) of the CIPAA.
[3] It was also argued by the principal who is the Government of Malaysia ("GOM") and more particularly Jabatan Kerja Raya ("JKR") that since it did not recognise nor consent to the main contractor appointing the subcontractor, it was not bound to make any payments under s 30 of the CIPAA.
In the High Court Below
[4] The subcontractor KSB was the plaintiff in the High Court below and the appellant here. The GOM/JKR was the defendant below and the respondent here.
[5] The High Court held that the liability of the principal to pay if there is a debt due or payable from it to the main contractor is irrespective of whether the subcontractor is recognised or approved by the principal, as this is not a requirement under s 30 of the CIPAA.
[6] The High Court was satisfied that there was no money "due or payable" from the principal to the main contractor, the losing party in the adjudication as the last Interim Payment Certificate ("IPC") in IPC No 84 showed a negative sum of RM1,788,581.24 as the recommended amount for payment by the GOM to NSB, the main contractor.
[7] The High Court had further held that there was an issue as to whether there was a debt due or payable from the principal to the main contractor in that there was a dispute as to whether the percentage of works completed at the point of termination of the contract by the principal of the main contractor was physical or financial completion. The High Court held that such a dispute was essentially to be resolved between JKR and its main contractor, NSB.
[8] The High Court had thus dismissed the plaintiff's/subcontractor's application under s 30 of the CIPAA. The plaintiff had appealed to the Court of Appeal.
Before The Court Of Appeal
[9] The plaintiff appealed to the Court of Appeal on the ground that the plaintiff had proved on the balance of probabilities that there was money "due or payable" from JKR to the main contractor NSB which money was more than enough to satisfy the adjudicated amount that the plaintiff had obtained and enforced against the main contractor.
[10]
Aspen Glove Sdn Bhd v. Tialoc Malaysia Sdn Bhd
Krishnadas Achutan Nair & Ors v. Maniyam Samykano
Kasugi Prima Sdn Bhd v. Cobrain Holdings Sdn Bhd
Murni Environmental Engineering Sdn Bhd v. Eminent Ventures Sdn Bhd & Anor
Cabnet Systems [M] Sdn Bhd v. Dekad Kaliber Sdn Bhd & Anor
Pali PTP Sdn Bhd v. Bond M&E Sdn Bhd & Anor Appeal
HSL Ground Engineering Sdn Bhd v. Civil Tech Resources Sdn Bhd
Cubic Electronics Sdn Bhd v. Mars Telecommunications Sdn Bhd
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.