SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 MarsdenLR 5269

HIGH COURT MALAYA KUALA LUMPUR
AGILE PJD DEVELOPMENT SDN BHD – Appellant
Versus
CHINA CONSTRUCTION YANGTZE RIVER (MALAYSIA) SDN BHD – Respondent
[Originating Summons No: WA-24NCC-141-03/2024]



Petitioner Advocates:Foo Joon Liang,Carissa How Chen Huey,Chiew Zhe Sheng ,Respondent Advocate: Choon Hon Leng,Khor Yongshi,Cheryl Leong See Teng

The court clarified that adjudication decisions are binding and enforceable in winding up proceedings unless specifically set aside, and bona fide disputes must be genuine and not previously adjudicated.

Headnote:(A) Specific Relief Act 1950 - Sections 50 and 51(2) - Construction Industry Payment and Adjudication Act 2012 - Adjudication decisions binding and enforceable unless set aside or stayed - Profound implications of adjudication decisions on solvent disputes clarified - Legal standards established for Fortuna injunctions cited in Fortuna Holdings Pty Ltd and others - Court underscored that alleged disputes must be bona fide and that previous adjudications cannot be challenged in winding-up petitions unless they are overturned (Paras 10-19, 27-29).

(B) Bona fide dispute - Not established as counterclaims had been adjudicated or were newly raised claims - Financial capacity of Plaintiff questioned with significant liabilities against limited assets (Paras 19-21).

(C) Concurrent remedies - No prohibition against pursuing enforcement and winding up proceedings simultaneously - Such rights preserved in case law substantiating commercial choice (Paras 22-26).

Facts of the case:
Plaintiff sought a Fortuna injunction to prevent Defendant from filing a winding-up petition following an adjudication decision compelling the Plaintiff to pay substantial sums. The Plaintiff claimed unresolved counterclaims as the basis for disputing the debt.

Findings of Court:
The court determined the Plaintiff failed to demonstrate a bona fide dispute as most claims were previously adjudicated. The application for a Fortuna injunction was dismissed.

Issues: The validity of the debt, the nature of the alleged disputes, and the Plaintiff's financial solvency were critical.

Ratio Decidendi: The court emphasized the binding nature of adjudication decisions and dismissed the Plaintiff’s claims of a bona fide dispute over previously adjudicated issues.

Result: Application dismissed with costs.

Table of Content
1. foundation of plaintiff's winding-up application. (Para 1 , 2 , 3 , 4 , 5 , 6)
2. arguments for and against the fortuna injunction. (Para 7 , 8 , 9)
3. legal framework for fortuna injunctions. (Para 10 , 11)
4. binding nature of adjudication decisions. (Para 12 , 13 , 14 , 15 , 16 , 17)
5. assessment of bona fide disputes and commercial solvency. (Para 18 , 19 , 20 , 21)
6. allowance of concurrent remedies in enforcement actions. (Para 22 , 23 , 24 , 25)
7. grounds for dismissal of the fortuna injunction application. (Para 26 , 27 , 28)
Wan Muhammad Amin Wan Yahya J:

[1] This was the Plaintiff's application for a Fortuna injunction to restrain the Defendant from filing a winding up petition based on a statutory notice of demand dated 29 February 2024 ("this Application").

[2] The statutory notice was founded upon the Corrected Adjudication Decision dated 20 February 2024 ("Corrected Adjudication Decision" or "Adjudication Decision". This Application was brought under ss 50 and 51(2) of the Specific Relief Act 1950 .

A] Salient Background Facts

[3] By letter of award dated 9 December 2016, the Plaintiff engaged the Defendant as the main contractor to carry out construction works for the Agile Mont Kiara Project ("the Project"). The Defendant completed the works on 10 July 2021, with the Certificate of Practical Completion ("CPC") issued on 15 July 2021. However, disputes arose regarding payment, with the Plaintiff alleging that the Defendant failed to complete the works satisfactorily and claiming substantial counterclaims and set-offs.

[4] Due to the Plaintiff's failure to pay, the Defendant issued a Payment Claim dated 3 October 2023 under the Construction Industry Payment and Adjudication Act 2012 ("CIPAA"). The Defendant subsequently commenced adjudication proceedings seeking RM89,333,051.89 or alternatively RM84,050,170.91 plus RM5,282,880.98.

[5] The Adjudicator delivered the Corrected Adjudication Decision on 20 February 2024, essentially ordering the Plaintiff to pay the Defendant:

i) RM59,304,233.53 as the principal adjudicated sum;

ii) 5% simple interest per annum from the date of the decision;

iii) Legal costs of RM30,000.00; and

iv) Further costs of RM59,184.14.

[6] When the Plaintiff failed to pay within the 21-day period, the Defendant issued the statutory notice of demand on 29 February 2024.

B] The Plaintiff'S Arguments

[7] The Plaintiff contended that a Fortuna injunction should be granted on the grounds that:

i) There is a bona fide dispute concerning the debt arising from substantial counterclaims and set-offs totalling RM79,616,815.86 (comprising liquidated damages of RM10,679,748.13, debit notes of RM2,194,713.29, payments on behalf amounting to RM8,246,945.40, direct payments to subcontractors of RM49,722,131.05, direct payments to nominated subcontractors of RM11,995,484.37, and additional costs for fire door defects of RM12,156,894.00).

ii) The Plaintiff is commercially solvent with total assets of RM80,740,003.00.

iii) The winding up petition, if presented, would cause irreparable damage to the Plaintiff.

iv) The petition would have no chance of success.

[8] The Defendant's concurrent pursuit of enforcement under s 28 CIPAA and winding up proceedings is contradictory and inconsistent. There are three relevant applications currently before the Courts:

i) The Defendant's Enforcement application filed via Originating Summons No WA-24C-20-02/2024 dated 23 February 2024, seeking an order that the Corrected Adjudication Decision be recognised as binding and enforceable as a judgment of the court ("Enforcement OS"). The Enforcement OS is scheduled for hearing on 19 July 2024.

ii) The Plaintiff's Setting Aside application filed via Originating Summons No WA-24C-37-03/2024 dated 20 March 2024, which is to be heard together with the Enforcement OS on 19 July 2024.

iii) The Plaintiff's Stay application filed via Originating Summons No WA-24C-39-03/2024 dated 20 March 2024, which is scheduled for hearing on 6 June 2024.

C

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top