SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2016 Supreme(SC) 482

SUPREME COURT OF INDIA
Fakkir Mohamed Ibrahim Kalifulla, C. Nagappan, JJ.
M/s Umesh Goel – Appellant
Versus
Himachal Pradesh Cooperative Group Housing Society Ltd. – Respondent
Civil Appeal No. 7916 of 2009
Decided On : 29-06-2016

IMPORTANT POINTS
All ingredients of sub-sections (1) and (2) of section 69, Partnership Act should be read into sub-section (3) and thereafter apply the said sub-section.
Section 69(3) would come into play when a suit is launched by an unregistered partnership firm or a partner thereof either to a claim for set off in the said suit or any other proceedings intrinsically connected with the said suit.
Section 69 was applied in case of arbitration under Act, 1940 but would not apply to arbitration under Act 1996.
It cannot be held that the entire Arbitral proceeding is a Civil Court proceedings for the purpose of applicability of Section 69(3).

Headnote:(a) Indian Partnership Act, 1932 – Section 69 – Carefully read, it is found that provisions of sub-sections (1) and (2) have been impliedly incorporated in sub-section (3) – The two sub-sections should be held to be bodily lifted and incorporated in sub-section (3) – It is imperative that all ingredients of sub-sections (1) and (2) should be read into sub-section (3) and thereafter apply the said sub-section. (Para 10)

       (b) Indian Partnership Act, 1932 – Section 69(1), (2) and (3) – Sub-section (1) imposes a ban on a partner of an unregistered firm from filing any suit against the firm or any partner to enforce a right arising from a contract or a right conferred under the Partnership Act in any Court – Sub-section (2) imposes the same ban on the partners or the firm as against third party. (Para 11)

       © Indian Partnership Act, 1932 – Section 69(3) – Other proceedings – Section 69(3) would come into play when a suit is launched by an unregistered partnership firm or a partner thereof either to a claim for set off in the said suit or any other proceedings intrinsically connected with the said suit. (Para 13, 14)

       (d) Indian Partnership Act, 1932 – Section 69(3) and (4) – Proceedings specifically excluded in section 69(3)(a) and (b) – Even though such proceedings may fall under the expression “other proceedings” and may be intrinsically connected with a suit in a Court, yet the ban would not operate against such proceedings – ‘Other proceeding’ in sub-section (4) can only relate to a pending suit in a Court and not to any other different proceeding. (Para 15, 16)

       (e) Indian Partnership Act, 1932 – Section 69 – Respondent invoking arbitration clause and appointing arbitrator – Filing its claim – Appellant making appearance and filing counter claim – Respondent trying to invoke section 69 – Arbitrator rightly held that Section 69 has no application to the proceedings of arbitrator. (Para 18)

       (f) Indian Partnership Act, 1932 – Section 69 – Other proceedings – Arbitration – Extent of control and operation of a Court under Arbitration Act, 1940 was far more intensive and elaborate than Arbitration and Conciliation Act, 1996 – Section 69 therefore applied in case of arbitration under Act, 1940 but would not apply to arbitration under Act 1996 – Jagdish Chander will have no application to a post Award situation. (Para 26, 27, 28)

       (2000) 6 SCC 659 – Relied upon

       1964 (8) SCR 50; AIR 1950 SC 188; (2004) 3 SCC 155; (2007) 10 SCC 82; (1993) 4 SCC 338; (2009) 6 SCC 72; 2009 (2) Law Weekly 849; (1998) 8 SCC 559 – Referred

       (g) Indian Partnership Act, 1932 – Section 69 and section 43, Arbitration and Conciliation Act, 1996 – Enforcement of award – What is enforced is the award crystalising the rights of the parties under the Indian Contract Act and the general law to be paid for the work executed – No right arising only from the objectionable contract is enforced – Section 69 has no application. (Para 30)

       (h) Indian Partnership Act, 1932 – Section 69(3) r/w section 14, Limitation Act, 1963 – Section 14, Limitation Act may treat arbitral proceeding at par with a suit but when section 69(3) does not apply to post award proceedings, there is no question of treating arbitral proceeding at par with court proceeding. (Para 32)

       2008 (6) SCALE 748; (2000) 5 SCC 355 – Distinguished

       (i) Arbitration and Conciliation Act, 1996 – Section 35 and 36 – Section 35 makes the award binding on the parties – Section 36 only creates a statutory fiction limited for the purpose of enforcement of the Award – Therefore, it cannot be held that the entire Arbitral proceeding is a Civil Court proceedings for the purpose of applicability of Section 69(3). (Para 34)

       (2004) 6 SCC 59; (2006) 13 SCC 322 – Relied upon

       Facts of the case:

       An interesting but very important legal question arises for consideration in this appeal relating to interpretation of Section 69(3) of the Indian Partnership Act with reference to its applicability to Arbitral proceedings.

       The respondent, a Cooperative Group Housing Society, invited tenders for construction of 102 dwelling units with basement at Plot No. 21 Sector 5, Dwarka New Delhi. The tenders were invited in May 1998.

       The appellant, an unregistered partnership firm, was the successful bidder and the contract was awarded to the appellant at an estimated cost of Rs.9.80 crores.

       The appellant submitted its first bill for the construction of the compound wall etc.

       A dispute arose as between the appellant and the respondent which necessitated the appellant to move the High Court of Delhi by way of an application under Section 9 of the Arbitration and Conciliation Act 1996 to restrain the respondent from dispossessing the appellant from the worksite till the work executed by the appellant is measured by the Commissioner to be appointed by the Court.

       A Commissioner was appointed by the High Court. The appellant filed another application under Section 9 of the 1996 Act to restrain the respondent from operating its bank accounts and from dispossessing the appellant.

       An arbitrator/an advocate namely Smt. Sangeeta Tomar was appointed by the respondent.

       The appellant participated in the arbitration proceedings before the arbitrator appointed by the respondent. Claims and counter claims were made.

       The arbitrator passed the award on 05.05.2005 wherein the claim of the appellant was allowed to the extent of Rs. 1,36,24,886.08 along with interest at the rate of 12% from 01.06.2002 till the date of the award and further interest from the date of award till its payment at the rate of 18% per annum.

       The respondent challenged the award before the Delhi High Court which was dismissed by the Single Judge. The Review Application filed by the respondent was also dismissed. Respondent’s appeals thereagainst was allowed.

       Finding of the Court:

       Bar under section 69(3), Partnership Act does not apply to post award proceedings.

       Result: Appeal allowed.

JUDGMENT :

Fakkir Mohamed Ibrahim Kalifulla, J.

1. An interesting but very important legal question arises for consideration in this appeal relating to interpretation of Section 69(3) of the Indian Partnership Act with reference to its applicability to Arbitral proceedings.

2. The facts are not in controversy which can be briefly stated as under: The respondent which is a Cooperative Group Housing Society invited tenders for construction of 102 dwelling units with basement at Plot No. 21 Sector 5, Dwarka New Delhi. The tenders were invited in May 1998. The appellant, an unregistered partnership firm submitted its bid in response to the said tender on 06.05.1998. The appellant was the successful bidder and the contract was awarded to the appellant at an estimated cost of Rs.9.80 crores. The appellant was issued a letter of intent. On 09.08.1998 the appellant submitted its first bill for the construction of the compound wall etc. The agreement for the construction of 102 dwelling units with basement was entered into between the appellant and the respondent on 02.02.1999. It is stated that there was some delay in getting the plan sanctioned, which according to the appellant, he was not responsible for the delay. A dispute arose as between the appellant and the respondent which necessitated the appellant to move the High Court of Delhi by way of an application under Section 9 of the Arbitration and Conciliation Act 1996 (for short “1996 Act”) to restrain the respondent from dispossessing the appellant from the worksite till the work executed by the appellant is measured by the Commissioner to be appointed by the Court. It was filed on 22.05.2005. A Commissioner was also appointed by the High Court. The appellant filed another application under Section 9 of the 1996 Act to restrain the respondent from operating its bank accounts and from dispossessing the appellant on 29.01.2003.

3. With reference to the dispute which arose as between the appellant and the respondent an arbitrator/an advocate by name Smt. Sangeeta Tomar was appointed by the respondent to adjudicate the dispute between them. As the appointment came to be made on 17.03.2003 by the respondent, though, the appellant earlier moved the High Court by way of an Arbitration Application No.145 of 2003 on 09.07.2003 under Section 11(5) of the 1996 Act for appointment of an independent arbitrator, the same was subsequently withdrawn. The appellant participated in the arbitration proceedings before the arbitrator appointed by the respondent. Claims and counter claims were made by the appellant as well as the respondent before the arbitrator. The arbitrator passed the award on 05.05.2005 wherein the claim of the appellant was allowed to the extent of Rs. 1,36,24,886.08 along with interest at the rate of 12% from 01.06.2002 till the date of the award and further interest from the date of award till its payment at the rate of 18% per annum. While resisting the claim of the appellant, the respondent did not specifically raise any plea under Section 69 of the Partnership Act.

4. The respondent challenged the award dated 05.05.2005 under Section 34 of the 1996 Act before the Delhi High Court which was registered as A.A. No.188 of 2005. The said application was filed on 02.08.2005. The respondent’s application was dismissed by the learned Single Judge by an order dated 01.09.2005. The respondent filed Review Application No.26 of 2005 which was also dismissed by the learned Single Judge by an order dated 03.10.2005. As against the orders dated 01.09.2005 and 03.10.2005, the respondent preferred appeals in FAO (OS) No.376 of 2005 on 14.11.2005. Pending disposal of the appeals, an interim order was passed on 21.07.2006 directing the respondent to deposit 50% of the decretal amount within six weeks and by subsequent order dated 18.08.2006 the time was extended by another four weeks. By the impugned order dated 20.11.2007 the Division Bench having allowed the FAO(OS) No.376 of 2005, the appella

























































Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top