External Factors Causing Delays - Courts have recognized that delays attributable to external parties such as site conditions, natural calamities, insurgency, or pandemic disruptions are often justified and do not constitute contractor fault C.A.MUHAMMED IQBAL Vs STATE OF KERALA - Kerala, T. APPUKUTTAN Vs STATE OF KERALA - Kerala, T.L. Construction vs Union Of India - Gauhati, M/s.State Industries Promotion Corporation Of Tamil Nadu Ltd. vs M/s.RPP Infra Projects Limited (Formerly Known As RPP Construction (P) Ltd.) - Madras.
Responsibility and Justification for Delays - When delays are caused by external obstacles like site identification issues, site blockages, or unforeseen events, courts tend to uphold the contractor's claim for extensions or absolve them of responsibility UTTAR PRADESH STATE BRIDGE CONSTRUCTION CORPORATION LIMITED, VS LUCKNOW BANGALORE DEVELOPMENT AUTHORITY - Karnataka, T. APPUKUTTAN Vs STATE OF KERALA - Kerala, CHACKO JOSEPH vs STATE OF KERALA - Kerala.
Contractual and Procedural Considerations - Courts emphasize the importance of adhering to contractual provisions, procedural fairness, and proper documentation when external delays occur. The absence of arbitration clauses or failure to respond timely can influence case outcomes UTTAR PRADESH STATE BRIDGE CONSTRUCTION CORPORATION LIMITED, VS LUCKNOW BANGALORE DEVELOPMENT AUTHORITY - Karnataka, Krishi Ifratech Bangalore VS Union of India - Calcutta.
Insurance and External Delays - Insurance claims related to bridge failures or delays are subject to strict interpretation of exclusion clauses, with courts often holding insurers accountable when delays stem from external causes like structural failures or natural disasters United India Insurance Co. Ltd. VS Hyundai Engineering & Construction Co. Ltd. - Supreme Court, UNITED INDIA INSURANCE CO. LTD. vs M/S. HYUNDAI ENGINEERING AND CONSTRUCTION CO. LTD. - Supreme Court.
Impact of External Events like Pandemics - Extraordinary external events, such as COVID-19, have been accepted as valid reasons for delays, leading courts to grant extensions or adjust contractual obligations accordingly PNC-TRG (JV) vs National Highways Authority of India - Delhi.
Analysis and Conclusion:
Courts generally recognize external parties' actions or unforeseen events—such as natural disasters, site issues, insurgency, or pandemics—as valid causes of delays in bridge projects. When delays are proven to stem from these external factors, contractors are often granted extensions or relief from penalties, provided they substantiate their claims with proper documentation and adhere to contractual procedures. Insurance disputes also hinge on the interpretation of exclusion clauses, with courts tending to hold insurers accountable when delays or failures are due to external causes beyond the contractor's control.
Finding of the Court: The court acknowledged the petitioner's delays were partially justified by external factors and ... Fact of the Case: The petitioner contracted for toll collection on specified bridges, faced delays in payments due ... delays were justified. ... A reading of Ext.P4 report of the Superintending Engineer would show that the delay caused by the petitioner in payment is not wholly without justification. On the opening of the new Goshree #HL_START....
The court held that the appellant was not responsible for the delay in completion of the project because the delay was caused by ... The court also held that there was no arbitration clause in the agreement between the parties and that the appellant was not precluded ... Whether there was an arbitration clause in the agreement between the parties and whether the appellant was precluded from seeking ... itself and there is no requirement of any external aid. ... Seen in this light, the ....
, citing delays caused by obstacles beyond his control, including delays in site identification for dumping dredged material and ... Ratio Decidendi: The court established that delays caused by reasons outside of the contractor's control cannot serve as grounds ... emphasizing the necessity for contract performance despite external hindrances not attributable to the petitioner, shaping its decision ... EXHIBIT P15 ORIGINAL PHOTOGRAPHS OF THE INCOMPLETE BRI....
were caused by external factors, not his fault. ... (Paras 2-14) ... ... (B) Procedural Fairness - It was ruled that all parties must be given a fair ... Facts of the case: ... The petitioner, a contractor, sought to quash orders imposing penalties for work left undone, arguing that delays ... According to the petitioner, the construction of the bridge was impossible without blocking the entire road and demolishing the existing cartable bridge at Velamkadavu, for which no provision ....
... ... Findings of Court: ... The court recognized the delays due to external factors and underscored the necessity of adherence ... of contract and entitlement to revised compensation - Disputes arising from delays due to insurgency and other causes - Acknowledgment ... terms and ongoing obligations of the parties. ... proceeding between the parties.” ... In addition, in the year 2008, the bridge at Tzutsung river, the only connecting b....
Engineer, citing failure to form a Dispute Adjudication Board, lack of reasons for termination, and inability to complete work due to external ... to respond before the contract was rescinded. ... Natural Justice - Termination of Contract - Clause 62, 63, 64 - The court emphasized the necessity of adhering ... All the parties are directed to act on the basis of the server copy of the order. ... The drawings had been supplied in respect of bridge Nos.5, 7, 10 in the first week of February and ....
caused by the Covid pandemic and the demise of the Presiding Arbitrator - The court allowed the extension due to no objection from ... ... ... Issues: Whether to extend the mandate of the arbitral tribunal due to delays. ... Delays were attributed to the pandemic and the substitution of the presiding arbitrator. ... Ltd) and respondent-National Highways Authority of India (NHAI) with regard to certain disputes arising out of a contract dated 19.9.2007, for the work of four laning of Km 51.00 to Km. 61.00 (including Cha....
Section 23[Consumer Protection Act, 2019 – Section 67] – Insurance – Contractor’s All Risk Insurance Policy – Death of 48 workmen in bridge ... cannot be asked to cover a loss that is not mentioned – Exclusion clauses in insurance contracts are interpreted strictly and against ... (A) Insurance Act, 1938 – Section 45 – Insurance – Insurance is a contract of indemnification, being a contract ... The Chambal Bridge Accident was a sudden and catastrophic structural failure. It may be pointed out that the #....
The respondent contended that the delays were due to external factors. ... a concrete retaining wall claiming abandonment due to delays caused by the respondent's inability to efficiently manage the work ... The claims made were supported by the Arbitrator's analysis of circumstantial evidence regarding the delays. ... Chenab Bridge Project Undertaking reported in 2023 9 SCC 85 and Paragraph 28 is extracted hereunder: 28. The conclusion [Chenab Bridge Project v. Konka....
that exclusion clauses in insurance contracts are interpreted strictly against the insurer, who bears the burden of proving their ... (Paras 1, 14.1, 14.3, 30) ... ... (B) Insurance Contracts - Exclusion Clauses - The court emphasized ... The appellant challenged the NCDRC's order directing payment of Rs. 39,09,92,828/- for an insurance claim related to a collapsed bridge ... Concrete batching plants involved were of a lower capacity, leading to delays in construction of the lateral spans. Para 8.1.2 (iii) was also bro....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.