EPC contracts (Engineering, Procurement, and Construction) are foundational in India's infrastructure and power sectors. These turnkey agreements bundle design, procurement, and construction under one contractor, but they come with strict legal requirements that can make or break projects. From tender qualifications to arbitration enforcement, understanding these is crucial for contractors, developers, and government entities alike.
This post breaks down EPC contract requirements based on landmark Supreme Court judgments and statutory principles. We'll explore eligibility criteria, arbitration applicability, stamp duty hurdles, and judicial oversight—drawing directly from key cases. Note: This is general information, not legal advice. Consult a qualified lawyer for your specific situation.
Tender processes for EPC contracts demand rigorous pre-qualification to ensure capable bidders. Courts emphasize deference to tendering authorities.
of the contract between the parties. ... of refund bank guarantees issued under the contracts. ... The agreement contained an arbitration clause for resolution of disputes arising out of the contract. ... The award related to an EPC (Engineering, Procurement and Construction) Contract dated 4th November, 2005 (“the EPC Contract#HL_END....
terms and conditions of contract, then no fault can be found, if Arbitrator proceeds to accept one interpretation as against other ... UHL has filed Civil Appeal No. 10342 of 2011 and the State of Himachal Pradesh has filed Civil Appeal No. 10342 of 2011, as both ... in re-appreciating findings returned by Arbitral Tribunal and taking an entirely different view in respect of interpretation of ... ....
breach of contract by State, cannot be dressed up and disguised as a case of arbitrary State action – Violation of natural justice ... PPA’) – Termination of – Termination of a contract results in intrusion into and deprivation of valuable rights which are vouchsafed ... or a subordinate legislation – Terms and conditions of PPA are not transplanted into PPA fro....
- Court are of considered view that finding in SMS Tea Estates and Garware that non-payment of stamp duty on commercial contract ... entered into a sub-contract termed as a Work Order dated with Appellant Company - M/s. ... contract, would be an arbitrable dispute – Held, ground on which fraud was held to be non arbitrable earlier was that it would entail ... It is as if two contracts-one in regard to the substantive terms of the ma....
If the parties had been acting in a particular manner for a long time upon interpreting the terms and conditions of the contract, ... two years as per the contract. ... Clause 2 of Article 14 postulates that pending arbitration, the rights and obligations of the parties shall remain in full force ... The Dynamic Parameters of each Unit and the Project will initially be those projected in the #HL_S....
under Section 34 of the Arbitration and Conciliation Act, 1996, and the application of Section 73 of the Contract Act in relation ... It held that the delay attributable to NHAI entitled MAPEX to claim damages under Section 73 of the Contract Act. ... Contract Act. ... with the Construction ....
73 of the Contract Act. ... that the scope of review under these sections is limited and not equivalent to full trial - The learned Single Judge upheld the ... of required evidence from the appellant - The burden rests on the claimant to prove both breach and quantifiable loss under Section ... with the #HL_S....
assess what components of a contract are required and what components are not required - Previous experience in execution of EPC ... of bridge over a river - Court is not equipped to assess such requirements - It is not the job of judicial wing of the State to ... Transport Roads and Buildings Department dated - Government accorded administrative sanction for the#HL_END....
EPC Agreement - Railway Station Redevelopment - Delhi Preservation of Trees Act, 1994 - Clause 8.1 and 8.3 of EPC Contract - Sections ... The Court also observed that the termination of the contract was in accordance with the EPC Agreement. ... Issues: The main issues were the delay in #HL_S....
was actuated by malice or malafides – That being so, the prescription of higher standards in the pre-qualification criteria by the ... APGENCO cannot be said to be illegal – Consequential disqualification of the petitioner company by application of such higher standards ... is therefore equally free of illegality – Writ Petition Dismissed (Paras 41, 42) ... The bidder should have executed #HL_STAR....
c) Clause 3.1.7(a) of the EPC Contract casts an obligation on the contractor to make applications before government authorities to obtain necessary permits listed under Schedule F annexed to the EPC Contract. ... 9) You are requested to comply and conform the requirements after Termination as mentioned in Article 23.4 of the Contract Agreement." "13.?? ... under Schedule F to the EPC Agreement. ... Single Judge in the impugned judgment also observed that Section 14(1)....
be getting the dispute referred to arbitrator as per clause 26.3 of the EPC agreement. ... Sharma does not dispute the fact that there is an arbitration mechanism in terms of the EPC Agreement.5. ... By filing a return, respondent Nos. 1 to 3, amongst others, stated that Article 26 of the Engineering Procurement and Construction (EPC Agreement) provides for Dispute Resolution System. ... /agreement executed in favour of the petitioner company and accordingly the agreement/contract awarded to the petitioner company has be....
56: Arbitration • All disputes or differences which may arise between the EPC Consultant and the EPC Contractor/ Contractor in connection with this Contract (other than those in respect of which the decision is expressed in the Contract to be final and binding) shallafterwrittennoticebyeitherpartytotheotherandrequest ... The petitioner was declared as the successful bidder and was subsequently awarded the Contract vide a formal Agreement No.WAP/RD/NIUM/2018/EPC/dated24.07.2018.3. ... o....
Conversely, Clause 13.7 provided for the identical requirements/stipulations as contained in Clause 13.6 except in place of OFC Manufacturer, Clause 13.7 provided EPC Contractor to be the bidder. ... It is further stated that the said amendment was brought to the Tender 2024 without any prior intimation to the bidders thereby altering the eligibility requirements. ... Clause 13.1.1 clearly indicated that the bidder should be either an “EPC Contractor” or an “OFC Manufacturer”, where EPC stands for Engin....
However, for succeeding in the arbitration, it was for MAPEX to show whether under the terms of the sub-contract/EPC contract, the EPC Contractor was entitled to raise a claim of prolongation cost and if at all any such claim had been paid by MAPEX to such EPC Contractor. ... As noted by the Arbitral Tribunal, the contract between MAPEX and EPC Contractor was not placed before the Arbitral Tribunal. ... Therefore, it could not be shown on record whether or not under t....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.