SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2011 Supreme(SC) 786

2011 (9) SCC 354
SUPREME COURT OF INDIA
(ASOK KUMAR GANGULY & SWATANTER KUMAR, JJ.)
M/S. DELHI AIRTECH SERVICES PVT. LTD. & ANR. Appellants
VERSUS
STATE OF U.P. & ANR. Respondents
Civil Appeal No.24 of 2009
Decided on 18-08-2011.

Headnote:A) CONSTITUTION OF INDIA : Art.141, LAND ACQUISITION ACT : S.10, S.11, S.11(a), S.16, S.17, S.17(1), S.17(3)(a), S.23, S.28, S.31(2), S.34, S.4, S.48, S.5, S.6, S.7, S.8, S.9:- This appeal arises out of the non-compliance with the pre-condition laid down under sub-section (3) of Section 17of Land Acquisition Act and the order of the High Court of Allahabad declaring the emergency acquisition as unsustainable. Due to the divergence of opinion between the two judges, the matter was referred to a larger bench.

JUDGMENT

Asok Kumar Ganguly, J.- The facts giving rise to the present appeal are simple and fall within a narrow compass. However, they raise questions which are of public importance and legal significance. Thus, it will be appropriate for us to state the questions of law at the very threshold:

A. When the Government, in exercise of its emergency powers under Section 17 of the Land Acquisition Act, 1894 (for short the `Act') acquires lands, which have since vested in the State, can such an acquisition proceeding lapse and consequently the land can be transferred to the owners/persons interested in the event of default by the State, in complying with the provisions of Section 11A of the Act? B. Whether the provisions of Section 17(3A) of the Act are mandatory or directory? In either event, would non-compliance with this Section have the effect of invalidating or vitiating the entire acquisition proceedings, even where the land has vested in the State in terms of Section 17(1) of the Act? C. Whether with the invoking of the emergency provisions which have the effect of dispensing with the provision of hearing under Section 5A of the Act, the Court is entitled to construe the emergency provisions strictly, being drastic provisions in an exproprietory law and consider the safeguards inbuilt in Section 17(3A) against such drastic provisions as conditions precedent and mandatory for a valid exercise of emergency provisions.

D. Whether having regard to the principle of reasonableness being a basic component of fundamental rights under the Constitution, this Court has to construe the provisions of the said Act, a pre-constitutional law in consonance with reason and justice-the fundamental tenets of Article 14 and thus arrive at a balanced interpretation of the interest of the State as against the rights of citizens or land owners.

FACTS:

2. The appellant No.1 is a company duly incorporated under the provisions of the Indian Companies Act, 1956 and is alleged to be the owner of the land sought to be acquired by the respondents. The appellant's land, admeasuring about 2-06-1/3-0 Bighas situated in Village Haldauni, Tehsil and Pargana Dadri, District Gautam Budh Nagar which is abadi land, was sought to be acquired by the appropriate Government under a notification dated 17th April, 2002 issued under Section 4(1) read with Sections 17(1) and 17(4) of the Act. This land was acquired for the planned industrial development in District Gautam Budh Nagar through the New Okhla Industrial Development Authority (NOIDA). The notification also stated that the provisions of Section 5A of the Act shall not apply. In pursuance to the said notification, a declaration under Section 6 of the Act was published on 22nd August, 2002, declaring the area which was required by the Government. It also stated that after expiry of 15 days from the date of the publication of the notification under sub-section (1) of Section 9 of the Act, possession of the acquired land shall be taken. The appellants have alleged that they did not receive any notice under Section 9(1) of the Act but possession of the land was nevertheless taken on 4th February, 2003. According to the appellants, even after a lapse of more than three and a half years after the declaration under Section 6 of the Act, no award had been made and published.

3. The appellants further alleged that, despite inordinate delay, they were neither paid 80 per cent of the estimated compensation in terms of Section 17(3A) of the Act at the time of taking of possession, nor had the Collector passed an award within two years of making the declaration under Section 17(1), as required by Section 11A of the Act. It was the case of the appellants that this has the effect of vitiating the entire acquisition proceedings. Non-payment of compensation and conduct of the Government compelled the appellants to file a writ petition in the High Court of Allahabad praying for issuance of an order or direction in the nature of ce






















































































































































































































































































Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top