SUPREME COURT OF INDIA
R. F. Nariman, Indu Malhotra, JJ.
RELIANCE CELLULOSE PRODUCTS LTD. – APPELLANT
VERSUS
OIL AND NATURAL GAS CORPORATION LTD – RESPONDENT
CIVIL APPEAL NO.1110 of 2010
WITH
OIL AND NATURAL GAS CORPORATION LTD. – APPELLANT
VERSUS
RELIANCE CELLULOSE PRODUCTS LTD. – RESPONDENT
CIVIL APPEAL NO.1111 of 2010
Decided On : 20-07-2018
(2017) 14 SCC 323; (2012) 12 SCC 10; (2016) 6 SCC 36 – Relied upon
(1992) 1 SCC 508; (1988) 1 SCC 418; (2001) 2 SCC 721; (1996) 1 SCC 516; (2005) 6 SCC 462; (2008) 8 SCC 251; (2009) 12 SCC 1; (2009) 16 SCC 504; (2010) 1 SCC 549; (1999) 1 SCC 63; (2010) 8 SCC 767; (2011) 7 SCC 279; (2015) 9 SCC 695; Civil Appeal Nos. 5964- 5965 of 2018 – Referred
Facts of the case:
The present appeals relate to questions which arise qua the pre-reference and pendente lite interest under the Arbitration Act, 1940. The ONGC floated a notice inviting tender for the supply of 1200 Metric Tons of Sodium Carboxyl Methyl Cellulose. Reliance Cellulose Products Ltd. submitted its tender quoting a price of Rs. 14,999/- per MT for quantities above 900 MT. It is not disputed that the offer of Reliance was accepted for the supply of 1200 MT of CMC, and accordingly, a supply order dated 01.12.1988 was placed on Reliance. Since Reliance agreed to supply 1200 MT only if the price is higher than Rs. 14,999/- per MT, the parties ultimately went to arbitration in order to decide what should be the contract price for supply of 1200 MT of CMC. A separate order, referred to as the repeat order, was also placed for supply of 600 MT of CMC. The supply was made on time and payments were received for both contracts at the rate of Rs. 14,999/- per MT.
The petitioner filed a Special Civil Application before the Gujarat High Court which referred the disputes between the parties to arbitration, which were with regard to the price for the supply of 1200 MT and 600 MT of CMC respectively.
The Arbitrators fixed the price of 1200 MT at Rs. 18,500/- per MT, and Rs. 20,500/- per MT insofar as 600 MT of CMC was concerned. The Arbitrators awarded pre-reference, pendente lite and future interest all at the rate of 18% per annum.
The Civil Judge rejected these objections of ONGC but ultimately reduced the interest for all three periods to 10% per annum. This interest was payable on the difference between Rs. 14,999/- and Rs. 18,500/- and Rs. 20,500/- respectively.
The appeals filed before the High Court were dismissed.
Finding of the Court:
In absence of express bar in the contract, arbitrator could award pre-reference, pendente lite and future interest under 1940 Act.
Being a PSU is not a ground to reduce rate of interest awarded by the arbitrator.
Result: Appeal of ONGC dismissed and the appeal of Reliance allowed.
JUDGMENT
R.F. NARIMAN, J.
The present appeals relate to questions which arise qua the prereference and pendente lite interest under the Arbitration Act, 1940. The ONGC floated a notice inviting tender for the supply of 1200 Metric Tons (hereinafter referred to as "MT") of Sodium Carboxyl Methyl Cellulose (hereinafter referred to as "CMC"). Reliance Cellulose Products Ltd. (hereinafter referred to as "Reliance") submitted its tender quoting a price of Rs. 14,999/- per MT for quantities above 900 MT. It is not disputed that the offer of Reliance was accepted for the supply of 1200 MT of CMC, and accordingly, a supply order dated 01.12.1988 was placed on Reliance. Since Reliance agreed to supply 1200 MT only if the price is higher than Rs. 14,999/- per MT, the parties ultimately went to arbitration in order to decide what should be the contract price for supply of 1200 MT of CMC. A separate order, referred to as the repeat order, was also placed for supply of 600 MT of CMC. It is undisputed that the supply was made on time and payments were received for both contracts at the rate of Rs. 14,999/- per MT.
2. In October 1990, the petitioner filed a Special Civil Application before the Gujarat High Court in the course of which, by an order dated 11.10.1990, the disputes between the parties were referred to arbitration, which were with regard to the price for the supply of 1200 MT and 600 MT of CMC respectively. The original Arbitral Tribunal consisted of Justice V.S. Deshpande and Mr. S. Tibrewal. Shri Deshpande having died, Justice B.J. Divan was appointed in his place.
3. By an award dated 29.12.1993, the Arbitrators fixed the price of 1200 MT at Rs. 18,500/- per MT, and Rs. 20,500/- per MT insofar as 600 MT of CMC was concerned. The Arbitrators awarded pre-reference, pendente lite and future interest all at the rate of 18% per annum. Objections were filed to the award by the ONGC. The learned Civil Judge, by his judgment dated 30.07.1998, rejected these objections, but ultimately reduced the interest for all three periods to 10% per annum. Needless to state, this interest was payable on the difference between Rs. 14,999/- and Rs. 18,500/- and Rs. 20,500/- respectively. The appeals that were filed to the High Court yielded the same result vide the impugned judgment dated 23.08.2006. Both parties are in appeal before us.
4. Shri K.V. Viswanathan, who argued Civil Appeal No.1110/2010, has argued before us that no good reason is given for reducing interest from 18% to 10%. Indeed, the only reason that is forthcoming from the impugned judgment is that interest has been reduced because ONGC is a Public Sector Undertaking. According to him, therefore, pre-reference, pendente lite and future interest at 18% all become payable from the date of the cause of action till 21.01.1999, when the ONGC had deposited an amount of Rs. 1,09,34,323/-, and an amount of Rs. 46,86,138/- on 30.04.2003, on account of principal and interest at the rate of 10% per annum, and differential interest till date.
5. In the ONGC appeal, the learned Additional Solicitor General, Shri Sandeep Sethi, has argued that though the plea that no pre-reference or pendente lite interest was payable, there is an express bar to the grant of such interest between the parties, which was noted by both the learned Civil Judge and the High Court, but no finding has been given thereon. According to the learned ASG, clause 16 of the General Conditions of Contract clearly bars payment of interest for any delay and is set out hereinbelow:
"16. Our standard terms of payment are within 30 days of receipt of stores and inspection at site. But any delay in payment will not make the Commission liable for any interest."
6. He has cited a number of judgments to buttress his submission that clause 16 would amount to a contractual bar to the payment of any interest on the facts of this case. On the other hand, Shri Viswanathan has also referred to various judgments. His argument is that clause 16 does
Irrigation Department, State of Orissa v. G.C. Roy
Executive Engineer (Irrigation), Balimela v. Abhaduta Jena
Executive Engineer, Dhenkanal Minor Irrigation Division, Orissa v. N.C. Budharaj
Board of Trustees for the Port of Calcutta v. Engineers-De- Space-Age
Bhagwati Oxygen Ltd. v. Hindustan Copper Ltd.
State of Rajasthan v. M/s. Ferro Concrete Construction (P) Ltd.
Union of India v. Saraswat Trading Agency
Madnani Construction Corporation (P) Ltd. v. Union of India
State of U.P. v. Harish Chandra and Co.
Sree Kamatchi Amman Constructions v. The Divisional Railway Manager (Works), Palghat
Tehri Hydro Development Corporation Ltd. v. Jai Prakash Associates Ltd.
Union of India v. Bright Power Projects (India) (P) Ltd.
Union of India v. Ambica Construction ("First Ambica Construction Case")
Ambica Construction v. Union of India ("Second Ambica Construction Case")
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.