SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2021 Supreme(SC) 342

SUPREME COURT OF INDIA
R.F. NARIMAN, B.R. GAVAI, HRISHIKESH ROY, JJ.
PRAVIN ELECTRICALS PVT. LTD. - APPELLANT
VERSUS
GALAXY INFRA AND ENGINEERING PVT. LTD. - RESPONDENT
CIVIL APPEAL NO. 825 OF 2021 (@ SPECIAL LEAVE PETITION (CIVIL) NO.8718 OF 2020)
DECIDED ON : 08-03-2021

Headnote:

Constitution of India, 1950 - Article 14 - Arbitration and Conciliation Act, 1996 - Sections 11(6), 7(3) , 7(4) , sub-section (4) or sub-section (5) or sub-section (6) , 16 , 11(6-A) , 45 , 8 and 11 - Demand-cum-legal notice - Execution of a Scheme - Alleged that Appellant sent an email Respondent with a draft agreement attached for comments and confirmation - On same day, Respondent sent its reply stating that certain terms were not acceptable - In emails that have surfaced for first time in this Court - Respondent argued that, in point of fact, all differences between parties were ironed out and a Final Consultancy Agreement was agreed upon through correspondence between parties - Alleged that it had raised an invoice payment as an advance for consultancy charges including service tax - It is important to note that said invoice was addressed Construction and Technical Services and makes reference to an agreement entered into between Respondent and Process - Alleged that it raised yet another invoice on the Appellant - Invoice was also addressed to Process and makes reference to an agreement between Respondent and Process - Ledger accounts that were produced in normal course of business by Respondent reflects transactions with Process and not the Appellant - Held, Deeper consideration of whether an arbitration agreement exists between parties must be left to an Arbitrator who is to examine documentary evidence produced before him in detail after witnesses are cross-examined on the same - For all these reasons set aside the impugned judgment of Delhi High Court in so far as it conclusively finds that there is an Arbitration Agreement between parties – Court uphold ultimate order appointing Justice retired Delhi High Court Judge as a Sole Arbitrator - Learned Judge will first determine as a preliminary issue as to whether an Arbitration Agreement exists between the parties, and go on to decide the merits of the case only if it is first found that such an agreement exists - It is clarified that all issues will be decided without being influenced by the observations made by this court - Appeal is allowed.

JUDGMENT :

R.F. Nariman, J.

1. Leave granted.

2. This appeal arises out of a petition filed under Section 11(6) of the Arbitration and Conciliation Act, 1996, for appointment of a Sole Arbitrator for adjudication of disputes between the parties. The Respondent, Galaxy Infra and Engineering Pvt. Ltd., is a company incorporated under the provisions of the Companies Act, 1956, having its registered office at Village Arra Gadh, Post Office Dharhara, Dist. Vaishali, P.S. Hajipur, Bihar and is in the business of providing consultancy services. The Appellant, Pravin Electricals Pvt. Ltd., operates in key industrial and commercial retail sectors and provides services for electrical supplies etc.

3. On 26th May, 2014, an online tender was invited by Chief Engineer, South Bihar Power Distribution Company Ltd. (hereinafter referred to as “SBPDCL”) for appointment of implementing agencies for execution of a Scheme, on turnkey basis, for strengthening, improvement and augmentation of distribution systems capacities of 20 towns in Bihar. The Appellant submitted its technical and financial bid and was declared the L1 bidder and was awarded the work on 22nd September, 2014. It is the case of the Respondent that it had made substantial efforts under a Consultancy Agreement dated 7th July, 2014, to facilitate the Appellant in getting the aforesaid contract for which it was entitled to commission. It is then alleged that the Appellant sent an email dated 15th July, 2014 to the Respondent with a draft agreement attached for comments and confirmation. On the same day, the Respondent sent its reply stating that certain terms were not acceptable. In emails that have surfaced for the first time in this Court dated 22nd July, 2014 and 25th July, 2014, the Respondent argued that, in point of fact, all differences between the parties were ironed out and a Final Consultancy Agreement was agreed upon through correspondence between the parties.

4. The Respondent alleged that it had raised an invoice on 27th September, 2014, for payment of Rs.28.09 lakhs as an advance for consultancy charges including service tax. It is important to note that the said invoice was addressed to one M/s Process Construction and Technical Services Pvt. Ltd. (hereinafter referred to as “Process”) and makes reference to an agreement entered into between the Respondent and Process. Also, on 24th April, 2016, the Respondent alleged that it raised yet another invoice on the Appellant. This invoice was also addressed to Process and makes reference to an agreement between the Respondent and Process. Ledger accounts that were produced in the normal course of business by the Respondent reflects transactions with Process and not the Appellant. Finally, vide an email dated 30th June, 2017, the Respondent attached the final invoice to the Appellant claiming an amount of Rs.5.54 crores under the alleged Consultancy Agreement dated 7th July, 2014.

This was followed up by a demand-cum-legal notice dated 9th March, 2018, seeking payment of Rs.5,54,14,318/-from the Appellant as being due under the alleged Consultancy Agreement dated 7th July, 2014. Vide its reply dated 22nd March, 2018, the Appellant recorded its surprise on receiving such demand notice and flatly denied that any agreement dated 7th July, 2014, was ever entered into between the parties. The Appellant further requested the Respondent to provide a copy of the alleged Agreement dated 7th July, 2014 and payment details referred to in the legal notice.

5. On 26th April, 2018, the Respondent invoked Article 14 of the alleged Consultancy Agreement dated 7th July, 2014, in which they nominated one Kameshwar Choudhary as Sole Arbitrator to adjudicate differences between the parties. On 3rd May, 2018, the Appellant denied execution of the Agreement dated 7th July, 2014 and, therefore, stated that the matter could not be referred to arbitration. We are informed that on 14th May, 2018, the Respondent’s Advocates finally supplied a copy of the all

      Click Here to Read the rest of this document
      1
      2
      3
      4
      5
      6
      7
      8
      9
      10
      11
      SupremeToday Portrait Ad
      supreme today icon
      logo-black

      An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

      Please visit our Training & Support
      Center or Contact Us for assistance

      qr

      Scan Me!

      India’s Legal research and Law Firm App, Download now!

      For Daily Legal Updates, Join us on :

      whatsapp-icon telegram-icon
      whatsapp-icon Back to top