SUPREME COURT OF INDIA
SANJAY KISHAN KAUL, S. RAVINDRA BHAT, M.M. SUNDRESH, JJ.
Gujarat Urja Vikas Nigam Limited and Others – Appellants
Versus
Renew Wind Energy (Rajkot) Private Limited and Others – Respondents
Civil Appeal Nos. 3480-3481 of 2020
Decided On : 13-04-2023
| Table of Content |
|---|
| 1. challenge orders under electricity act (Para 1 , 2) |
| 2. regulatory framework for power procurement (Para 3 , 4 , 5 , 6 , 9) |
| 3. jurisdiction of state commission over ppa (Para 14 , 15 , 16 , 17 , 18) |
| 4. dynamic nature of appc and rec pricing (Para 26 , 27 , 28 , 29 , 30) |
| 5. applicability of regulatory amendments to existing contracts (Para 60 , 61 , 62) |
| 6. requirements for proving coercion in contracts (Para 66 , 67 , 68 , 69 , 70) |
| 7. court's conclusion on appeals (Para 72) |
JUDGMENT :
S. RAVINDRA BHAT, J.
1. The current civil appeals1 [Civil Appeals Nos. 3480 and 3481 of 2020] under Section 125 of the ELECTRICITY ACT , 2003, (hereafter, “the Act”) challenge orders of the Appellate Tribunal for Electricity (hereafter “APTEL”) dated 06.12.2018 (“first impugned order”)2 [in Appeal No. 209/2015] and order dated 24.07.2020 (“second impugned order”)3 [in Review Petition No. 03/2019]. The APTEL had, by those orders, rejected the appeals preferred by the present appellant, and the review petition, as well. Resultantly, the order of the Gujarat Electricity Regulatory Commission (hereafter “the State Commission”) dated 01.07.20154 [in petition No. 1363/2013] was affirmed.
2. The first appellant-Gujarat Urja Vikas Nigam Limited (hereafter “Gujarat Urja”) had approached this court previously challenging the order of APTEL, which was disposed of by this court5 [Civil Appeal No. 1253/2019 by order dated 15.02.2019] granting liberty to it, to seek review/rectification. Gujarat Urja then preferred a review petition, which was rejected by APTEL, by the second impugned order. When this appeal was taken up for hearing, on 14.10.2020, this court had issued notice and stayed the impugned order of APTEL.
Background
3. Gujarat Urja procures power in bulk on behalf of distribution licensees in the state of Gujarat; it is an authorized licensee within the meaning of the term under the Act. The second, third, fourth and fifth appellants are distribution licensees in the State of Gujarat. The first respondent, Renew Wind Energy (Rajkot) Pvt. Ltd. (hereafter “RWE”) is a wind generator which had set up 25.2 MW Wind Turbine Generators at District Rajkot, Gujarat under the Renewable Energy Certification scheme notified by the Central Electricity Regulatory Commission (hereafter, “Central Commission”). The second respondent is the Wind Independent Power Producers Association (hereafter “Association”). The Respondent No 3, Gujarat Electricity Regulatory Commission (hereinafter “the State Commission”) is the regulatory commission under the Act, for the State of Gujarat. The fourth respondent, Wish Wind Infrastructure LLP (“Wish Wind” hereafter) is a wind generator.
4. By Section 86 of the Act6 [The relevant extract of Section 86 is as follows: 86. Functions of State Commission: (1) The State Commission shall discharge the following functions, namely: (a) determine the tariff for generation, supply, transmission and wheeling of electricity, wholesale, bulk or retail, as the case may be, within the State. (b) regulate electricity purchase and procurement process of distribution licensees including the price at which electricity shall be procured from the generating companies or licensees or from other sources through agreements for purchase of power for distribution and supply within the State; (c) facilitate intra-State transmission and wheeling of electricity....(e) promote co-generation and generation of electricity from renewable sources of energy by providing suitable measures for connectivity with the grid and sale of electricity to any person, and also specify, for purchase of electricity from such sources, a percentage of the total consumption of electricity in the area of a distribution licensee....] State Commissions discharge several functions - which include the determination of tariff “for generation, supply, transmission and wheeling of e
Point of law: since Merit Order Despatch does not apply to renewable energy, which runs on Must Run Basis, the learned single Judge has not committed any illegality in directing that the respondents ....
Tariff determination for hydro projects with enhanced capacity, binding nature of prior PPAs on successors, and writ jurisdiction limited; exclusive domain of regulatory commission, not courts, to fi....
Power purchase agreements must be aligned with regulatory frameworks and cannot be enforced if unapproved, particularly regarding classifications impacting fixed charges.
The court clarified that Section 63 of the Electricity Act allows local authorities to apply for tariff adoption, rejecting the APTEL's restrictive interpretation.
The court affirmed that power producers can determine tariffs based on their depreciation benefit status, rejecting the imposition of rates for those availing accelerated depreciation on entities not....
Tariff modifications in power purchase agreements must comply with regulatory approvals as per Section 86(1)(b) of the Act, ensuring valid determination of electricity purchase prices.
Point of Law : Section 61 of Electricity Act, 2003 deals with tariff regulations and it empowers Regulatory Commission to specify terms and conditions for determination of tariff.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.