SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(HP) 484

IN THE HIGH COURT OF HIMACHAL PRADESH, SHIMLA
G.S. Sandhawalia, C.J., Jiya Lal Bhardwaj, J.
Himachal Pradesh Electricity Board Ltd. - Appellant
Versus
Kundan Hydro (Luni) Pvt. Ltd. & another - Respondents
LPA No. 492 of 2024
Decided On : 09-01-2026

Advocates Appeared:
For the Appellant :Mr. Anand K. Ganesan, Advocate (through V.C.) with Mr. Shivom Vashista and Ms. Shivani Verma, Advocate.
For the Respondent:Mr. Prithu Garg and Mr. Vaibhav Chauhan, Advocates, Mr. Pranay Pratap Singh, Additional Advocate General

Tariff determination for hydro projects with enhanced capacity, binding nature of prior PPAs on successors, and writ jurisdiction limited; exclusive domain of regulatory commission, not courts, to fix composite tariffs per regulations.

Headnote:(A) Electricity Act, 2003 - Sections 86(1)(a) & (b) - HPERC (Promotion of Generation from Renewable Energy Sources and Terms & Conditions for Tariff Determination) Regulations, 2017 - Regulation 17(3) - Power Purchase Agreement executed in 2000 at fixed tariff of Rs.2.50/kWh for 3 MW hydro project - Subsequent transfers via tripartite and supplementary implementation agreements, capacity enhancement to 4.50 MW, and change in management post-insolvency - Successor developer bound by original agreements and obligations as per transfer clauses unequivocally accepting all assets, liabilities, privileges - Tariff for original capacity governed by 2000 PPA; for additional capacity by 2017 Regulations; composite tariff to be worked out on normative basis - Determination of tariff, including price at which electricity procured from generating companies, exclusive domain of State Commission - Writ court cannot direct execution of fresh PPA for entire enhanced capacity at tariff applicable on scheduled commercial operation date under 2017 Regulations, bypassing regulatory process - Action of distribution licensee in insisting on supplementary PPA reflecting original terms not arbitrary; parties to approach Commission via joint petition. (Paras 28, 31, 35, 36)

(B) Constitution of India - Article 226 - Writ jurisdiction - Alternative remedy - Exhaustive code under Electricity Act, 2003 - Issues of tariff fixation, PPA approval not to be entertained directly; expert regulatory bodies to adjudicate - No manifest arbitrariness warranting interference. (Paras 21, 36, 37)

Facts of the case:
Hydro power project allotted in 2000 with implementation agreement and separate PPA for 3 MW at Rs.2.50/kWh. Transferred to new entity via tripartite agreement in 2004 binding it to original terms; supplementary implementation agreement in 2008 for enhanced 4.50 MW capacity; insolvency led to management change approved by tribunal in 2022, new supplementary agreement in 2024. On request for fresh PPA, licensee directed supplementary PPA maintaining original tariff for 3 MW per Regulation 17(3), composite for enhanced capacity. Writ petition allowed by Single Judge quashing direction and ordering new PPA at 2017 Regulations tariff; Letters Patent Appeal thereagainst.

Findings of Court:
Judgment of Single Judge set aside; parties relegated to file joint petition before Regulatory Commission for tariff determination keeping in view project delay since 2000.

Issues: Whether original PPA binding on successors; maintainability of writ bypassing alternative remedy; entitlement to fresh PPA at current tariff for entire capacity; applicability of capacity enhancement Regulation 17(3).

Ratio Decidendi: Successors unequivocally accepted all prior obligations via transfer agreements; tariff fixation specialized function of Commission per Sections 86(1)(a),(b); writ court cannot re-fix contract terms or usurp regulatory domain, especially absent arbitrariness. Result : Appeal allowed.

Table of Content
1. single judge quashed old ppa as non-binding on petitioner (Para 1 , 2 , 3 , 4 , 5 , 6)
2. project transferred via tripartite agreements and insolvency resolution (Para 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17 , 18)
3. dispute over binding tariff from 2000 ppa (Para 19 , 20)
4. writ jurisdiction limited; tariff for regulatory commission (Para 21 , 22)
5. new ppa mandated at current hperc tariffs (Para 23 , 24 , 25 , 26)
6. successors bound by original ppa through assignments (Para 27 , 28 , 29 , 30 , 31 , 32 , 33 , 34 , 35)
7. tariff fixation exclusive domain of hperc (Para 36 , 37 , 38 , 39 , 40)
8. appeal allowed; relegate parties to hperc (Para 41 , 42)

JUDGMENT :

G.S. Sandhawalia, C.J.

Challenge by the appellant-Himachal Pradesh State Electricity Board Ltd. (hereinafter referred to as ‘the appellant-Board’) in the instant Letters Patent Appeal, is to the judgment dated 10.09.2024, rendered by the learned Single Judge in CWP No.7177 of 2024, titled Kundan Hydro (Luni) Private Limited vs. State of Himachal Pradesh through its Addl. Chief Secretary (MPP & Power) & anr., whereby the writ petition filed by the petitioner-Kundan Hydro (Luni) Private Ltd-respondent No.1 herein has been allowed by quashing impugned communication dated 16.07.2024 (Annexure P-13) holding the Power Purchase Agreement (for short the "PPA") dated 31.05.2000 executed between appellant-Board and "SPML” not binding upon it being unenforceable against it. The appellant-Board was directed to execute a "PPA" with the writ petitioner-Power Company in respect of the entire Project capacity of 4.50 MW at the "HPERC Regulations- 2017" determined tariff applicable as on Scheduled Commercial Operation Date of the Project in accordance with law and complete all codal formalities in furtherance thereof without unnecessary delay. In order to avoid loss of electricity generated at the Project, it was ordered that till the determination of tariff as on the date of commissioning of the Project by the "HPERC Regulations-2017" in terms of direction supra, the petitioner-Hydro Company was permitted by the respondents to sell the electricity generated from its Power Project to third parties after adjusting the free power supply to the respondents in accordance with law.

Reasoning of the learned Single Judge:

2. The learned Single Judge had allowed the writ petition primarily on the ground that the "PPA" dated 31.05.2000 (Annexure P-14) had been executed between the Board and "SPML” and therefore was not binding upon the petitioner and could not be enforced. The necessary directions thus came to be issued to execute the "PPA" in respect to the entire Project capacity of 4.50 MW at the HPERC (Promotion of Generation from Renewable Energy Sources and Terms & Conditions for Tariff Determination) Regulations, 2017 as on Scheduled Commercial Operation Date. It was further directed that the determination of tariff shall be as on the date of commissioning of the Project by the "HPERC Regulations-2017" in terms of direction No.(iii), the petitioner was permitted by the respondents to sell the electricity generated from its Power Project to third parties after adjusting the free power supply to the respondents in accordance with law.

3. Principally, the reasons which weighed with the learned Single Judge were that both the Implementation Agreement (IA) and the "PPA" dated 31.05.2000 for the 3.00 MW was an agreement which provided specific terms for execution of separate Agreement for purchase of power generated which was to be done within three months. The petitioner-Company was not a party to the said Agreement and the assignment could only be done as per Article 15.10 by written Agreement and the petitioner was not a successor to be bound by it and therefore have come into the picture only later on 25.09.2004 (Annexure P-3) by virtue of Tripatite Agreement executed by "SPML” and respondent No.1-State. The separate "PPA" was required to be executed which was not done a

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top